Home
Projects
Digital Map
Road & Market Database
Admin_Login
Loading...
Project Scheme Detail List
SL No.
Package No.
Name
Length (Km)
Allotment (Lac)
Name of Contractor
Contract Amount (Lac)
Date of Commencement
Date of Completion
Physical Progress (%)
Date of Progress Update
Remarks
1
Bhurungamari
1
W.016
Construction of CHAR BHURUNGIMARI UP Complex
90.400
90.400
05/08/2016
100
23/08/2020
FINAL
2
W.406
Construction of BANGO SONAHAT UP Complex
84.900
84.900
06/07/2015
100
23/08/2020
FINAL
2
Chilmari
1
W.202
Construction of RANIGONJ UP Complex
85.230
85.230
19/03/2014
100
23/08/2020
FINAL
3
Fulbari
1
013/246
Construction of kashipur UP Complex
59.000
59.000
18/10/2010
100
23/07/2020
final
2
014/246
Construction of fulbari UP Complex
59.000
59.000
02/02/2011
100
23/07/2020
final
4
Nageswari
1
005/176
Constructio of NARAYANPUR UP Complex
59.000
59.000
13/10/2014
100
06/09/2020
FINAL
2
W.644
Construction of VITORBONDO UP Complex
125.590
125.590
14/02/2020
30
23/08/2020
ONGOING
3
011/246
Construction of ramkhana UP Complex
59.000
59.000
10/07/2013
100
23/07/2020
final
5
Rajarhat
1
W.457
Construction of UMAR MASJIDUP Complex
94.700
94.700
15/06/2017
100
23/08/2020
FINAL
6
Rowmari
1
W.581
Construction of CHAR SHOLMARI UP Complex
117.680
117.680
09/02/2019
90
23/08/2020
ONGOING
7
Ulipur
1
006/176
Construction of buraburi UP Complex
83.500
83.500
20/07/2015
100
06/09/2020
final
2
007/176
Constructio of BEGUMGANJ UP Complex
83.410
83.410
10/03/2014
100
06/09/2020
FINAL
Total :
0.0000 (Km)
1001.41 (Lac)
1001.41 (Lac)