Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Dighalia
1 PWA-UZC- Dighalia-153 Construction of Upazila Complex Extention Building & Hall Room 638.650 M/S Azam Construction-MH (JV) 638.650 100 19/12/2018 Building Qty: 2
2 Dumuria
1 PWA-UZC- Dumuria-154 Construction of Upazila Complex Extention Building & Hall Room 752.850 Esha-Mbpl-Mohiuddin (JV) 752.850 20/11/2017 20/11/2018 20 19/12/2018 Building Qty: 2
3 Koira
1 PWA-UZC- Kayra-151 Construction of Upazila Complex Extention Building & Hall Room 440.140 M/S Esha Enterprise 440.140 21/11/2012 20/11/2013 100 19/12/2018 Building Qty: 1
4 Terokhada
1 PWA-UZC- Terokhada-529 Construction of Upazila Complex Extention Building & Hall Room 548.210 M/S Ziaul Traders 548.210 09/08/2017 08/08/2018 15 19/12/2018 Building Qty: 2
Total : 0.0000 (Km) 2379.85 (Lac) 2379.85 (Lac)