Joypurhat

LGED JOYPURHAT , District Scheme Details

Project Name
Upazila

District Scheme Details

SL No. Package No. Package Name Project Name Upazila Name Road ID Length of Road (Km) Length of Bridge (M) Building Qauntity (No) Estimated Amount (Lac) Name of Contractor Contract Amount (Lac) Date of Contract Date of Commencement Date of Completion Physical Progress (%) Financial Progress (Amt) Financial Progress (%) Date of Progress Update Remarks
1 CRMIDP/JYP/W-73 Raikali Hat CRMIDP akkelpur 16 335.00 M/S Mondol Traders Chalkbaria, Dist.- Naogaon. 264.79 09/03/2020 29/06/2022 30 43.06 16 21/07/2022
2 CRMIDP/JYP/W-72 Puranpeilo Bazar CRMIDP joypurhat-s 69 370.00 Md.Selim Reza 306.54 11/05/2020 07/02/2022 15/10/2022 85 212.40 69 21/07/2022
3 CRMIDP/JYP/W-74 Harunja Hat CRMIDP kalai 19 212.00 M/S Mondol Traders Chalkbaria, Naogaon. 174.21 09/03/2020 30/12/2021 09/09/2022 25 33.00 19 21/07/2022
4 CRMIDP/JYP/W-75 Lalagor Hat CRMIDP khetlal 15 336.00 M/S Mondol Traders Chalkbaria, Naogaon 268.82 02/04/2020 26/06/2022 30 40.00 15 21/07/2022
5 CRMIDP/JYP/W-76 Feska ghat Hat CRMIDP panchbibi 40 342.00 Md.Saydul Islam 273.54 29/10/2020 17/10/2021 15/09/2022 75 109.04 40 21/07/2022
6 GPBRIDP/Rd-469 Improvement of Sonamukhi Hat-Gopinathpur UP Office via Vnurkanda Road ch.2482m-3500m GPBRIDP akkelpur   1.02 0.00 100 52.91 M/S Rina Enterprise Akkelpur, Joypurhat. 51.98 01/01/1900 22/03/2016 02/12/2016 100 51.98 100 30/06/2020 Final
7 GPBRIDP/Rd-470 Improvement of Tilokpur UP Office-Sujaldighi Hat Via Marma Road ch.2270m-3270m GPBRIDP akkelpur 138133004 1.00 0.00 100 54.01 M/S Kazol Enterprise Akkelpur, Joypurhat. 53.49 01/01/1900 25/05/2016 23/12/2017 100 53.49 100 30/06/2020 Final
8 GPBRIDP/Rd-471 Improvement of Mohonpur Hat-Sonamukhi UP Via Koya Village Road ch.1655m-2655m GPBRIDP akkelpur 138133007 1.00 0.00 100 55.38 M/S Mondal Traders Chalkbaria,Naogoan. 55.37 01/01/1900 30/03/2016 25/02/2018 100 55.37 100 30/06/2020 Final
9 GPBRIDP/Rd-472 Improvement of Raikali UP Office-Horisadi Hat Via Pun duria Road 1920m-2990m GPBRIDP akkelpur 138133008 1.07 0.00 100 60.11 M/S Rina Enterprise Akkelpur, Joypurhat. 63.12 01/01/1900 28/06/2016 04/04/2018 100 63.11 100 30/06/2020 Final
10 GPBRIDP/Rd-473 Improvement of Gopinathpur UP Office-Kuranu Hat Via Madertali Ghat Road ch.4500m-5500m GPBRIDP akkelpur   1.00 0.00 100 59.94 M/S Rina Enterprise Akkelpur, Joypurhat. 59.93 01/01/1900 22/03/2016 17/12/2016 100 59.92 100 30/06/2020 Final
11 GPBRIDP/Rd-474 Improvement of Tilokpur UP-Chatiangram Ht Road(Akkelpur Portion)ch.2370m-2746m GPBRIDP akkelpur 138133011 0.38 0.00 100 20.71 M/S Alaya Construction Sultangoanjpara,Goalgary, Bogra 20.54 01/01/1900 28/06/2016 26/02/2018 100 20.53 100 30/06/2020 Final
12 GPBRIDP/Rd-475 Improvement of Vikoni Hat -Sonamukhi UP Office Road ch.575m-1735m GPBRIDP akkelpur 138133013 1.16 0.00 100 62.62 M/S Rina Enterprise Akkelpur, Joypurhat. 63.99 01/01/1900 24/04/2016 26/04/2018 100 63.98 100 30/06/2020 Final
13 GPBRIDP/Rd-478 Improvement of Gopinathpur UP Office (Karitoli)-Raikali UP Office Road ch.1525m-2525m. GPBRIDP akkelpur 138133010 1.00 0.00 100 54.77 Kalicharan Agarwala Old Hospital Road,Joypurhat. 54.65 01/01/1900 27/04/2016 30/10/2017 100 53.98 100 30/06/2020 Final
14 GPBRIDP/Rd-476 Improvement of Sonamukhi UP Office (Simultali More)-Raikali UP Office (Munjia) Road ch.3450m-4550m. GPBRIDP akkelpur 138133005 1.10 0.00 100 58.15 M/S Mondal Traders Chalkbaria,Naogoan. 58.15 01/01/1900 05/05/2016 15/03/2018 100 58.04 100 30/06/2020 Final
15 GPBRIDP/Rd-479 Improvement of Gopinathpur UP Office-Kashira Hat Road ch.1010m-2010m GPBRIDP akkelpur   1.00 0.00 100 57.69 M/S Mondal Traders Chalkbaria,Naogoan. 57.75 01/01/1900 05/05/2016 30/12/2018 100 57.74 100 30/06/2020 Final
16 GPBRIDP/Rd-480 Improvement of Rukindipur UP Office-Bottolihat Road ch.1860m-2860m. GPBRIDP akkelpur 138133014 1.00 0.00 100 61.19 M/S Kazol Enterprise Akkelpur, Joypurhat. 61.07 01/01/1900 26/04/2016 02/11/2016 100 61.06 100 30/06/2020 Final
17 GPBRIDP/Rd-481 Improvement of Tilakpur karamje Noagar Road ch500-1030m Salvage ValueTk. 140149 GPBRIDP akkelpur 138134006 0.53 0.00 100 29.34 M/S Alaya Construction Sultangoanjpara,Goalgary, Bogra 28.43 01/01/1900 21/06/2017 27/06/2018 100 28.43 100 30/06/2020 Final
18 GPBRIDP/Rd-482 Improvement of Kathalbari-Halholia road ch.500-745 & 2025-2280m. GPBRIDP akkelpur 138134012 0.50 0.00 100 26.43 M/S Alaya Construction Sultangoanjpara,Goalgary, Bogra 25.49 01/01/1900 21/06/2017 27/06/2018 100 25.49 100 30/06/2020 Final
19 GPBRIDP/Rd-483 Improvement of Raikali-Debishawal road with link Road ch.1215m-1715m. GPBRIDP akkelpur 138134009 0.50 0.00 100 27.48 M/S Alaya Construction Sultangoanjpara,Goalgary, Bogra 26.67 01/01/1900 06/10/2016 28/02/2018 100 26.67 100 30/06/2020 Final
20 GPBRIDP/Rd-486 Improvement of Akkelpur- Tilokpur Upazila road to Kadoa Kholagari road ch.700-1192m Salvage Value Tk.33963 GPBRIDP akkelpur 138134021 0.49 0.00 100 26.63 M/S Alaya Construction Sultangoanjpara,Goalgary, Bogra 25.38 01/01/1900 21/06/2017 27/06/2018 100 24.79 100 30/06/2020 Final
21 GPBRIDP/Rd-506 Improvement of Tilokpur-Baragram Upazila Road Road to Bamnigram Village Road from ch.00-820m (Salvage Value:BDT.697334.00) GPBRIDP akkelpur   0.82 0.00 100 68.05 M/S Sukra Enterprise Chalk Sutrapur, Badurtola,Bogra. 64.05 01/01/1900 28/12/2017 10/11/2018 100 63.16 100 30/06/2020 Final
22 GPBRIDP/Rd-507 Improvement of Sreerampur Bridge (Gonipur) Holholia Railway Bridge Road from ch.00-1000m GPBRIDP akkelpur 138135097 1.00 0.00 100 56.84 M/S Mondal Traders Chalkbaria,Naogoan. 56.20 01/01/1900 28/12/2017 29/11/2018 100 56.20 100 30/06/2020 Final
23 GPBRIDP/Rd-515 Improvement of Kanupur GPS (Porbari Kanupur Kanda)ch.00m-845m.Salvage value: BDT.712913.00 GPBRIDP akkelpur 138135085 0.85 0.00 100 61.61 M/S Mondal Traders Chalkbaria,Naogoan. 58.41 01/01/1900 06/02/2018 05/02/2019 100 55.52 100 30/06/2020 Final
