SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Delduar
1 SP35231 Maistha beel Khal Subproject: Re-sectioning of embankment (Ch.0+000km to Ch.2+810km), Re-excavation of Maistha Khal (Ch.0+000km to Ch.0+380km),(Ch.0+400km to Ch.0+530km) 3.3400 60.680 LCS 60.680 0 21/08/2020 Approved
2 Mirzapur
1 SP71003 Kashab khali Khal Subproject: Re-excavation of Kashab khali Khal (Ch.0+000km to Ch.3+110km), Re-excavation of Kashab khali Khal Branch Khal (Ch.0+000km to Ch.0+230km) 3.3000 175.570 LCS 175.570 30/04/2020 83 21/08/2020 Tender approved
2 SP71002 Bagjan Khal Subproject:Bagjan Khal Regulator (Ch.0+100 km), Re-excavation of Bagjan Khal (Ch.0+000km to Ch.3+40km), Re-excavation of Branch Khal (Ch.0+000km to Ch.0+210km) 3.6000 179.160 LCS 179.160 30/04/2020 54 21/08/2020 Tender approved
3 Shakhipur
1 SP35254 Tengra Madla Khal Subproject: Re-excavation of Tengra Madlai Khal (Ch.0+000km to Ch.5+525km), Re-excavation of Tengra Madla Khal Branch Khal (Ch.0+000km to Ch.1+750km) 7.2000 165.890 LCS 165.890 30/04/2020 72 21/08/2020 On going
Total : 17.4400 (Km) 581.30 (Lac) 581.30 (Lac)