Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Aditmari
1 PWA-UZC- Aditmari-19 Construction of Upazila Complex Extention Building & Hall Room 460.370 M/S Kohinoor Enterprise 460.370 27/02/2018 26/02/2019 75 19/12/2018 Building Qty: 2
2 Hatibandha
1 PWA-UZC- Hatibandha-20 Construction of Upazila Complex Extention Building & Hall Room 326.370 M/S K. A. & H (JV) 326.370 05/02/2012 05/02/2013 100 19/12/2018 Building Qty: 2
3 Lalmonirhat-s
1 PWA-UZC- Lalmonirhat-S-21 Construction of Upazila Complex Extention Building & Hall Room 457.810 MD. Khairul Kobir Rana 457.810 09/06/2016 19/09/2017 65 19/12/2018 Building Qty: 2
Total : 0.0000 (Km) 1244.55 (Lac) 1244.55 (Lac)