24 GPBRIDP/Rd-529 Improvement of Akkelpur College hat-Kesobpur Embank ment Road (ch.188-585m) GPBRIDP akkelpur 138134022 0.40 0.00 100 20.73 Md. Mostafizur Rahman Paksi Ishordi,Pabna. 19.70 01/01/1900 20/05/2018 13/08/2018 100 19.70 100 30/06/2020 Final
25 GPBRIDP/Rd-530 (Part-A).Improvement of Kalanja-Ambari road ch.00-1300m.(Salvage Value: BDT.1692260.00) (Part-B).03 Nos U-Drain (625mmx600mm) on the same road at ch. 6m, 205m & 603m,(Part-C).Improvement of Kalanja Community Clinic-house of Mizanur Rahman road ch.00-560m GPBRIDP akkelpur   1.86 0.00 100 108.12 Multifarious Engineers Jolesharitola,Bogra 102.72 01/01/1900 30/05/2018 11/06/2020 100 96.37 100 30/06/2020 Final
26 GPBRIDP/BRG-32 Construction of 42.00 m long RCC girder bridge on Rukindi pur UP office Battala hat road at ch. 5190 m GPBRIDP akkelpur 138133014 42.00 0 0.00 M/S Binoy Chandra Akkelpur,Joypurhat. 171.56 01/01/1900 15/05/2018 30/07/2019 100 170.87 0 30/06/2020  
27 GPBRIDP/BRG-33 Construction of 69m Long Bridge at ch.100m on Lengapir Mazar (Sonamukhi Ghat)-Rajkanda Mallapara Road. GPBRIDP akkelpur 138135032 69.00 100 0.00 M/S Mondal Traders Chalkbaria,Naogoan. 257.94 01/01/1900 28/11/2016 12/02/2020 100 255.65 100 30/06/2020 Final
28 GPBRIDP/Rd-423 Improvement of Khejurtali-Durgadaha Road ch. 4320m-5320m. GPBRIDP joypurhat-s 138472003 1.00 0.00 100 66.65 M/S Jabbar Traders, Nischinta bazar, Kheetlal,Joypurhat. 58.65 01/01/1900 29/03/2016 06/12/2016 100 58.64 100 30/06/2020 Final
29 GPBRIDP/Rd-424 Improvement of Puranapoil-R&H via Tajpur Road ch.1600m-2600m. GPBRIDP joypurhat-s 138472008 1.00 0.00 100 58.66 M/S Khalequzzaman Traders Sadar Road,Joypurhat. 58.56 01/01/1900 24/03/2016 09/10/2016 100 58.55 100 30/06/2020 Final
30 GPBRIDP/Rd-425 Improvement of Joypurhat(Khanjanpur)-Rukindipur via Nurpur Road ch.5850m-7180m. GPBRIDP joypurhat-s 138472011 1.33 0.00 100 75.31 M/S Zaman Bricks Sadar Road,Joypurhat. 75.10 01/01/1900 22/03/2016 18/11/2016 100 75.09 100 30/06/2020 Final
31 GPBRIDP/Rd-426 Improvement of Dogachi UP Office-Jamtali via Dalaher Road ch.1314m-2314m. GPBRIDP joypurhat-s 138473003 1.00 0.00 100 58.16 M/S Zahid Traders Dewanpara,Sadar,Joypurhat. 58.12 01/01/1900 28/03/2016 20/09/2016 100 58.12 100 30/06/2020 Final
32 GPBRIDP/Rd-427 Improvement of Chalkbarkat UP Office-Pagladawan Hat road ch.00-1480m. GPBRIDP joypurhat-s 138473004 1.48 0.00 100 81.09 M/S Azam Builders Bazar goli,Joypurhat sadar. 85.15 01/01/1900 20/04/2016 27/05/2017 100 85.15 100 30/06/2020 Final
33 GPBRIDP/Rd-428 Improvement of Durgadah-Pakarmatha via Mohammad UP road ch.4225-5395m. GPBRIDP joypurhat-s 138473006 1.17 0.00 100 62.56 M/S Zahid Traders Dewanpara,Sadar,Joypurhat. 62.53 01/01/1900 04/07/2017 09/02/2018 100 62.36 100 30/06/2020 Final
34 GPBRIDP/Rd-430 Improvement of Dogachi (Uttor Joypur)-Baguan road ch.750-1250m. GPBRIDP joypurhat-s 138475013 0.50 0.00 100 26.48 M/S Zahid Traders Dewanpara,Sadar,Joypurhat. 29.46 01/01/1900 08/05/2016 30/05/2017 100 29.39 100 30/06/2020 Final
35 GPBRIDP/Rd-431 Improvement of Thiot-Nengapir road ch 00-500m. GPBRIDP joypurhat-s 138474008 0.50 0.00 100 25.04 M/S Haque Nirmata Sadar Road,Joypurhat. 24.96 01/01/1900 30/05/2016 12/11/2017 100 24.89 100 30/06/2020 Final
36 GPBRIDP/Rd-432 Improvement of Kadamtoli-Kallyanpur road ch 00-500m. GPBRIDP joypurhat-s 138474001 0.50 0.00 100 30.70 M/S Haque Nirmata Sadar Road,Joypurhat. 30.60 01/01/1900 30/05/2016 09/11/2017 100 30.58 100 30/06/2020 Final
37 GPBRIDP/Rd-433 Improvement of Shalpara-DharanjeeUP Office Via Koria road ch 1168-2168m. GPBRIDP joypurhat-s 138474027 1.00 0.00 100 27.29 M/S Haque Nirmata Sadar Road,Joypurhat. 27.20 01/01/1900 30/05/2016 07/11/2017 100 27.19 100 30/06/2020 Final
38 GPBRIDP/Rd-434 Improvement of Kadamtali more-Dargaghat-(Koria BOP) road ch 00-500m. GPBRIDP joypurhat-s 138474071 0.50 0.00 100 22.64 M/S Haque Nirmata Sadar Road,Joypurhat. 22.56 01/01/1900 30/05/2016 07/11/2017 100 22.56 100 30/06/2020 Final
39 GPBRIDP/Rd-435 Improvement of Dostopur more-Halloti Govt.Pry. School road ch 00-500m. GPBRIDP joypurhat-s 138475033 0.50 0.00 100 29.69 M/S Haque Nirmata Sadar Road,Joypurhat. 29.65 01/01/1900 30/05/2016 07/11/2017 100 29.28 100 30/06/2020 Final
40 GPBRIDP/Rd-501 Improvement of Helkunda-Halatti Road from ch.00m-1745m. GPBRIDP joypurhat-s 138475037 1.75 0.00 100 89.10 M/S Progoti Nirman East Janier Bagan,Joypurhat. 88.81 01/01/1900 28/12/2017 18/06/2018 100 88.39 100 30/06/2020 Final
41 GPBRIDP/Rd-502 Improvement of Chaksyme-Uttar Joypur Road from ch.00m-1000m, (Salvage value: BDT. 673232.00) GPBRIDP joypurhat-s 138474016 1.00 0.00 100 60.83 M/S Azam Builders Bazar goli,Joypurhat sadar. 57.76 01/01/1900 28/12/2017 18/06/2018 100 57.71 100 30/06/2020 Final
42 GPBRIDP/Rd-503 (a) Improvement of Uttar Joypur-Baguan Road , from ch. 1250-1550m, (b) Improvement of Paschim Dogachi-Pakurtoli Road, from ch. 00-700m, (Salvage Value:BDT.413644.00). GPBRIDP joypurhat-s   1.00 0.00 100 52.70 M/S Mahadi Construction Main Road,C.O.Colony, Joypurhat. 51.93 01/01/1900 28/12/2017 11/04/2018 100 51.09 100 30/06/2020 Final
43 GPBRIDP/Rd-504 Improvement of Salpara GC-Dharanji UP Office via Koria Hat Road from ch.1700-2800m GPBRIDP joypurhat-s 138473008 1.10 0.00 100 63.52 M/S Liton Traders Sadar Road,Joypurhat. 60.10 01/01/1900 28/12/2017 11/06/2018 100 60.09 100 30/06/2020 Final
44 GPBRIDP/Rd-489 Improvement of Kadamtali-Dargahat road at ch.500-1000m, GPBRIDP joypurhat-s 138474071 0.50 0.00 100 22.13 M/S Defence Enterprise Aramnagar, Sadar, Joypurhat. 21.70 01/01/1900 25/07/2017 13/06/2018 100 21.67 100 30/06/2020 Final
45 GPBRIDP/Mw-112 Maintenance of Simulia road ch.00-1600m GPBRIDP joypurhat-s 138475018 1.60 0.00 100 71.36 M/S Didarul Haque & Sonce Jamalganj Bazar, Akkelpur, Joypurhat. 72.36 01/01/1900 25/04/2016 08/12/2016 100 69.57 100 30/06/2020 Final
