MGSP/TAN/2015-16/W-05
|
(a) Improvement of road starting from Suruj road Tintala moar to Dewla Kalighor Ch. 00-1270m, under Tangail Pourashava.
(b) Construction of RCC drains with footpath starting from Suruj road Tintala moar to DewlaKalighor Ch. 00-1270(R/S) and Ch. 00-1330(L/S) under Tangail Pourashava.
(c) Supplying, fitting & fixing of Street Lights starting from Suruj road Tintala moar to Dewla Kalighor Ch. 00-1270m in median under Tangail Pourashava.
|
5.1450
|
146856221.960
|
M/s. G.K. Enterprise
|
146856221.960
|
01/09/2016
|
01/04/2018
|
22
|
27/09/2017
|
|
2
|
MGSP/TAN/2015-16/W-04
|
(a) Construction of RCC Drain leading from Adi Tangail Textile Mill to Boro Kalibari Central Drain via Malancha Cinema Hall with Footpath (Partli portion ch. 800-1100) on top on drain under Tangail Pourashava. Ch. 0+000 to 1+110. (Total length-1110.00m)
(b) Construction of RCC Drain leading from Adalat para Biddut Office morh to Central Drain under Tangail Pourashava. Ch. 0+000 to 0+400. (Total length-400.00m)
(c) Construction of RCC Drain starting from Delduar road to Kachuadanga morh via Berabosna Water Tank with waste water treatment facilities near outfall under Tangail Pourashava. Ch. 0+000 to 0+995. (Total length-995.00m)
|
2.5050
|
62562881.930
|
Mohammad Eunus & Brothers (Pvt) Ltd
|
62562881.930
|
01/09/2016
|
31/08/2017
|
37
|
27/09/2017
|
|
3
|
MGSP/TAN/W-03
|
a-i)Improvement of Bypass road leading from kagmari bridge to Tangail Zilla Porishad by WBM & Carpeting under Tangail Pourashava.Ch 0.00m-795.00m . (Total Length = 786.40m)
a-ii) Construction of protective works of Bypass road leading from kagmari bridge to Tangail Zilla Porishad by WBM & Carpeting under Tangail ( Total Length = 785.00m)
b-i) Construction of box culvert at Kagmari bridge to Dighulia bridge Bypass road under Tangail Pourashava. (4.30x4.30) Ch.110.00. (Total Length=4.30m)
b-ii) Construction of box culvert at Kagmari bridge to Dighulia bridge Bypass road under Tangail Pourashava. (4.30x4.30) Ch.400.00. (Total Length=4.30m)
c) Rehabilitation of road starting from Zilla Sadar road pressclub morh to Kagmara Meser Market & kurtubi Madrasa by WBM & carpeting under Tangial Pourashava. Ch-0.00m-2916.00m.(TotalLength =2507.00m)
d) Re- Construction RCC Drain at Zilla Sadar road pressclub morh to Kagmara Meser Market under Tangial Pourashava. Ch 512.00m-822.22m (TotalLength=310.00m)
e) Rehabilitation of Kazipur Main road starting from Shantikunja morh to west Kazipur Primary School by WBM & Carpeting under Tangial Pourashava .Ch.0.00m-2000.00mTotal Length=2000.00m)
f) Rehabilitation of road starting from near the H/O Joaher Ali to Dharerbari road via Enayetpur Eidgah by WBM & Carpeting under Tangial Pourashava .Ch.0.00m-1340.00mTotal Length=1340.00m)
g) Rehabilitation of road starting LGED morh (bailla) to Tangail DC office morh & LGED morh to H/O Azmot Ali by WBM & Carpeting under Tangial Pourashava .Ch.0.00m-940.00m&Link Ch 0.00m-170.00(Total Length=1111.00m)
|
8.8476
|
60260368.000
|
BC-FE (JV) Sabalia,Tangail
|
60260368.000
|
18/11/2015
|
18/06/2017
|
83
|
27/09/2017
|
|
4
|
MGSP/TAN/W-02
|
a) Improvement of road starting from Central Graveyard R&H road to Kazipur main road via Sabujbag Ch.0+000-1+205m & link road Ch.0+644-0+844m by WBM, Carpeting & Seal coat under Tangial Pourashava. (TotalLength =1405m)
b) Improvement of road starting from Alowa R&H road to Bayanpara morh by WBM, Carpeting & Seal coat under Tangial Pourashava.Ch.0+000-0+810m (TotalLength=810m)
c) Improvement of Sakrail Saruti road starting from Omarpur road to Sakrail Bazar by WBM ,Carpeting & Seal coat under Tangial Pourashava .Ch.0+000-1+710m (Total Length=1710.00m)
d) Improvement of road starting from Hazraghat morh to Bailla Madrasa morh by WBM ,Carpeting & Seal coat under Tangial Pourashava.Ch.0+000-1+350m (TotalLength=1350m)
|
5.2750
|
37681613.000
|
Classic Bulders and Khan &Co.(JV)
|
37681613.000
|
05/02/2015
|
04/02/2016
|
100
|
27/09/2017
|
Completed
|
5
|
MGSP/TAN/W-01
|
a) Rehabilitation road from R&H Victoria road to Baray R&H Road via Adi Tangail Textile Mill to Mirarbetka LGED road by WBM Carpeting & Seal coat under Tangail Pourashava. Ch.0+000-3+370m, (Total Length=3370m)
b) Construction of Retaining Wall of Purbo Adalat Para Poura pond at road fron R&H Victoria road to Baray R&H Road via Adi Tangail Textile Mill to Mirarbetka LGED road under Tangail Pourashava. Ch.273. (Total Length = 295.00m)
c) Construction of Beautyfication work & Minipark retaining Wall of Purbo Adalat Para Poura pond at road from R&H Victoria road to Baray R&H Road via Adi Tangail Textile Mill to Mirarbetka LGED road under Tangail Pourashava. Ch.273. (Total Length=273m)
|
3.9380
|
43966175.000
|
SB-NE-(JV)
|
43966175.000
|
19/03/2015
|
|
95
|
27/09/2017
|
|