SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Mohammadpur
1 PWA-UZC- Mohammadpur-168 Construction of Upazila Complex Extention Building & Hall Room 474.640 Aroma Traders 474.640 100 19/12/2018 Building Qty: 2
Total : 0.0000 (Km) 474.64 (Lac) 474.64 (Lac)