46 GPBRIDP/Mw-115 Maintenance of Kalai- Boiragipara -Matrai road ch.3300-5000m GPBRIDP kalai 138582011 1.70 0.00 100 22.53 M/S Masfa Enterprise 1 No.Rail Gate,Bogra. 18.46 01/01/1900 27/04/2016 10/06/2016 100 18.45 100 30/06/2020 Final
47 GPBRIDP/Rd-448 Improvement of Molamgari-Atmul-Shibgonj Road ch.2351m-2562m,2799m-2830m & 3092m-3230m. GPBRIDP kalai 138582011 0.38 0.00 100 28.82 M/S Rubina Construction Kalai, Joypurhat. 28.74 01/01/1900 27/04/2016 08/10/2017 100 27.96 100 30/06/2020 Final
48 GPBRIDP/Rd-455 Improvement of Silimpur-Binsara road ch.1800-2300m. GPBRIDP kalai 138474008 0.50 0.00 100 31.66 M/S Nazrul Islam Kalai,Joypurhat. 32.68 01/01/1900 05/07/2017 10/04/2018 100 32.67 100 30/06/2020 Final
49 GPBRIDP/Rd-451 Improvement of Kalai Chinema hall-Gongadashpur Road ch.3320m-4320m, GPBRIDP kalai 138583001 1.00 0.00 100 64.15 M/S Rubina Construction Kalai, Joypurhat. 64.04 01/01/1900 24/04/2016 02/05/2018 100 64.04 100 30/06/2020 Final
50 GPBRIDP/Rd-457 Improvement of Bafalgari-Shikta-Dingapara road ch.2026-2526m Salvage Value Tk.732141 GPBRIDP kalai 138474005 0.50 0.00 100 31.55 M/S Alaya Construction Sultangoanjpara,Goalgary, Bogra 29.76 01/01/1900 21/06/2017 05/06/2018 100 29.76 100 30/06/2020 Final
51 GPBRIDP/Rd-458 Improvement of Itail-Panchgram road ch.00-764m GPBRIDP kalai 138474006 0.76 0.00 100 41.33 M/S Nazrul Islam Kalai,Joypurhat. 42.89 01/01/1900 21/06/2017 05/11/2018 100 42.89 100 30/06/2020 Final
52 GPBRIDP/Rd-450 Improvement of Moslemgonj(st.Mandai)-Chottrogram Road ch.950m-2450m. GPBRIDP kalai 138583005 1.50 0.00 100 87.21 M/S Nazrul Islam Kalai,Joypurhat. 91.56 01/01/1900 27/04/2016 30/06/2018 100 91.56 100 30/06/2020 Final
53 GPBRIDP/Rd-449 Improvement of Matrai-Beala-Aligram-Kamdia Road ch. 3340m-4480m. GPBRIDP kalai 138583004 1.04 0.00 100 68.27 M/S Nazrul Islam Kalai,Joypurhat. 71.70 01/01/1900 24/04/2016 30/06/2018 100 71.69 100 30/06/2020 Final
54 GPBRIDP/Rd-508 Improvement of Katahar-Hatior road from ch.3282-4282m GPBRIDP kalai 138584010 1.00 0.00 100 61.77 Md.Munjurul Alam Mohon Chalk Sutrapur,Bogra. 59.90 01/01/1900 18/02/2018 24/02/2019 100 59.37 100 30/06/2020 Final
55 GPBRIDP/ Rd-452 Improvement of Moslemgonj-Panitola Road ch.1960m-3360m GPBRIDP kalai 138583002 1.40 0.00 100 82.54 M/S Zia Enterprise BattaliBazar,Khetlal,Joypurhat. 82.54 01/01/1900 27/04/2016 26/12/2017 100 81.78 100 01/01/1900 Final
56 GPBRIDP/Mw-114 Maintenance of Benai Milghar-fashitola Via Benai Govt. Primary School road ch.00-1300m GPBRIDP khetlal 138614011 1.30 0.00 100 23.03 Kalicharan Agarwala Old Hospital Road,Joypurhat. 22.95 01/01/1900 21/04/2016 24/12/2016 100 22.95 100 30/06/2020 Final
57 GPBRIDP/Rd-436 Improvement of Matigar-hope Hat road ch.946-2966m (ID No:138612007) [Khetlal] GPBRIDP khetlal 138612007 2.00 0.00 100 133.02 M/S Progoti Nirman East Janier Bagan,Joypurhat. 141.30 01/01/1900 27/04/2016 01/05/2017 100 141.00 100 30/06/2020 Final
58 GPBRIDP/Rd-438 Improvement of MamudpuUP Office-Sannastola Ghat road ch.5000-6000m GPBRIDP khetlal 138613006 1.00 0.00 100 52.87 M/S Kazol Enterprise Akkelpur, Joypurhat. 52.79 01/01/1900 26/04/2016 13/10/2017 100 52.79 100 30/06/2020 Final
59 GPBRIDP/Rd-439 Improvement of Monjharhat-Dhantola Mamudpur UP Office Road ch.00m-1700m GPBRIDP khetlal 138613004 1.70 0.00 100 92.40 Zia International Enterprise Arafat Nagar,Joypurhat. 91.97 01/01/1900 29/06/2016 11/05/2017 100 91.97 100 30/06/2020 Final
60 GPBRIDP/Rd-440 Improvement of Moushumi Bazar RHD-Gopinath pur GC via Samantahar-Barail GPS road Khetlal part Ch.2475-3100m Salvage Value Tk.63903. GPBRIDP khetlal 138612009 0.63 0.00 100 35.51 M/S Sukra Enterprise Chalk Sutrapur, Badurtola,Bogra. 37.21 01/01/1900 14/07/2017 30/05/2018 100 37.20 100 30/06/2020 Final
61 GPBRIDP/Rd-441 Improvement of Shakaranja Shapmara More Basota more via Nashinpur hat road ch.3970-4970m GPBRIDP khetlal   1.00 0.00 100 53.81 M/S Sukra Enterprise Chalk Sutrapur, Badurtola,Bogra. 56.39 01/01/1900 14/07/2017 25/11/2018 100 56.39 100 30/06/2020 Final
62 GPBRIDP/Rd-442 Improvement of Borotara Up Office-Uttarhat Shahor-Gorshal Road ch.1500-2000m GPBRIDP khetlal 138613008 0.50 0.00 100 28.67 M/S Defence Enterprise Aramnagar, Joypurhat. 28.31 01/01/1900 25/07/2017 30/08/2018 100 27.79 100 30/06/2020 Final
63 GPBRIDP/Rd-446 Improvement of Dakhin Hatshaher-Mainam Bandighi road ch.590-1090m. GPBRIDP khetlal 138614013 0.50 0.00 100 26.69 M/S Defence Enterprise Aramnagar, Sadar, Joypurhat. 26.05 01/01/1900 25/07/2017 30/08/2018 100 26.05 100 30/06/2020 Final
64 GPBRIDP/Rd-447 Improvement of JamgghoKarimpur Bazarr-Nasirpur road ch.336-836m. GPBRIDP khetlal 138615014 0.50 0.00 100 27.32 M/S Defence Enterprise Aramnagar, Sadar, Joypurhat. 26.67 01/01/1900 25/07/2017 30/08/2018 100 26.64 100 30/06/2020 Final
65 GPBRIDP/Rd-509 Improvement of Karimpur-Damghor-Noshipur Road Jamghor-Nashipur Road from ch.836-1336m. GPBRIDP khetlal 138615074 0.50 0.00 100 30.17 M/S Progoti Nirman Moon Super Market, Sadar, Joypurhat. 30.47 01/01/1900 12/02/2018 14/06/2018 100 30.46 100 30/06/2020 Final
66 GPBRIDP/Rd-510 Improvement of Shakharanjo Shahpara more to Basotamore via Nashipur hat Road from ch.2113-2766m and ch.4970-5317m GPBRIDP khetlal 138614024 1.00 0.00 100 60.09 Md.Munjurul Alam Mohon Chalk Sutrapur,Bogra. 58.28 01/01/1900 18/02/2018 06/05/2019 100 58.27 100 30/06/2020 Final
67 GPBRIDP/Rd-459 Improvement of Bagzana-Jibonpur-Mazhinahat Road ch.5150m-6150m. GPBRIDP panchbibi 138743004 1.00 0.00 100 52.87 M/S Haque Nirmata Sadar Road,Joypurhat. 52.74 01/01/1900 30/03/2016 23/12/2016 100 52.74 100 30/06/2020 Final
68 GPBRIDP/Rd-460 Improvement of Atapur UP Office(Uchai Bazar)-Feskahat Road ch.3000-4300m. GPBRIDP panchbibi 138743010 1.30 0.00 100 68.72 M/S Liton Traders Sadar Road,Joypurhat. 68.62 01/01/1900 03/04/2016 08/01/2017 100 68.62 100 30/06/2020 Final
