Narail

LGED Narail Menu
LGED, Narail
Local Government Engineering Department (LGED)
Bidhan Chandra Somadder, Executive Engineer, Executive Engineer Office LGED, Narail.
Narail 7500, Bangladesh.
Contact No:0481-62331

Achievements

LGED-Narail Achievement

 List of few important Projects/scheme`s name given bellow : 

1 Construction of Lahuria - Kaligonj bazar Mithapur via Charbalidia Road                                                       

2 Constuction of Server Station at lohagara & Kalia Upazila.      

3 Improvement of Gabtala R&H - Maizpara GC Road by BC.   

4 Improvement of Lohagara-Radhanagar via Itna Bazar by BC.        

5 Improvement of Peroli Bazar-Khororia Bazar by BC.

6. Narail  PTI Complex Bhaban

7.  Construction of Jatio Mahila Sangistha Zila Complex

8. Construction of Sheikh Rasel Bridge 140m Long

9. Construction of 175m long PC Girder Bridge on Arenda (Kashipur UP) –Manikgonj Bazar Road

10. Development of 102Km Road Under Important Rural Infrastructure Development Project-2 (IRIDP-2)

11. Development of 57Km Road Under Khulna Division Rural Infrastructures Development Project (KDRIDP)

12. Development of 107Km Road Under Greater Jashore Infrastructures Development Project (GJP)

13. Development of 6Km Road Under Improtant Rural Infrastructures Development Project (DRIDP)

14. Development of 24Km Road Flood & Disaster Damaged Rural Road Infrastructure Rehabilitation Project (FDDRIRP)

15. Construction of 6 Nos Union Land Office (TULO)

16. Construction of 3Nos Upazila Muktijoddha Complex (CUMCP)

17. 62Nos  Mosque,Mondir, GraveYeard, Sawshan & Eidgah Development  under GSIDP

18. Construction of  38 Nos Housing for Landless & Under privileged Muktijoddhas Project

Moreover road & bridge maintenance activities are going on smoothly on different roads to Keep the roads & bridges well.  

sheikh Rasel Bridge

Synopsis of Sheikh Rasel Bridge:
140m Long PC Girder Bridge over Chitra River.
Estimated Cost:-2663.54 Lac
Contract Amount: 2913.96 Lac
Payment Amount : 2911.00 Lac
Total Span a) 3Nos@33m=99m
                b) 2Nos@21m=42m
Viaduct Span: 17Nos@14m=238m
 Total Length with Viaduct=379m
Approach Road Length 1248m
Bi-pass Road Length 572m
Approach Retaining Wall =120m
Electric Light Post=28 Nos
Vertical Nevegation Clearance=7.207m
Horizental Clearance =33m
Work Start Date=30.04.2015
Actual Date of Work Completion=20.06.2017

LGED-Narail Achievement

  • Implemented some remarkable roads & bridges at Narail district under various RuralDevelopment Projects underLGED
       SADAR UPAZILA                          
  • Complete Maintenance activity of Narail -Maizpara road under Sadar upazila.(8.00 km). FY 2012-13 &2014-15.
  • Complete Maintenance activity of Gobra-Vatpara road ( 12.99 kmunder Sadar upazila.FY 2013-14 &2014-15.
        LOHAGARA UPAZILA
  • Complete Maintenance activity of Lohagara bazar-Siarbar hat road .(12.00 km).FY 2013-14 &2014-15.

  • 160m Bridge over Naboganga river at Mithapur - Hobokhali road.

  • 86m Bridge over Naboganga river near Arenda bazar.
           KALIA UPAZILA        
  • 168m Bridge at Ragunathpur ghat on kalia- Nowapara road        


  • Tularampur- Shaikhati road ( 12.00km) 
  • Kalia -Jogania road (17.22km)
  • Kalia -Majirgati road ( 7.67km)
  • Jogaina-Bordia road (12.15km) 
  • Purulia-Khororia bazar road ( 7.11 km)                                                                   
  • Chapoilghat - Sachiadah bazarroad(6.5km)  
  • Laksmipasa-Mohajon road ( 13.62km)
  • Siarbar GC.-Mithapur GC (10.00km)    
  • Gobra -Singasolpur road (5.6km)  
  • Narail Shaikhati-via Mulia road ( 15.30km)
  • Gorerhat - Maizpara road ( 3.33km)
  • Maizpara - Uttar Singa road ( 6.00km) 
Narail At a Glance
Area: 990km2
Upazila Road: 206.6 km
Union Road: 232.03Km
Village Road: 662.18Km VA
2124.29Km VB
Population: 721668
Density: 746 Nos / sq.kmKm2
Literacy: 61.30%
No. of Upazila: 3
No. of Union: 38
No. of Pourashava: 3
No. of Primary School: 442
No. of High School: 126
No. of College: 26
Procurment, Narail