Loading...

Greater Pabna & Bogra District Rural Infrastructure Development Project GPBRIDP (2ndRevised)

Components

Sl No. Name of the Components Physical Quantity

(nos/km/m.) Cost as per DPP

(Tk in Lakh)

A. Revenue Component :

1. Manpower 7 persons 114.62

2. Manpower Outsourcing 3 persons 40.61

3. Supply & Services and Repairs, Maintenance & Rehabilitation LS 428.12

B. Capital Component :

4. Transport (Jeep, Pickup and Motor Cycle.) 8 nos 148.50

5. Computer with Accessories 8 nos. 8.00

6. Photocopier 2 nos. 3.00

7. Furniture & Fixtures LS 14.00

8. Land Acquisition/ Purchase 0.00 Acre 0.00

C. Civil works

 9. Rural roads 

(a) Imp. of Upazila Road 112.75 km 6547.43

(b) Imp. of Union Road 168.64 km 10049.50

(c) Imp. of Village Road 175.17 km 9918.62


10 Structures (Bridge/Culverts)

(a) Const. of Structure on Upazila Roads 358.20 m 1674.86

(b) Const. of Structure on Union Roads 925.13 m 4474.10

(c) Const. of Structure on Village Roads 1286.46 m 7184.41

(d) Const. of RCC Road 4.30 km 596.91

(e) Const. of Sub-mersible Road 15.97 km 1993.04

(f) Const. of Slope Protection works 15.01 km 1251.89

(g) Road Widening works 43.79 km. 2217.04

(h) Road Maintenance works 155.37km. 4135.35

Total : 50800.00
At a Glance
Short Title: GPBRIDP
Ministry: LGRD
Executing Agency: LGED
Approval Ref: Memo No: 20.00.0000.346.14.015.15 (Part-1)-282, Dated:05/05/2021
Project Code: 224049300
Sector: Rural
Status: Ongoing Investment Project
Funded By: GOB.
Budget: 50710.00 Lac
Start Date: Oct-2015
Completion Date: Jun-2021
Name of PD: Nayeema Nazneen Naz