69 GPBRIDP/Rd-461 Improvement of Atapur UP Office-Mazhina Road ch. 1584m-2450m. GPBRIDP panchbibi 138743011 1.00 0.00 100 52.87 M/S Rawshanara Enterprise Balighata,Panchbibi,Joypurhat. 50.53 01/01/1900 30/03/2016 27/10/2017 100 50.52 100 30/06/2020 Final
70 GPBRIDP/Rd-462 Improvement of Dharanji UP Office-Khangoirhat Road ch.1400m-2352m GPBRIDP panchbibi 138743012 1.00 0.00 100 52.87 M/S Bahar Traders Panchbibi,Joypurhat. 52.76 01/01/1900 17/03/2016 14/02/2017 100 52.76 100 30/06/2020 Final
71 GPBRIDP/Rd-463 Improvement of Nondail-Dharanji Road ch.00m-500m. GPBRIDP panchbibi 138744001 0.50 0.00 100 26.60 M/S Defence Enterprise Biswaspara,Joypurhat. 26.59 01/01/1900 10/04/2016 26/10/2017 100 26.59 100 30/06/2020 Final
72 GPBRIDP/Rd-464 Improvement of Aymarasulpur-Shimultali road ch.1162-1662m. GPBRIDP panchbibi 138744004 0.50 0.00 100 26.45 M/S Rahman Traders Jhowtola, Bogra. 25.79 01/01/1900 21/06/2017 14/06/2018 100 25.79 100 30/06/2020 Final
73 GPBRIDP/Rd-465 Improvement of Shimultali-Birnagar via Kashpur road ch.520-1020m Salvage Value Tk. 81779.00 GPBRIDP panchbibi 138744007 0.50 0.00 100 26.40 M/S Rahman Traders Jhowtola, Bogra. 25.73 01/01/1900 21/06/2017 18/06/2018 100 25.72 100 30/06/2020 Final
74 GPBRIDP/Rd-466 A.Improvement of Sikta-Sonapur road Ch.00-500m.B.Improvement of BairaKhidirpur-Dugurpara road ch.950-1450m. GPBRIDP panchbibi   1.00 0.00 100 57.43 M/S Rahman Traders Jhowtola, Bogra. 56.08 01/01/1900 23/07/2017 13/09/2018 100 56.07 100 30/06/2020 Final
75 GPBRIDP/Rd-467 Improvement of Golakata-Angra road Ch.1500-2000m. GPBRIDP panchbibi   0.50 0.00 100 26.39 M/S Rahman Traders Jhowtola, Bogra. 25.99 01/01/1900 21/06/2017 18/06/2018 100 25.97 100 30/06/2020 Final
76 GPBRIDP/Rd-487, 488 a. Improvement of Dargahat-Kadamtali road at ch00-525m. b.Improvement of Karia-Lakma road at ch1000-1200m. GPBRIDP panchbibi   0.73 0.00 100 38.99 M/S Rahman Traders Jhowtola, Bogra. 38.43 01/01/1900 23/07/2017 18/06/2018 100 38.42 100 30/06/2020 Final
77 GPBRIDP/Rd-505 Improvement of Dharanjee UP Office-Salpara GC Via koria hat Road from ch.00-2000m GPBRIDP panchbibi 138743013 2.00 0.00 100 127.41 M/S Sukra Enterprise Chakshutrapur,Badurtola, Bogra. 127.41 01/01/1900 28/12/2017 24/04/2019 100 127.39 100 30/06/2020 Final
78 GPBRIDP/Rd-514 mprovement of Atapur UP Office(Uchai Bazar)-Faska Hat road at (ch.4355-5250m). GPBRIDP panchbibi   0.90 0.00 100 56.81 M/S Kazol Enterprise Akkelpur, Joypurhat. 56.32 01/01/1900 30/01/2018 05/06/2018 100 56.26 100 30/06/2020 Final
79 GPBRIDP/Rd-513 Improvement of Nandael-Dharabge road at (ch.500-1355m) GPBRIDP panchbibi 138744001 0.86 0.00 100 50.73 M/S Kazol Enterprise Akkelpur, Joypurhat. 50.18 01/01/1900 30/01/2018 30/09/2018 100 50.16 100 01/01/1900 Final
80 GSIDP/JOY/DW-1 Improvement of Aushgara Eid Gha Math Gate and Mohammadabad Eid Gha Math Gate, Boundary Wall, under Mohammadabad Union, Upazila: Sadar, district: Joypurhat. Latitude:25.0888 , Latitude:25.0793, Latitude:89.0093, Longitude:89.0114 GSIDP joypurhat-s 3.81 M/S. Joy Traders 3.62 05/07/2018 04/09/2018 0  
81 GSIDP/JOY/DW-2 Improvement of Paikortoli Eid Gha Minar and Boundary wall under Union: Jamalpur, Upazila: Sadar, District: Joypurhat. Latitude:25.0527, Longitude:89.0320. GSIDP joypurhat-s 3.00 MS Patwary Construction 2.85 22/06/2018 21/08/2018 0  
82 GSIDP/JOY/DW-3 Improvement of Boro Majhipara moha Shoshan under Union: Bhadsha, Upazila: Sadar, District: Joypurhat. Latitude:25.19577, Longitude:88.9504 . GSIDP joypurhat-s 3.59 MS Liton Traders 3.41 25/06/2018 24/08/2018 0  
83 GSIDP/JOY/DW-4 Improvement of Kenduli Moha Shoshan under Union: Amdoi, Upazila: S PD adar, District: Joypurhat. Latitude:25.2583, Longitude:89.12357. GSIDP joypurhat-s 3.32 M/S. Motahar Ali 3.15 05/07/2018 04/09/2018 0  
84 GSIDP/JOY/DW-5 Improvement of Madhainagor Mondolpara Jame Mosque under Union: Amdoi, Upazila: Sadar, District: Joypurhat. Latitude:25.01893, Longitude:89.12793. GSIDP joypurhat-s 4.01 M/S. Chistia Construction 3.81 09/07/2018 08/09/2018 0  
85 GSIDP/JOY/DW-6 Improvement of Uttor jamalpur Dhakhkhin Dadra Jame Mosque under Union: Jamalpur, Upazila: Sadar, District: Joypurhat. Latitude::25.0497, Longitude:89.0386. GSIDP joypurhat-s 5.37 M/S. Arco Engineers 5.11 04/07/2018 03/09/2018 0  
86 GSIDP/JOY/DW-7 Improvement of Chanda Sarbojanin Durga Mondir, under Union: Jamalpur, Upazila:Sadar, District: Joypurhat. Latitude:25.0470, Longitude:89.0350. GSIDP joypurhat-s 3.15 M/S. Rashel Traders 2.99 09/07/2018 08/09/2018 0  
87 GSIDP/JOY/DW-8 Improvement of Bel Amla Baro Shib Mondir, Joypurhat Sadar, Joypurhat. under Union : Mohammadabad,Upazila:Sadar,District:Joypurhat.Latitude:25.1311,Longitude: 89.0158. GSIDP joypurhat-s 5.04   0.00 0  
88 GSIDP/JOY/DW-9 Improvement of Uri(Jamalpur) Moha Shoshan, under Union: Jamalpur, Upazila: Sadar, District: Joypurhat. Latitude:25.0594, Longitude:89.0234. GSIDP joypurhat-s 3.81 M/S. Khan Construction 3.62 01/07/2018 01/09/2018 0  
89 GSIDP/JOY/DW-10 Improvement of Nutunhat Baitul Mamur Jame Masque under Union: Pourashava, Upazila: Sadar, District: Joypurhat. Latitude:25.0946, Longitude:89.0288. GSIDP joypurhat-s 5.60 M/S. Duke Construction 5.32 13/06/2018 12/08/2018 0  
90 GSIDP/JOY/DW-11 Improvement of Joypurhat Central Baroyary Mondir, Union: Pourashava, Upazila: Sadar, District: Joypurhat. Latitude:25.1034, Longitude:89.02798. GSIDP joypurhat-s 5.62 M/S. Milu Construction 5.34 22/06/2018 21/08/2018 0  
91 GSIDP/JOY/DW-12 Improvement of Joypurhat Central Shib Mondir, Union: Pourashava, Upazila: Sadar, District: Joypurhat. Latitude:25.1035, Longitude:89.02717. GSIDP joypurhat-s 4.50 M/S. Sarder Chaul Kal 4.28 09/07/2018 08/09/2018 0  
92 GSIDP/JOY/DW-13 Improvement of Chalkborkot Nidhi Jame Mosque, Union: Chalkborkot, Upazila: Sadar, District: Joypurhat. Latitude:25.1519, Longitude:88.9301. GSIDP joypurhat-s 4.00 M/S. Rakib Departmental Store 3.80 25/06/2018 24/08/2018 0  
