Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Basail
1 RTIP-II/TAN/GCM-16 Improvement of Ishorganj GCM 1.0000 144.837 M/S. S. Hossain 144.837 07/06/2015 31/07/2017 100 23/12/2018 Final
2 RTIP-II/TAN/RPM-36 Basail-Shakhipur (Nalua) 6.0800 136.761 M/S. Tarafder Builders 136.761 11/03/2013 31/05/2015 100 23/12/2018 Final
3 RTIP-II/TAN/UNR-35 Kashil UP Office-Aisara Bazar via Janjania. 3.8490 282.659 M/S. Amzad Traders 282.659 26/06/2014 31/12/2015 100 23/12/2018  
2 Bhuapur
1 RTIP-II/TAN/RPM-102 b) Tepibari R&H-Gopalpur via Falda Bazar road [Bhuapur portion] 5.3900 80.333   80.333 02/03/2014 21/11/2015 100 23/12/2018  
2 RTIP-II/TAN/UNR-58 Gobindashi UP-Nikrail Bazar Road 3.2700 497.352 Sheik Hemayet Ali 497.352 17/09/2015 08/11/2017 100 23/12/2018  
3 Delduar
1 RTIP-II/TAN/RPM-271 a) Silimpur-Karatia Road 6.7000 145.639 M/S. Friends Construction 145.639 13/08/2015 31/01/2017 100 23/12/2018 Final
2 RTIP-II/TAN/PBMC-10.2 a) Delduar-Lawhati GCC Road. 11.3100 601.948 IDRIS-MITHU-JV 601.948 05/07/2016 04/07/2021 100 23/12/2018  
3 RTIP-II/TAN/UNR-36 Baoikhula Bazar-Nallapara hat via Dubail UP office, Bathuli hat, Fultara Hat Road 10.3360 731.845 M/S. Ajit Kumar Bose & M/S. Taposh Traders JV 731.845 02/11/2014 31/07/2017 100 23/12/2018  
4 Dhanbari
1 RTIP-II/TAN/GCM-29 Improvement of Dhanbari GCM 1.0000 150.677 M/S. Mitu Traders 150.677 29/09/2015 15/11/2017 100 23/12/2018 Final
2 RTIP-II/TAN/UZR-37.1 Dhanbari-Nandina Road 6.0000 685.807 JV of M/S. S. Hossain & M/S. Habib & Co. (S. Hossain-Habib & Co. JV) 685.807 01/09/2015 31/07/2017 100 23/12/2018 Final
5 Ghatail
1 RTIP-II/TAN/RPM-273 a) Pakutia (Deolabari UP office)-Cherabhanga-Deojana Bazar Road 7.5100 191.230 M/S. S. Hossain 191.230 11/06/2015 06/05/2016 100 23/12/2018 Final
2 RTIP-II/TAN/UZR-40-STR-13 Construction of 60 m Long RCC Girder Bridge on Porabari-Angarkhola-Garo Bazar road at Ch. 11+450 km 60.0000 273.001 M/S. Durga Enterprise 273.001 26/03/2015 08/12/2016 100 23/12/2018 Final
3 RTIP-II/TAN/PBMC-10.3 a) Sakhipur-Garo Bazar GC Road 15.2570 834.465 M/S. Haque International-Jalil (JV) 834.465 29/06/2017 28/06/2022 100 23/12/2018  
4 RTIP-II/TAN/UNR-59 Kadamtoli (Digar UP)-Teghory-Maiderchala Bazar Road 6.1850 648.706 Md. Abdus Salam Khan & M/S. Ajit Kumar Bose (JV) 648.706 26/01/2016 30/11/2017 100 23/12/2018  
5 RTIP-II/TAN/UZR-40.2 Porabari-Angarkhola-Garo Bazar Rd. 9.6120 1177.156 M/S. Mahafuz Khan, M/S. Khan & Co. and Classic Builders (M Khan-K C & C Builders-JV) 1177.156 22/04/2015 31/07/2017 100 23/12/2018  
6 RTIP-II/TAN/UZR-40.1 Porabari-Angarkhola-Garo Bazar Rd. 10.0000 1061.946 M/S. Alam Construction & M/S. Syed Mozibor Rahman (JV) 1061.946 12/07/2015 04/12/2017 100 23/12/2018  
