Southern Country Iron Bridge Reconstruction & Rehabilitation Project (IBRP) (1st Revision)

Project Implementation Strategy

The scheme of the project has been taken from the approved DPP in accordance with the priority of the concern Honorable MP. After then the concerned district Executive Engineer, LGED, Invite tender for selecting contractor following PPR-2008.   
At a Glance
Short Title: IBRP
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 20.00.0000.411.14.11.18-261
Project Code: 224238700
Sector: Rural
Status: Ongoing Investment Project
Funded By: GOB.
Budget: 2334 Crore Taka
Start Date: Jul-2018
Completion Date: Jun-2023
Name of PD: Syed Ahmed Ali