93 GSIDP/JOY/DW-14 Improvement of Dhalarhar Rayhanpara Jame Mosque, Union: Dhalarhar, Upazila: Sadar, District: Joypurhat. Latitude:25.1699, Longitude:89.9630. GSIDP joypurhat-s 5.70 M/S. Joy Traders 5.42 05/07/2018 04/09/2018 0  
94 GSIDP/JOY/DW-15 Improvement of Durgadhah Bazar Jame Mosque, under Union: Bhadsha, Upazila: Sadar, District: Joypurhat. Latitude:25.21554, Longitude:88.98932. GSIDP joypurhat-s 0.00 M/S. Mollah Shamsul Alam 5.70 19/06/2018 17/08/2018 0  
95 IRIDP-2/JOY/DW-1 Improvement of Paschim Dogachi-Pakurtali road (Ch. 1500m-2500m). IRIDP-2 joypurhat-s 1.00 49.07 M/S Didarul Haque & Sons 49.05 31/01/2016 01/07/2016 100  
96 IRIDP-2/JOY/DW-2 a)Improvement of Atthoka-Dhalahar road (ch. 00m-500m). b)Construction of 1nos culvert 0.625x0.600m at Ch.90m. c)Construction of 1nos culvert 0.375x0.450m at Ch.190m. IRIDP-2 joypurhat-s 0.50 26.45 Classic Construction 26.45 20/01/2016 30/04/2017 100  
97 IRIDP-2/JOY/DW-3 Improvement of Dogachi UP Office-Jamtoli Via Dhalahar UP Office road (Ch. 714-1314m). IRIDP-2 joypurhat-s 0.60 34.23 Kalicharam Agarwala 34.21 19/01/2016 15/12/2016 100  
98 IRIDP-2/JOY/DW-4 Improvement of Mongalbari-Pechulia Link road (Ch.00m-500m). IRIDP-2 joypurhat-s 0.50 25.56 MS Liton Traders 25.56 25/01/2016 10/12/2016 100  
99 IRIDP-2/JOY/DW-5 a)Improvement of Gopalpur Baskata road (ch. 900m-1400m). b)Construction of 1nos culvert 0.900x0.900m at Ch.1250m. IRIDP-2 joypurhat-s 0.50 25.08 M/S Zahid Traders 25.07 26/01/2016 30/08/2016 100  
100 IRIDP-2/JOY/DW-6 a)Improvement of Noapara-Mongalbari road (ch.1900m-2400m). b)Construction of 1nos culvert 0.625 x 0.600m at Ch.2080m. IRIDP-2 joypurhat-s 0.50 30.81 M/S Mahadi Construction 30.78 21/01/2016 22/07/2016 100  
101 IRIDP-2/JOY/DW-7 Improvement of Rangta Polikadoa-Mirgram Via Kadoa road ( ch. 4200m-4700m). IRIDP-2 joypurhat-s 0.50 26.49 M/S Mahadi Construction 25.17 21/01/2016 22/07/2016 100  
102 IRIDP-2/JOY/DW-8 Improvement of Dogachi ( Uttar Joypur)-Baguan road (ch.00-750m) IRIDP-2 joypurhat-s 0.75 39.39 Classic Construction 34.95 20/01/2016 30/04/2017 100  
103 IRIDP-2/JOY/DW-9 Improvement of Mongalbari Hat ( Dogachi UP Office)-Durgadaha Bazar road (Ch. 2939m-3689m). IRIDP-2 joypurhat-s 0.75 39.34 Kalicharam Agarwala 35.54 19/01/2016 15/12/2016 100  
104 IRIDP-2/JOY/DW-10 a)Improvement of Mozahidpur Pucca road-Ichua road (ch.00-500m). b)Construction of 1nos culvert 0.375x0.450m at Ch.266m. IRIDP-2 joypurhat-s 0.50 26.88 Kalicharam Agarwala 24.52 19/01/2016 15/12/2016 100  
105 IRIDP-2/JOY/DW-11 Improvement of Panial-Paglabazar-Barokandi road ( ch.7950m-8450m). IRIDP-2 panchbibi 0.50 25.86 M/S Kaderi Kibria 23.14 20/01/2016 30/06/2017 100  
106 IRIDP-2/JOY/DW-12 Improvement of Kusumba UP Office-Berakhai Road ( ch.500m-765m & 900m-1330m). IRIDP-2 panchbibi 0.27 28.56 MS Liton Traders 28.56 21/01/2016 30/11/2016 100  
107 IRIDP-2/JOY/DW-13 Improvement of Koria-Lakma road (ch. 00m-500m) . IRIDP-2 panchbibi 0.50 25.50 Classic Construction 25.35 04/02/2016 30/04/2017 100  
108 IRIDP-2/JOY/DW-14 Improvement of Berakhai Village road (ch. 00m -500m). IRIDP-2 panchbibi 0.50 21.77 M/S Kaderi Kibria 19.68 03/02/2016 23/06/2016 100  
109 IRIDP-2/JOY/DW-15 Improvement of Sultanpur Dewanbagi Mosque - Siddique Mondal house road (ch.00m-500m). IRIDP-2 panchbibi 1.00 21.61 M/S Rawshanara Enterprise 19.70 04/02/2016 16/06/2016 100  
110 e-Tender/NBIDNNGPS/JOY/JOY/2017-2018/W1-00391 MASTER PARA PRIMARY SCHOOL NBIDNNGPS joypurhat-s 74.54 M/S Maa Empex 70.81 17/04/2018 18/04/2019 75  
111 e-Tender/NBIDNNGPS/JOY/PAN/2017-2018/W1-00210 DOGHORA ADORSHO GPS NBIDNNGPS panchbibi 65.46 M/S Mondal Traders 58.91 14/03/2018 20/03/2019 90  
112 e-Tender/NBIDNNGPS/JOY/PAN/2017-2018/W1-00212 URANI ADIBASI GOVT. PRIMARY SCHOOL NBIDNNGPS panchbibi 65.46 M/S Mondal Traders 58.91 14/03/2018 20/03/2019 80  
113 e-Tender/NBIDNNGPS/JOY/PAN/2017-2018/W1-00213 HABIBPUR GOVT. PRIMARY SCHOOL NBIDNNGPS panchbibi 69.60 Md. Saydul Islam 62.64 14/03/2018 20/03/2019 70  
114 e-Tender/NBIDNNGPS/JOY/PAN/2017-2018/W1-00301 ATAPUR ANGARI PRIMARY SCHOOL NBIDNNGPS panchbibi 71.70 Techbay International 64.53 19/03/2018 18/03/2019 75  
115 e-Tender/NBIDNNGPS/JOY/PAN/2017-2018/W1-00302 MRIDHAPARA GOVT. PRIMARY SCHOOL NBIDNNGPS panchbibi 72.30 Md. Saydul Islam 65.07 14/03/2018 20/03/2019 80  
116 CW-33/RCIP/JOY 1. Improvement of Panchbibi GC - Salaipur RHD Road (Road ID138742001, Upazila: Panchbibi, District: Joypurhat) 2. Improvement of Gopinathpur UP office(Karaitola)-Raikali UP office . (Road ID138133010, Upazila: Akkelpur, District: Joypurhat) 3. Improvement of Mongalbari hat Rd(Dogachi Up Office)to Durgadaha bazar road (Road ID138473005, Upazila: Joypurhat-S, District: Joypurhat) 4. Improvement of Moushumi Bazar (RHD) - Rukindipur GC via Sannyash Ghat (Khatlal portion) (Road ID138612010, Upazila: Khetlal, District: Joypurhat) 5. Improvement of Kalai-Kichok RHD Via Gongadaspur Road (Road ID138582014, Upazila: Kalai, District: Joypurhat) RCIP panchbibi 138742001 36.07 0.00 72 3458.46 Md. Moyenuddin (Bashi) and M/S Masuma Begum(JV) Katnarpara, Bogura Sadar,Bogura.Mob: 01711-899676 3435.81 29/08/2019 05/09/2019 17/01/2023 88 2466.51 72 05/01/2023  
117 RDRIDP/Joy/ Akkelpur-01/17-18 a. Rukindipur-Shahpur road at Ch.1650-2150m Road ID 138135004 b. Rukindipur-Pali road at Ch.1000-1500m Road ID 138135005 c. Kesermore-Bottoli road at Ch. 1000-1500m Road ID 138134035 d. Tilokpur-Karamjee Naozar road at Ch. 1000-2100m Road ID 138134006 Upazila Akkelpur District Joypurhat . RDRIDP akkelpur 2.60 152.69 M/S. SRITI TRADERS 145.06 07/01/2018 07/01/2019 40  
118 RDRIDP/Joy/ Akkelpur-02/17-18 (a). Gopinathpur UP office-Kuranuhat via Madartoli ghat road at Ch. 800-2300m (Road ID: 138133009) (Salvage Cost BDT: 842315.00 ) (b). Naldanga-Palsha road at Ch.1000-1525m (Road ID: 138134032) Upazila: Akkelpur District: Joypurhat RDRIDP akkelpur 2.03 117.90 M/S. MOSNOBI ENTERPRISE 112.00 17/06/2018 16/06/2019 15  
