Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bahubal
1 PWA-UZC- Bahubal-94 Construction of Upazila Complex Extention Building & Hall Room 533.060 MBC & NB (JV) 533.060 02/03/2017 22/05/2018 5 19/12/2018 Building Qty: 2
2 Baniachong
1 PWA-UZC- Baniachong-96 Construction of Upazila Complex Extention Building & Hall Room 470.050 M/S Haque Trading Corporation 470.050 20/02/2017 12/02/2018 35 19/12/2018 Building Qty: 2
3 Chunarughat
1 PWA-UZC- Chunarughat-95 Construction of Upazila Complex Extention Building & Hall Room 427.080 M/S Shikder Enterprise 427.080 30/04/2015 30/08/2017 95 19/12/2018 Building Qty: 2
4 Habiganj-s
1 PWA-UZC-Habiganj-S-97 Construction of Upazila Complex Extention Building & Hall Room 485.840 MBC & NB (JV) 485.840 05/03/2017 04/09/2018 35 19/12/2018 Building Qty: 2
Total : 0.0000 (Km) 1916.03 (Lac) 1916.03 (Lac)