Important 19 (Nineteen) Pourashava Infrastructure Development Project. (INPIDP)

Project Implementation Strategy

The Project is proposed to be implemented over a Three year period. Local Government Engineering Department under Local Government Division (LGD) will be the Executing Agency (EA) for the project along with concerned Pourashavas. A Project Management Office (PMO) with a full-time Project Director from LGED and supporting staff will be established at LGED Head Quarter in Dhaka. Project Director and his staff will get salary and other allowances from the project fund. A Project co-ordination committee (PCC) headed by concerned Pourashava Mayor will be established at the local level. Chief executive officer of concerned Pourashava, representative of R&H, LGED, DPHE, WDB and PDB will be the Members of the committee.Executive Engineer /Assistant Engineer of concerned Pourashava will act as Member Secretary of the PCC. The main responsibility of the PCC is to Co-ordinate the project activities at Pourashava level. Executive Engineer/Assistant Engineer of respective Pourashava will act as the Project Manager for implementation of this project.

For Procurement of all works, goods & Services PPR/2008 will be followed.

At Pourashava level all works will be implemented under direct supervision of Pourashava Engineering Section. Before payment of any bill Project Manager will give a certificate regarding the quality of the work. Regional Superintending Engineer, LGED will supervise the work to maintain the quality of the work. For this purpose copy of work order, drawing & design and work schedule to be supplied to the regional Superintending Engineer of LGED.

Local Govt. Division will release fund in favor of the Project Director. Thereafter the Project Director will sub-allocate necessary fund to the concerned Pourashava. All payment at Pourashava level will be made under the joint signature of Pourashava Chief Executive Officer (CEO) and Pourashava Mayor. A bank account will be opened in each Pourashava at any schedule bank and will be operated by Joints signature of CEO and Mayor of the respective Pourashava. Pourashava authority will draw the fund from Local accounts office as advance by a single receipt voucher and deposited the same in schedule bank account.

The Project Manager will maintain proper accounts of the project fund and face audit by Comptroller and Auditor General (C&AG). 

At a Glance
Short Title: INPIDP
Ministry: LGRD
Executing Agency: LGED & 19 Pourashava
Approval Ref:
Project Code: 224052000
Sector: Urban
Status: Ongoing Investment Project
Funded By: GOB.
Budget: 61213.00 Lac
Start Date: Jan-2010
Completion Date: Dec-2019
Name of PD: Md. Mohir Uddin Shiekh