119 RDRIDP/Joy/ Akkelpur-03/17-18 a. Bhikni hat Sonamukhi UP offioce road at Ch.00.00-575.00 & 1735.00-2000.00m Road ID 138133013 Salvage Cost BDT 313818.00 b. Raikali UP office-Horishadi hat via Punduria road at Ch. 2990.00-4550.00m Road ID 138133008 Salvage Cost BDT 1128516.00 Upazila Akkelpur District Joypurhat . RDRIDP akkelpur 2.40 134.55 M/S. A.R ENTERPRISE 127.82 07/01/2018 07/01/2019 15  
120 RDRIDP/Joy/ Sadar -01/17-18 a. Chakbarkot UP Office Pagladewan hat road at Ch.1480.00 - 1545.00m & 1645.00-2580.00m Road ID.138473004 b. Dhalarhar School JamtoliAtthok Grameen Bank Dhalarhar School at Ch.00-1000.00m Salvage Cost BDT.892150.00 Road ID.138474003. UpazilaJoypurhat sadar District Joypurhat RDRIDP joypurhat-s 2.00 117.57 M/S Kazol Enterprise 111.69 06/03/2018 06/03/2019 100  
121 RDRIDP/Joy/ Sadar -02/17-18 a. Thiot Nengapir road at Ch.500-1500.00m Road ID.138474008 b.Aushgara Teghora road at Ch.00-475.00m Road ID138474014 Salvage Cost BDT991153.00 UpazilaJoypurhat sadar DistrictJoypurhat. RDRIDP joypurhat-s 1.48 83.30 M/s Zehad Enterprise 79.13 06/03/2018 06/02/2019 100  
122 RDRIDP/JOY/Sadar-03/17-18 a.Beltoli Khaspanada Mission road at Ch.00-1000.00m Road ID 138474025 Salvage Cost BDT 733647.00 b Gopalpur Bashkata road at Ch.2000-2500.00m Road ID 138474030 Upazila Joypurhat sadar District Joypurhat . RDRIDP joypurhat-s 1.50 83.99 M/S. SUKRA ENTERPRISE 79.79 06/06/2018 06/06/2019 0  
123 RDRIDP/JOY/Sadar-04/17-18 (a). Puranapoil â?? Karimnagar road at Ch.00-1150.00m (Road ID: 138474031) (b). Bhadsha â?? Haripur road at Ch.1000-2500.00 (Road ID: 138474043) Upazila: Joypurhat sadar District: Joypurhat. RDRIDP joypurhat-s 2.65 148.57 MD. ABDUL JALIL 141.14 06/06/2018 06/06/2019 0  
124 RDRIDP/Joy/ Sadar -05/17-18 (a). Improvement of Suktahar â?? Pali road at Ch.00.00 - 1020.00m ( Salvage Value BDT ; 44,787.00 ) Road ID. 138474056 (b). Improvement of Beltoli-Chak Dadra road at Ch.00-1000.00m Road ID.138474057 Upazila: Joypurhat-Sadar District: Joypurhat RDRIDP joypurhat-s 2.02 134.69 M/S Kazol Enterprise 127.95 19/07/2018 18/07/2019 20  
125 RDRIDP/Joy/ Sadar -06/17-18 (a). Improvement of Jamalpur-Chatrapukur road at Ch.00-1000.00m (Salvage Value BDT: 86,545.00) Road ID.138474051 (b) Improvement of Pakurtoli-Jamalgonj Hat road at Ch.00-1000.00m Road ID.138474040 Upazila: Joypurhat Sadar District: Joypurhat . RDRIDP joypurhat-s 2.00 124.82 M/S Saiful Traders 118.58 22/07/2018 21/07/2019 20  
126 RDRIDP/Joy/ Kalai-01/17-18 (a) part-A. A) Chilimpur-Binsira road at Ch. 2300.00-3600.00m part-B. Construction of 4 nos U-Drain size 6000mmx625mmx600mm at Ch.2488m, 2813m , 3288m & 3598m on Same road. (Road ID: 138584008) (b). Nunuj-Basuria-Multia road at Ch. 2193.00-3813.00m (Road ID: 138584017) Upazila: Kalai District: Joypurhat . RDRIDP kalai 2.92 177.36 M/S. Ritu Enterprise 168.49 07/01/2018 07/01/2019 5  
127 RDRIDP/Joy/ Kalai-02/17-18 Moslemgonj GC-Kamdia GC via Chottragarm road at Ch. 2450.00-4450.00m Road ID 138582013 Upazila Kalai District Joypurhat RDRIDP kalai 2.00 122.07 M/S. Arnob Traders 115.96 07/01/2018 07/01/2019 0  
128 RDRIDP/Joy/ Khetlal-01/17-18 (a) . Part-A Tawsara-Roir road at Ch. 1000-2000m (Part-B) Construction of 05nos 0.625x0.60m U-drain at Ch. 1170m,1235m,1540m,1730m & 1900m (Road ID:138614005) (b). Part-A Hinda-Nasipur-Buripukur road at Ch. 00-1000m (Part-B) Construction of 02 nos 0.625x0.60m U-drain at Ch. 545m, 680m (Road ID: 138614003) Upazila: Khetlal District: Joypurhat . RDRIDP khetlal 2.00 117.48 M/S. ROKIB TRADERS 111.61 07/01/2018 07/01/2019 35  
129 RDRIDP/JOY/Khetlal-02/17-18 Borail UP office-Modhupukur Hat via Shakharanja & Alampur road Sha kharanjo Shah Para more Basotamore via Nashipur Hat road at Ch. 5317-6742m Road ID 138613002 Salvage Cost BDT 93931.00 Upazila Khetlal District Joypurhat . RDRIDP khetlal 1.43 82.77 M/S Anju Traders 78.63 07/01/2018 07/01/2019 0  
130 RDRIDP/JOY/Khetlal-03/17-18 a. R&H road Majhiasthal road at Ch.00-330m & Construction of 0.375mx0.45m U-Drain on Same road at Ch.65.00m Road ID 138615003 Salvage Cost BDT 222851.00 b. Tarakul Krishnonogar Fakirpara RHD road at Ch.1000.00-1500.00m Road ID 138614012 salvage Cost BDT 344083.00 Upazila Khetlal District Joypurhat . RDRIDP khetlal 0.83 48.09 M/S. MOSNOBI ENTERPRISE 45.69 17/06/2018 16/06/2019 0  
131 RDRIDP/JOY/Khetlal-04/17-18 (a). Shibpur Fuldighi road â?? Panchuil Noyapara road at C.00-500.00m. & Construction of 02 nos 0.625mx0.600m u-drain and 0.375mx0.450m on same road at Ch.332m &380m (Road ID: 138615116) (Salvage Cost BDT: 232652.00) (b). Talshon Eidgah math â?? Ikorgara road at Ch.00-500.00m ( Road ID : 138615029) . Upazila: Khetlal District: Joypurhat RDRIDP khetlal 1.00 63.39 M/S. SRITI TRADERS 60.22 07/01/2018 07/01/2019 0  
132 RDRIDP/JOY/Khetlal-05/17-18 a. Alompur high School Dhakhin Para road at Ch.00-500.00m & 03nos 0.625mx0.600m U-Drain on same road at Ch.128m311m355m Road ID 138615111 Salvage Cost BDT 227053.00 b. Ikorgara Embankment road at Ch.00-500.00m Road ID 138615055 Upazila Khetlal District Joypurhat . RDRIDP khetlal 1.00 66.52 M/S. S.B Traders 63.19 07/01/2018 07/01/2019 0  
133 RDRIDP/Joy/ Khetlal-06/17-18 Mohabbatpur Govt Praimary School â?? Madartoli road at Ch.00-500.00m & Construction of 03nos Size 0.675mx0.600m U-Drain at Ch.127m,164m, &320m (Road ID: 138615068) (Salvage Cost BDT: 90892.00) Upazila: Khetlal District: Joypurhat RDRIDP khetlal 0.50 31.95 M/S Bani Construction 30.35 07/01/2018 07/01/2019 5  
134 RDRIDP/Joy/ Panchbibi -01/17-18 a. Galakata-Angra road at Ch.4500-5500m Road ID 138744013 b. Fotipur-Bhutal road at Ch.00-1250m Road ID 138745022 Salvage Cost BDT 1305680.00 Upazila Panchbibi District Joypurhat RDRIDP panchbibi 2.25 134.97 M/S. SUKRA ENTERPRISE 128.22 06/06/2018 06/06/2019 0  
