SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bauphal
1 PWA-UZC- Bauphal-217 Construction of Upazila Complex Extention Building & Hall Room 0.000   0.000 0 19/12/2018 Building Qty: 2
2 Galachipa
1 PWA-UZC- Galachipa-189 Construction of Upazila Complex Extention Building & Hall Room 812.420 SE-AEC (JV) 812.420 24/07/2018 23/07/2019 10 19/12/2018 Building Qty: 2
3 Kalapara
1 PWA-UZC- Kalapara-190 Construction of Upazila Complex Extention Building & Hall Room 753.000 MGU-MRA (JV) 753.000 31/01/2017 24/04/2018 20 19/12/2018 Building Qty: 2
4 Mirjaganj
1 PWA-UZC- Mirzaganj-528 Construction of Upazila Complex Extention Building & Hall Room 461.980   461.980 0 19/12/2018 Building Qty: 2
5 Patuakhali-s
1 PWA-UZC- Patuakhali-S-191 Construction of Upazila Complex Extention Building & Hall Room 517.130 M/S Mohiuddin Ahmed 517.130 100 19/12/2018 Building Qty: 2
6 Rangabali
1 PWA-UZC- Rangabali-245 Construction of Twin Qrtr 0.000   0.000 0 19/12/2018 Building Qty: 1
2 PWA-UZC- Rangabali-244 Construction of UNO Qrtr 0.000   0.000 0 19/12/2018 Building Qty: 1
Total : 0.0000 (Km) 2544.53 (Lac) 2544.53 (Lac)