1
|
SP61009/Abdullahpur Subproject
|
WMCA Office & Others Re-exacavation of Buter khal (Ch-3+000khm to 3+710km) Re-exacavation of Chatlakhali Khsl-2 (Ch-0+000khm to 1+025km) Re-exacavation of Meduar khal (Ch-0+000khm to 2+400km) Re-exacavation of Mandar tola khal (Ch-0+500khm to 3+415km) Re-exacavation of Chatlakhali khal-1 (Ch-0+100khm to 2+150km) Re-exacavation of Lamba khali (Ch-0+000khm to 2+400km) Reference Lined sections (13 Nos. ) & Sup-project Identification signboard
|
|
107.698
|
Unus & Brother
|
107.698
|
30/11/2020
|
30/04/2021
|
100
|
13/08/2024
|
Completed
|
2
|
SP43068/Paschim Char Madras Subproject
|
Re-excavation of Baten Khali Khal (Ch-0+00km to 1+850km) Re-excavation of Goldar Khal (Ch-0+000km to 1+050km) Re-excavation of Nawalia Khal (Ch-0+000km to 3+500km) Re-excavation of Hilar Khal (Ch-0+000km to 1+130km) Ref. Lined Section 12 Nos. On 4 Khals, And SP Identf. Signboard (2 nos.)
|
|
62.644
|
LCS
|
62.644
|
21/03/2022
|
30/01/2023
|
100
|
13/08/2024
|
Completed
|
3
|
SP15317/Nilkamal DR & IRR Subproject
|
Guinga Khali Khal Re-excavation(ch0.00-3300m) Nill Kamal Khal Re-excavation(ch0.00-2550m) Mora Gangi Khal Re-excavation(ch0.00-5000m) Reference Line Section (10nos), Subproject Identification signboard (2nos.), Provisional Sum
|
|
85.298
|
LCS-7
|
85.298
|
22/03/2020
|
30/04/2021
|
100
|
13/08/2024
|
Completed
|
4
|
SP15283/South Char Aicha DR & IRR Subproject
|
Dokkhin char aicha khal re-excavation(ch.00-3510m) Referenced line section(4 Nos.) Bamboo bridge(3 Nos.) Kacharir Khal re-excavation (Ch:0.00-3900m) - 2023-24 Dasher Khal re-excavation (Ch:0.00-1920m) - 2023-24 Const. of 08 Nos. Ref. lined Section on 2 Khals, SP Identf. sign board 2, SP Indication Post 2 and Demarcation Post. 36 Nos - 2023-24
|
|
90.381
|
LCS-9
|
90.381
|
24/12/2023
|
30/04/2024
|
83
|
13/08/2024
|
Ongoing
|
5
|
SP15282/Sarujkhali Khal DR Subproject
|
Pangashia Khal Re-excavation(ch0.00-6050m) Surujkhali Khal Re-excavation(ch0.00-1800m) Referenced line section (8 Nos.), SP Identification signboard (2nos.) and Provisional Sum WMCA Office Building
|
|
102.930
|
OTM
|
102.930
|
30/11/2020
|
30/04/2021
|
100
|
13/08/2024
|
Completed
|
6
|
SP15264/Aminabad DR Subproject
|
Manik khali khal re-excavation(ch.00-2800m) Gohin khali khal re-excavation(ch.00-2300m) Referenced line section(6 Nos.) Bamboo bridge(4 Nos.)
|
|
107.113
|
LCS-9
|
107.113
|
04/04/2019
|
30/04/2019
|
100
|
13/08/2024
|
Completed
|