135 RDRIDP/Joy/ Panchbibi -02/17-18 a. Shimultoli-Birnagar via Kashpur road at Ch.1020-2595m Road ID 138744007 b. Aymarsulpur-Shimiltoli road at Ch.1662-2662m Road ID 138744004 Upazila Panchbibi District Joypurhat . RDRIDP panchbibi 2.58 146.91 M/S. Maa Tasin Enterprise 139.56 06/07/2018 06/06/2019 40  
136 RDRIDP/Joy/ Panchbibi -03/17-18 Panchbibi GC (REB Sub Station)-Habibpurhat Madhainagar GC road at Ch.3700-5550m (Road ID: 138742010_) ( Salvage Cost BDT: 56571.00) Upazila: Panchbibi District: Joypurhat RDRIDP panchbibi 1.85 141.88 M/S. SUKRA ENTERPRISE 134.79 06/06/2018 06/06/2019 0  
137 RERMP-3/JO YPUR/W-10 Maintenance of Rural Roads Joypurhat() RERMP-3 joypurhat-s N/A 37 1168.00 N/A 1168.00 40 434.00 37 26/12/2021 Ongoing
138 SP15221/Hatigara-Kamalpur WCS Subproject Re-excavation of Hatigara-Kamalpur Khal Reference line section (6nos.) Basher Shako (2nos, L=34m) Construction of WMCA Office and WRS Maintenance (weir) SSSWRDP joypurhat-s   6.70 90 136.62 LCS 133.59 17/04/2019 15/04/2020 30/04/2020 100 120.96 90 30/11/2022 Completed
139 SP24143/Kadirpur-Bakhara Subproject Re-excavation Kadirpur-Bakhra Khal Reference line section (5nos.) and Basher Shako (3nos, L=42m) Maintenance of Water Structure SSSWRDP kalai   3.60 91 51.04 LCS-11 51.05 17/04/2019 24/02/2022 30/04/2022 100 46.70 91 30/11/2022 Completed
140 SP13091/Kanmona-Haraboti WCS Subproject Harabati Khal re-xcavation (Ch:0.00m - 10000m) Const. of 05 Nos. Ref. lined Section on 01 Khal, SP Identf. sign board 2, SP Area Indication Post 2 Nos. SSSWRDP kalai   10.00 88 137.44 LCS 137.44 29/02/2024 25/03/2024 50 121.83 88 30/11/2022 Ongoing
141 SP15220/Pathanpara-Koitahar WCS Subproject Re-excavation of Patahnpara - Koitahar Khal (Ch-0+000km to 7+600km) Ref. Lined Section 7 Nos. On 1 Khals, And SP Identf. Signboard (2 nos.) Rehabilitation of Pathanpara - Koitahar Khal WRS (2v-1.5mx1.8m) -. Construction of WMCA office building SSSWRDP khetlal   7.60 96 63.59 OTM 61.34 31/08/2020 24/02/2022 30/04/2022 100 59.27 96 30/11/2022 Completed
142 SP15277/Boyra-Srikrishnapur DR & WCS Subproject WMCA Office and Others Boyra-Srikrishnapur khal re-excavation(ch.00-6800m) Referenced line section(5 Nos.) SSSWRDP panchbibi   6.80 92 106.30 TOFAZZOL 104.38 28/01/2019 07/07/2019 30/04/2018 100 96.89 92 30/11/2022 Completed
143 SP22015/Amirpur-Barail Subproject Amirpur Borail khal & Branch khal- 1 re-excavation(ch.00-6100m&ch.00-870m) Referenced line section(5 Nos.) SSSWRDP panchbibi   6.97 92 56.02 SABANA MUSTARIN 56.02 08/02/2018 05/03/2018 30/04/2018 100 51.89 92 30/11/2022 Completed
144 SP61015/Shekta Chaksamser Khal Subproject Re-exacavation of Shekta-Chak Samser Khal (Ch-0+300km to 4+590km) Re-exacavation of Shekta-Chak Samser Branch Khal (Ch-0+000km to 2+202km) Ref. Lined Section 6 Nos. On 2 Khal And SP Identf. Signboard (2 nos.) Shekta-Chak Samser Khal WRS-1 (2v-1.5mX2.5m) at Ch. 0+710 km Construction of WMCA office building. Shekta-Chak Samser Khal WRS-2 (2v-1.5mX1.5m) at Ch. 3+560 SSSWRDP panchbibi   6.49 98 190.89 OTM, Md. Sohel,Santahar,Bogra. 202.09 19/12/2021 22/03/2022 30/04/2022 100 198.10 98 30/11/2022 Completed
145 SP13078/Baharampur FCD Subproject Re-sectioning of Bahrampur Embankment (Ch-0+000km to 1+300km) and SP Identification Signboard & Post (2Nos.) SSSWRDP panchbibi   1.30 94 22.58 LCS 22.58 15/10/2023 13/11/2023 25/04/2024 100 21.38 94 30/11/2022 Completed
146 SP44109/Jhinaigari Khal Subproject Jhenaigari Khal re-excavation (Ch:0.00 - 7500m) Const. of 08 Nos. Ref. lined Section on 1 Khal SSSWRDP panchbibi   7.50 95 83.28 LCS 83.27 15/02/2024 07/03/2024 25/04/2024 100 79.36 95 30/11/2022 Completed
147 w-22 Construction of Vadsha UP Complex UCCP-2 joypurhat-s 0 121.82 106.44 17/10/2019 30/05/2020 15 0.00 0 23/08/2020 ongoing
148 w-499 Construction of jamalpur UP Complex UCCP-2 joypurhat-s 100 98.02 88.22 20/06/2017 30/11/2018 100 87.79 100 18/08/2020 final
149 w-514 Construction of mohammadabad UP Complex UCCP-2 joypurhat-s 100 99.01 89.11 07/12/2017 16/11/2018 100 70.26 100 18/08/2020 final
150 w-500 Construction of poranapul UP Complex UCCP-2 joypurhat-s 90.21 81.19 11/06/2017 20/08/2018 100 65.83 17/03/2020 ongoing
151 020/176 Construction of ZINDERPUR UP Complex UCCP-2 kalai 82.24 78.65 04/11/2013 30/12/2015 100 78.00 03/09/2020 FINAL
152 019/176 Construction of BOMBU UP Complex UCCP-2 kalai 85.36 89.60 27/01/2013 17/11/2013 100 89.60 03/09/2020 FINAL
153 w.336 Construction of barail UP Complex UCCP-2 khetlal 100 89.03 73.89 03/03/2016 30/06/2018 100 73.02 100 22/08/2020 final
154 w.421 Construction of barail UP Complex UCCP-2 khetlal 100 88.96 90.08 10/05/2016 30/11/2018 100 87.37 100 18/08/2020 final
155 023/246 Construction of alampur UP Complex UCCP-2 khetlal 100 56.05 58.48 15/07/2010 15/01/2012 100 58.47 100 23/07/2020 final
156 w.411 Construction of mohammadpur UP Complex UCCP-2 panchbibi 100 85.56 85.50 26/08/2014 30/03/2016 100 85.34 100 23/08/2020 final
157 w.604 Construction of balighata UP Complex UCCP-2 panchbibi 0 144.96 137.72 04/10/2018 28/02/2020 100 55.00 0 19/08/2020 ongoing
158 w.319 Construction of aymarsulpur UP Complex UCCP-2 panchbibi 100 87.27 87.22 06/12/2012 20/10/2013 100 87.18 100 18/08/2020 final
159 w.436 Construction of bagzana UP Complex UCCP-2 panchbibi 100 88.14 74.68 10/04/2016 31/07/2017 100 74.63 100 18/08/2020 final
160 CBU-100/ Purto-174 জয়পুরহাট জেলার সদর উপজেলাধীন পুরানাপোল-করিমনগর সড়কে ১১৫০ মিটার চেইনেজে ছোট যমুনা নদীর উপর সেতু নির্মাণ। (রোড আইডিঃ১৩৮৪৭৪০৩১) UHBP joypurhat-s 138474031 81.00 0 628.81 M/S Mondol Traders Chakdev,Main Road,Naogaon. 550.20 12/04/2021 25/12/2024 80 349.01 0 28/07/2024  
161 CBU-100/ Purto-175 জয়পুরহাট জেলার পাঁচবিবি উপজেলাধীন বাগজানা ইউপি - ধরঞ্জি ইউনিয়ন সংযোগ সড়কে ব্রিজ নির্মাণ। (রোড আইডিঃ১৩৮৭৪৩০০৬) UHBP panchbibi 138743006 96.00 0 976.74 M/S BHB-liton JV, M/s Liton Traders Sadar Road, Joypurhat. 873.70 15/04/2021 30/11/2023 100 857.66 0 28/07/2024  