6 Gopalpur
1 RTIP-II/TAN/RPM-273 b) Mirzapur UP-Mohanpur hat Road 3.0000 26.285   26.285 11/06/2015 06/05/2016 100 23/12/2018  
2 RTIP-II/TAN/RPM-103 a) Gopalpur-Syedpur road 5.2150 120.771 M/S. Taposh Traders 120.771 03/03/2014 30/11/2015 100 23/12/2018 Final
3 RTIP-II/TAN/RPM-37 Gopalpur-Nalin Hat 6.3500 126.917 S. M. Jahangir Enterprise 126.917 11/03/2013 13/08/2014 100 23/12/2018 Final
7 Kalihati
1 RTIP-II/TAN/RPM-391 Kalihati RHW-Barachowna G.C. Road 10.4200 522.875 Md. Abdus Salam Khan & M/S. Ajit Kumar Bose (JV) 522.875 01/02/2017 20/09/2018 100 23/12/2018 (Transferred from TAN/PBMC-10.1a)
2 RTIP-II/TAN/RPM-104 Suruz GC-Shakhipur Upazila road via Rampur GC road 13.0000 210.558 M/S. Syed Mozibor Rahman 210.558 19/12/2013 31/12/2015 100 23/12/2018 Final
3 RTIP-II/TAN/RPM-38.2 Suruz G.C.-Dhalapara G.C 9.2400 201.476 M/S. Syed Mozibor Rahman 201.476 26/02/2013 25/03/2014 100 23/12/2018 Final
4 RTIP-II/TAN/RPM-38.1 Suruz G.C.-Dhalapara G.C 5.4000 119.684 M/S. Taposh Traders 119.684 10/03/2013 09/03/2014 100 23/12/2018 Final
5 RTIP-II/TAN/UZR-37.2 Kalihati (Dhunail)-Shayahat-Hatia JBA Road 9.4900 1289.923 The Azad Engineers 1289.923 07/01/2016 30/06/2018 100 23/12/2018  
8 Madhupur
1 RTIP-II/TAN/RPM-388 Jalchatra-Solakuri Road 15.5000 698.082 M/S. Sikder Enterprise & Joint Venture Engineers Ltd [(SE & JVEL (JV)] 698.082 06/04/2017 23/10/2018 100 23/12/2018  
2 RTIP-II/TAN/RPM-328 Kakraid-Garohat Road 15.6900 614.986 M/S. Ismail Hossain 614.986 29/09/2016 14/09/2017 100 23/12/2018 Final
3 RTIP-II/TAN/UNR-60-STR-27 Construction of 54 m Bridge at Ch. 0+103 km on Bhaighat-Mirzabari bazar Road 54.0000 252.618 Md. Saiful Islam & M/S. Swarna Bricks JV, [SI-SB (JV)] 252.618 30/08/2016 28/02/2018 93 23/12/2018  
4 RTIP-II/TAN/RPM-102 a) Birtibari R&H (Modhupur Upazila) - Dhanbari GC via Zagirachala road 8.5000 216.270 Md. Abdul Jalil Sarkar & M/S. Sunvee Traders JV 216.270 02/03/2014 21/11/2015 100 23/12/2018 Final
5 RTIP-II/TAN/UNR-60 Bhaighat-Mirzabari bazar Rd 1.9210 151.082 JV of Mitu Traders & Farhan Enterprise (Mitu & Farhan JV) 151.082 29/09/2015 04/06/2017 100 23/12/2018 Final
9 Mirzapur
1 RTIP-II/TAN/RPM-387 Mirzapur-Pakutia GC (Nagarpur Upazila) road 10.7200 321.827 M/S. Sucarcon Traders 321.827 22/05/2017 30/10/2018 100 23/12/2018  
2 RTIP-II/TAN/RPM-276 Pakulla-Lawhati Road Via Bhabkhanda Bazar 9.6500 328.590 Alif Traders 328.590 04/08/2015 09/01/2017 100 23/12/2018 Final
3 RTIP-II/TAN/UZR-39-STR-11 Construction of 69 m bridge at Ch. 10+250km on Hatubhanga-Kaliakore-Fulbaria Road via Khatar Hat road 69.0000 316.579 The Azad Engineers 316.579 07/01/2015 31/01/2018 100 23/12/2018  
