SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Ghatail
1 PWA-UZC- Ghatail-134 Construction of Upazila Complex Extention Building & Hall Room 346.620 M/S Das & Kundu Traders 346.620 12/06/2012 11/06/2013 100 19/12/2018 Building Qty: 2
2 Kalihati
1 PWA-UZC- Kalihati-135 Construction of Upazila Complex Extention Building & Hall Room 532.290 PTSL-IB-DURGA Enterprise (JV) 532.290 22/03/2018 21/06/2019 35 19/12/2018 Building Qty: 2
3 Madhupur
1 PWA-UZC- Madhupur-133 Construction of Upazila Complex Extention Building & Hall Room 494.020 M/S Das Traders 494.020 09/04/2017 08/07/2018 82 19/12/2018 Building Qty: 2
4 Mirzapur
1 PWA-UZC- Mirzapur-226 Construction of Upazila Complex Extention Building & Hall Room 387.550 M/S Das Traders 387.550 16/01/2017 15/04/2018 90 19/12/2018 Building Qty: 2
5 Nagarpur
1 PWA-UZC- Nagarpur-137 Construction of Upazila Complex Extention Building & Hall Room 421.160 M/S Syed Mojibor Rahman 421.160 100 19/12/2018 Building Qty: 2
6 Shakhipur
1 PWA-UZC- Shakhipur-136 Construction of Upazila Complex Extention Building & Hall Room 444.360 M/S Das & Kundu (JV) 444.360 06/11/2014 31/01/2016 100 19/12/2018 Building Qty: 2
7 Tangail-s
1 PWA-UZC- OW-07 Construction of Internal Road 18.290 Desh Engineering & Development Agency Pvt. Ltd 18.290 100 19/12/2018 Building Qty: 0
2 PWA-UZC- Tangail-S-138 Construction of Upazila Complex Extention Building & Hall Room 436.720 Md. Abdul Jalil Sarker & M/S Sunve Traders (JV) 436.720 16/11/2014 15/11/2015 100 19/12/2018 Building Qty: 2
Total : 0.0000 (Km) 3081.01 (Lac) 3081.01 (Lac)