162 UIIP- BC/PCO/W-063 1.(a) Improvement of BC Road Starting from UNO Office to H/O Maruf at Damdama, Panchbibi Pourashava. Length- 0+000-0+200.00m, Ward No.-05. 2. Rehabilation of BC Road St. from Hili Road H/o Vim , to Mukto Khelaghor, Length- 0+000-0+600.00m, Ward No.- 05. 3. Improvement of BC Road St. from Panchbibi Koria Road Via Raihan Vai Plot to Hotatpara at Maloncha, Panchbibi Pourashava Length- 0+000-0+500.m, Ward No.- 04. 4. Rehabilation of BC Road St. from Kmdia Road to Danajpur Khanka Shrif, Length- 0+000-0+230.0m, Ward No.- 09. 5. Rehabilation of BC Road St. from Hariharpur Lat Aziz Chowdhury Para, Length- 0+000-0+220.00m, Ward No.- 01. UIIP panchbibi   1.69 0.00 95 98.69 M/S Raihan Construction 98.69 23/03/2021 26/09/2021 100 93.94 95 29/09/2022 0.0013% Less (Time Extension)
163 UIIP- BC/PCO/W-064 1. Improvement of Road Starting from Joypurhat - Hili Road to H/o Radhanath at Damdama, Panchbibi Pourashava. Length- 0+000-0+250.00m, Ward No.-05 2. Improvement of BC Road Starting from Mohipur College Road to H/o Kalam Sharkar at Panchbibi, Panchbibi Pourashava. Length- 0+000-0+180.00m, Ward No.-08 3. Improvement of BC Road Starting from Gopalpur Road to Danajpur Adibashipara at Danajpur, Panchbibi Pourashava. Length- 0+000-0+270.00m, Ward No.-09 4. Construction of RCC Drain St. From Pond of Kenedi Mondol to Radhabari Mosque at Radhabari,Panchbibi Pourashava.Word no.06 (Ch. 0+000-0+210.00). UIIP panchbibi   0.76 0.00 98 98.13 M/S Progoti Nirman 98.13 23/03/2021 26/09/2021 100 96.10 98 29/09/2022 0.12% Less (Time Extension)
164 UIIP-BC/PCO/W-065 Construction of Rcc Drain starting from 1 no. railgate to Danejpur Kamrul chaw mill at Panchbibi Pourashava, Ward no-09, length- ch.-0+000-0+550.00m, under Panchbibi Pourashava, District: Joypurhat. UIIP panchbibi   0.00 100 99.31 Kalicharan Agarwala 99.15 08/08/2020 15/08/2020 14/08/2021 100 99.15 100 29/09/2022 0.16% Less
165 UIIP-BC/PCO/W-066 1. Construction of RCC Drain St. From Mukto Khelaghor at Damdama Panchbibi Pourashava.Word no.05 (Ch. 0+000-0+255.00m).2. Construction of RCC Drain St. From Balighata Bazar Tinmatha Moor to Janata Bank Moor South Road Side at Panchbibi Pourashava.Word no.03 (Ch. 0+000-0+185.00m). UIIP panchbibi   0.00 100 99.52 M/S Raihan Construction 99.52 23/03/2021 03/12/2020 12/04/2021 100 99.52 100 29/09/2022 0.10% Less (Time Extension)
166 UIIP-BC/PCO/W-358 Construction of RCC Drain and RCC Road St From Society Market Gate Balighata Bazar Front Side of Panchbibi Pourashava Kitchen & Municipal Market to Panchbibi Bus Stand at Panchbibi Pourashava (Drain Ch. 0.0-295.00m Road Ch. 0.0-512.00m UIIP panchbibi   0.54 0.00 100 152.85 Kalicharan Agarwala 167.34 19/12/2021 19/12/2021 19/12/2021 100 167.30 100 29/09/2022 9.48% Above
167 UIIP-BC/PCO/W-359 (1) Improvement of BC Road Starting From Mahatas Monjil Mosjid to Mukto Khalaghor Via H/O Monower Chowdhury Pond at Panchbabi Pourashava, Joyporhat Length-0+000-360.00m (2) Improvement of BC Road St from Hilli Road to H/O Shirajul at Panchbibi Pourashava, Joypurhat Length- 0+000-290.00m (3) Improvement of BC Road St from Borgahati Road to 1.ono Raill Gate Via Griho Nirman office at Panchbibi Pourashava, Joypurhat, Length-0+000-350.00m (4) Improvement of BC Road Starting From H/O Elias Moulana to Gopalpur at Panchbibi Pourashava, Joypurhat, Length- 0+000-260.00m UIIP panchbibi   1.06 0.00 44 76.11 M/S Progoti Nirman 83.33 19/12/2021 19/12/2021 19/12/2022 60 36.83 44 29/09/2022 9.47% Above
168 UIIP-BC/PCO/W-360 Improvement of BC Road Starting From H/O Kohorulla Master to Ramtanu School (Rail) Gate) Via H/O Ex Copunsilor Mojurul at Panchbibi Pourashava UIIP panchbibi   0.68 0.00 0 70.29 M/S Progoti Nirman 76.90 19/12/2021 19/12/2021 19/12/2022 35 0.00 0 29/09/2022 9.40% Above
169 UIIP-BC/PCO/W-361 Improvement of BC Road St from Danejpur H/O Ab.Khallek to Via H/O Obaidul to H/O Shafiulla Mia at Panchbibi Pourashava Length- 0+000-380.00m (2) Improvement of BC Road St form Korroti Ram Krishno Mondir to Rail Line Via Ossman Para at Panchbibi Pourashava Joypurhat Length-0+000-850.00m UIIP panchbibi   1.04 0.00 62 94.67 M/S Progoti Nirman 103.67 19/12/2021 19/12/2021 19/12/2022 65 64.03 62 29/09/2022 9.50% Above
170 UIIP-BC/PCO/W-444 1. Construction of RCC Drain St. from Kamdia Road MP House Old Mosque to East Balighata (West Side) at Panchbibi Pourashava (Ch.0+000-0+400.00m) Ward No-01 UIIP panchbibi   0.00 0 68.70 Kalicharan Agarwala 72.06 14/06/2022 21/06/2022 20/06/2023 0 0.00 0 29/09/2022 5.00% Above
171 UIIP-BC/PCO/W-445 1. Construction of RCC Drain & RCC Road St. from Maloncha Charmatha More Culvert to House of Rashid Mosque (East side) at Panchbibi Pourashava (Drain Ch.0+000-0+80m, Road Ch.0+00-0+60m) Ward No-04 2. Construction of RCC Road St. from Kazi Office More to Kalai Hati Road at Panchbibi Pourashava, Joypurhat Length-0+000-200.00m, Ward No-08 3. Construction of RCC Drain & RCC Road St. from Textile Mill More to House of Nuhur at Panchbibi Pourashava, Joypurhat Length-0+000-90.00m, Ward No-02 UIIP panchbibi   0.06 0.00 0 64.61 Kalicharan Agarwala 67.84 14/06/2022 21/06/2022 20/06/2023 0 0.00 0 29/09/2022 5.00% Above
172 UIIP-BC/PCO/W-446 1. Construction of RCC Drain St. From Baitul Noor Boro Mosijid Moor to Balighata Bazar Tinmatha Moor (South Road Side) at Panchbibi Pourashava Ward No-03 (Ch0+000-0+115.00m) 2. Improvement of BC Road Starting from Pollibidut more to upzila Mosque Moor Length- 0+000-0+200.00m, Ward No-0) 3. Rehabilitation of BC Road Starting from upzila Mosque Moore to Jonoshatho Length- 0+000-0+550.00m) Ward No-05. UIIP panchbibi   0.55 0.00 0 61.38 Kalicharan Agarwala 64.43 14/06/2022 21/06/2022 20/06/2023 0 0.00 0 29/09/2022 5.00% Above
173 UIIP-BC/PCO/W-508 Rehabilitation on of RCC Road & RCC drain St from Joypurhat-Panchbibi Road to H/O Chandon Ward No: 02 Ch.0+94.00m. UIIP panchbibi   0.09 0.00 0 17.60 Kalicharan Agarwala 18.64 31/05/2022 07/06/2022 30/05/2022 40 0.00 0 29/09/2022 6.00% Above