Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bancharampur
1 PWA-UZC- Bancharampur-74 Construction of Upazila Complex Extention Building & Hall Room 344.090 M/S Tushi & Hazi ALi AKbar(JV) 344.090 14/03/2012 13/03/2013 100 03/07/2019 Building Qty: 2
2 Kasba
1 PWA-UZC- Kashba-75 Construction of Upazila Complex Extention Building & Hall Room 445.000 M/S Business Syndicate International 445.000 12/11/2014 31/10/2018 100 20/12/2021 Complete
3 Nabinagar
1 PWA-UZC- Nabinagar-76 Construction of Upazila Complex Extention Building & Hall Room 344.090 M/S Smriti Enterprise 344.090 27/03/2012 26/03/2013 100 03/07/2019 Building Qty: 2
4 Nasirnagar
1 PWA-UZC- Nasirnagar-77 Construction of Upazila Complex Extention Building & Hall Room 479.680 MBC & MZH (JV) 479.680 13/04/2016 12/07/2017 75 19/12/2018 Building Qty: 2
Total : 0.0000 (Km) 1612.86 (Lac) 1612.86 (Lac)