4 RTIP-II/TAN/RPM-103 b) Kadim Dhalla RHD-Sawali bazar to Adabari at Natiapara NHW-Kanchanpur GC UZR road 8.0800 194.635   194.635 03/03/2014 30/11/2015 100 23/12/2018  
5 RTIP-II/TAN/UZR-39.2 Hatubhanga-Kaliakore-Fulbaria Road via Khatar Hat road. 8.0180 1028.751 Kamal Associates 1028.751 17/06/2015 30/06/2018 100 23/12/2018  
6 RTIP-II/TAN/UZR-39.1 Hatubhanga-Kaliakore-Fulbaria Road via Khatar Hat road. 6.5000 698.842 Haque Construction & Rahman Construction Joint Venture 698.842 08/10/2014 30/06/2018 100 23/12/2018  
10 Nagarpur
1 RTIP-II/TAN/RPM-272 Nagarpur-Shahjani GC Road 11.9220 352.200 Syed Mozibor Rahman & Abdul Jalil Sarker JV 352.200 19/07/2015 31/05/2016 100 23/12/2018 Final
2 RTIP-II/TAN/PBMC-10.2 b) Lawhati GC-Saturia HQ Road 12.8500 0.000   0.000 05/07/2016 04/07/2021 100 23/12/2018  
3 RTIP-II/TAN/RPM-39 Shahbatpur-Batra Bazar Road via Mailjani 3.8780 81.335 M/S. S. Hossain 81.335 27/02/2013 28/07/2013 100 23/12/2018 Final
11 Shakhipur
1 RTIP-II/TAN/RPM-389 Sakhipur-Kalidash Road 5.7400 192.434 M/S. Shossain and Mohana Nirman Sangstha (JV) 192.434 14/03/2017 21/11/2017 100 23/12/2018 Final
2 RTIP-II/TAN/UZR-38-STR-24 Construction of 42m long RCC Bridge on Barachowna GC-Bhandeshwar GC via Indrajani GC road at Ch. 11+600 km 42.0000 223.651 M/S. Durga Enterprise 223.651 26/03/2015 08/12/2016 100 23/12/2018 Final
3 RTIP-II/TAN/PBMC-10.3 b) Sakhipur-Sagardighi via Barochowna Road 14.6600 0.000   0.000 29/06/2017 28/06/2022 100 23/12/2018  
4 RTIP-II/TAN/PBMC-10.1 c) Sakhipur-Dhalapara via Mohanandapur Road 11.3400 0.000   0.000 09/07/2015 08/07/2020 100 23/12/2018  
5 RTIP-II/TAN/RPM-100 Sakhipur-Sagardighi via Barochowna road 14.6600 343.325 Nise Friends & Rahman JV 343.325 02/03/2014 30/04/2015 100 23/12/2018 Final
6 RTIP-II/TAN/UZR-38 Barachowna GC-Bhandeshwar GC via Indrajani GC Road 11.7180 1145.228 Shamim Enterprise (Pvt.) Ltd. 1145.228 29/12/2014 16/12/2018 90 23/12/2018  
12 Tangail-s
1 RTIP-II/TAN/RPM-329 Dheli-Karatia Suruj Road 7.4700 291.564 M/S. Selim & Brothers- M/S. Nabila Enterprise-(JV) 291.564 17/08/2016 16/08/2017 100 23/12/2018 Final
2 RTIP-II/TAN/RPM-274 Tangail-Kakua Bazar via Dhalanshibpur Bazar, Kakua UP Road 5.9900 266.914 Alif Traders & Arnob Traders JV 266.914 04/08/2015 30/04/2017 100 23/12/2018 Final
3 RTIP-II/TAN/RPM-271 b) Karatia-Silimpur Road 3.8200 104.377   104.377 13/08/2015 31/01/2017 100 23/12/2018  
4 RTIP-II/TAN/RPM-101 Tangail-Aynapur road 9.2900 170.682 M/S. Syed Mozibor Rahman 170.682 02/01/2014 30/11/2014 100 23/12/2018 Final
Total : 588.5310 (Km) 18256.82 (Lac) 18256.82 (Lac)