Greater Dhaka Sustainable Urban Transport Project (BRT Gazipur-Airport) (GDSUTP)

Project Information Table
Implementing Agency : Local Government Engineering Department
Project Code : 5234
Project Name : Greater Dhaka Sustainable Urban Transport Project (BRT Gazipur-Airport) (GDSUTP)
Name of PD : Md. Mohirul Islam Khan
Date of Approval : 20/11/2012
Starting Date : Dec-2012
Completion Date : Dec-2020
Project Cost : Total GOB PA
23457.33 4418.64 19038.70
Commulative Expenditure : 6300.000 (In Lac Taka)
Physical Progress (%) : 65
Progress Reporting Date : 31/12/2018
Comments : Project will be completed December, 2020

At a Glance
Short Title: GDSUTP
Ministry: LGRD
Executing Agency: Local Government Engineering Department
Approval Ref: 20.00.0000.411.14.01.13-1
Project Code: 5234
Sector: Urban
Status: Ongoing Investment Project
Funded By: GOB.
Budget: 23457.33
Start Date: Dec-2012
Completion Date: Dec-2020
Name of PD: Md. Mohirul Islam Khan