1
|
SP62046/Sonatala Subproject
|
Re-excavation of Aga Padma Khal (Ch. 0+000 to Ch. 3+216 km) Re-excavation of Aga Padma Khal Br.1 (Ch. 0+000 to Ch. 1+205 km) Re-excavation of Aga Padma Khal-2 (Ch.0+000 to Ch.0+375 km) Re-excavation of Pritambar Khal (Ch. 0+000 to Ch. 2+130 km) Re-excavation of Sonatala Khal (Ch. 0+000 to Ch. 1+110m) Re-excavation of Sonatala Br-1 Khal (Ch. 0+000 to Ch. 0+750m) Re-excavation of Sonatala Br-2 Khal (Ch. 0+000 to Ch. 3+617m) Re-excavation of Sonatala Br-3 Khal (Ch. 0+000 to Ch. 0+460m) Re-excavation of Sonatala Br-4 Khal (Ch. 0+000 to Ch. 0+288m) Const. of 14 Nos Ref. lined Section on 9 Khal, SP Identf. sign board 2 Nos., Demarcation Post 36 Nos. and SP Indication Post 2 Nos. Construction of WMCA office
|
|
199.678
|
Mohammed eunus & Brothers (Pvt.) Ltd
|
199.678
|
30/03/2023
|
30/05/2023
|
100
|
13/08/2024
|
Completed
|
2
|
SP61016/Raybhog Subproject
|
Re-excavation of Rayvog Khal (Ch-0+000km to 0+822km) Re-excavation of Rayvog Branch Khal (Ch-0+000km to 0+535km) Re-excavation of Noli Chargachia Khal (Ch-0+200km to 4+340km) Re-excavation of Noli Chargachia Branch Khal (Ch-0+000km to 2+850km) Re-excavation of Kodom Tola Khal (Ch-0+000km to 3+100km) Re-excavation of Uttar khakbunia Khal (Ch-0+000km to 1+045km) Ref. Lined Section 13 Nos. On 7 Khals, And SP Identf. Signboard (2 nos.) Construction of WMCA office building
|
|
135.772
|
Sayed Ali
Zahanara Begum
|
135.772
|
23/01/2022
|
28/04/2022
|
100
|
13/08/2024
|
Completed
|
3
|
SP43041/Sonbunia Subproject
|
Aga Poddha khal re-excavation(ch.00-4700m) Ungaria khal re-excavation(ch.00-540m) Nolirdon khal re-excavation(ch.00-335m) Referenced line section(7 Nos.) Bamboo bridge (4 Nos.)
|
|
76.149
|
Yunus Akon
Md. Sagir
|
76.149
|
08/04/2019
|
25/05/2019
|
100
|
13/08/2024
|
Completed
|
4
|
SP43034/Potka Khali Subproject
|
Noli Bharani khal re-excavation(ch.2600-5950m) Noli Bharani Branch khal re-excavation(ch.00-2600m) Uttar Dhalvanga khal re-excavation(ch.00-1260m) Golbunia khal re-excavation(ch.00-985m) Tunibaria khal re-excavation(ch.00-700m) Referenced line section(11 Nos.) Bamboo bridge(11 Nos.)
|
|
81.279
|
Shapan
Khaleq
|
81.279
|
01/04/2019
|
25/05/2019
|
100
|
13/08/2024
|
Completed
|
5
|
SP43030/Aylapatakata Sub-project
|
Re-excavation of Lakshman Shikhari Khal (Ch-0+00km to 0+555km) Re-excavation of Panjur Khal (Ch-0+000km to 1+110km) Re-excavation of Gabtali Khal (Ch-0+000km to +720km) Re-excavation of Pakur Gachia Khal (Ch-0+000km to 2+200km) Re-excavation of Kewabunia Khal (Ch-0+000km to 0+990km) Ref. Lined Section 11 Nos. On 5 Khals, And SP Identf. Signboard (2 nos.)
|
|
72.771
|
Sanu Sikder
Sirin
|
72.771
|
28/03/2022
|
29/04/2022
|
100
|
13/08/2024
|
Completed
|
6
|
SP43029/Nur Ali-Burirchar Charakgachia
|
Nolitolar khal re-excavation(ch.00-4500m) Charakgachia khal re-excavation(ch.00-3800m) Referenced line section(8 Nos.) Bamboo bridge(6 Nos.)
|
|
89.071
|
Salma Begum
Md. Sagir Hossen
|
89.071
|
12/03/2019
|
20/05/2019
|
100
|
13/08/2024
|
Completed
|
7
|
SP42024/Nishanbari-Gazi Mahmud Subproject
|
Gazi Mahmud Khal re-excavation (Ch:0.00 - 2900m) Rashidar Khal re-excavation (Ch:0.00 - 975.00m) Nishanbaria Branch-1 Khal re-excavation (Ch:0.00 - 1100.00m) Nishanbaria Branch-2 Khal re-excavation (Ch:0.00 - 500.00m) Const. of 08 Nos. Ref. lined Section on 4 Khals, SP Identf. sign board 2, SP Area Indication Post 2 Nos.
|
|
37.332
|
LCS Secretary : Mst. Sabina Begum
|
37.332
|
27/02/2024
|
28/04/2024
|
100
|
13/08/2024
|
Completed
|
8
|
SP25324/Parir Khal Subproject
|
Amlokitola khal re-excavation(ch.00-6100m) Bain Samerto khal re-excavation(ch.00-2000m) Referenced line section(8 Nos.)
|
|
102.111
|
Sonia akter
|
102.111
|
18/01/2018
|
25/04/2018
|
100
|
13/08/2024
|
Completed
|
9
|
SP15332/Baliatali DR Subproject
|
Bara Balia Tali Khal Re-excavation(ch0.00-1200m) Baliatali Branch Khal Re-excavation(ch0.00-2160m) Agapara Branch Khal Re-excavation(ch0.00-300m) Paler Baliatali Khal Re-excavation(ch0.00-792m) Baliatali Thadamara Branch Khal Re-excavation(ch0.00-480m) Rarir Khal Re-excavation(ch0.00-365m) Ref. Lined Section 8 Nos. On 6 Khals, And SP Identf. Signboard (2 nos.)
|
|
42.705
|
Panu Mollick(President) Abdul Awaual
|
42.705
|
17/02/2021
|
07/04/2021
|
100
|
13/08/2024
|
Completed
|
10
|
SP15290/Maitha Khal DR Subproject
|
Amrajuri Khal re-excavation(ch.00-3500m) Khakbunia Khal re-excavation(ch.00-1485m) Koraitola Khal re-excavation(ch.00-1860m) Khejurtola Khal re-excavation(ch.00-1460m) Ehurchan Khal re-excavation(ch.00-1000m) Referenced Line section(11 Nos.) Bamboo bridge(11 Nos.)
|
|
91.734
|
Shree Nemai Chandra
Md. Atick Hossen
|
91.734
|
12/03/2019
|
18/05/2019
|
100
|
13/08/2024
|
Completed
|