SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bhurungamari
1 W.016 Construction of CHAR BHURUNGIMARI UP Complex 90.400 90.400 05/08/2016 100 23/08/2020 FINAL
2 W.406 Construction of BANGO SONAHAT UP Complex 84.900 84.900 06/07/2015 100 23/08/2020 FINAL
2 Chilmari
1 W.202 Construction of RANIGONJ UP Complex 85.230 85.230 19/03/2014 100 23/08/2020 FINAL
3 Fulbari
1 013/246 Construction of kashipur UP Complex 59.000 59.000 18/10/2010 100 23/07/2020 final
2 014/246 Construction of fulbari UP Complex 59.000 59.000 02/02/2011 100 23/07/2020 final
4 Nageswari
1 005/176 Constructio of NARAYANPUR UP Complex 59.000 59.000 13/10/2014 100 06/09/2020 FINAL
2 W.644 Construction of VITORBONDO UP Complex 125.590 125.590 14/02/2020 30 23/08/2020 ONGOING
3 011/246 Construction of ramkhana UP Complex 59.000 59.000 10/07/2013 100 23/07/2020 final
5 Rajarhat
1 W.457 Construction of UMAR MASJIDUP Complex 94.700 94.700 15/06/2017 100 23/08/2020 FINAL
6 Rowmari
1 W.581 Construction of CHAR SHOLMARI UP Complex 117.680 117.680 09/02/2019 90 23/08/2020 ONGOING
7 Ulipur
1 006/176 Construction of buraburi UP Complex 83.500 83.500 20/07/2015 100 06/09/2020 final
2 007/176 Constructio of BEGUMGANJ UP Complex 83.410 83.410 10/03/2014 100 06/09/2020 FINAL
Total : 0.0000 (Km) 1001.41 (Lac) 1001.41 (Lac)