1 Ruma
1 PWA-UZC- Ruma-65 Construction of Upazila Complex Extention Building & Hall Room 496.430 Mohammad Eunus & Brothers Pvt. Ltd. 496.430 25/01/2016 11/05/2017 65 19/12/2018 Building Qty: 2
2 Thanchi
1 PWA-UZC-OW-10 Construction of Internal Road 21.630 M/S Zawad Enterprise 21.630 0 19/12/2018 Building Qty: 0
2 PWA-UZC- Thanchi-234 Construction of Dormitory 210.660 Mr. U.T.Mong 210.660 28/09/2017 28/10/2018 35 19/12/2018 Building Qty: 1
3 PWA-UZC- Thanchi-232 Construction of UNO Qrtr. 105.470 Mr. U.T.Mong 105.470 15/02/2017 14/02/2018 93 19/12/2018 Building Qty: 1
4 PWA-UZC- Thanchi-64 Construction of Upazila Complex Extention Building & Hall Room 712.640 M/S Zawad Enterprise 712.640 23/10/2014 23/10/2015 100 19/12/2018 Building Qty: 2