SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Bauphal
|
1
|
UIIP/PCO/G-37
|
Implementation & Supply 765 nos Waste Basket (120 ltr) & 10 nos Non-motorized vehicle (van) under Bauphal Pourashava District: Patuakhali.
|
|
39.970
|
RFL Plastrics Limited
|
39.970
|
|
|
0
|
08/10/2024
|
|
2
|
UIIP-BC/PCO/W-579
|
(A). Construction of RCC Road from R&H Road to Qazi Nazrul Islam Saroni Via College Mosque (ch.0.00-250.00m) at ward no-03 Under Bauphal Pourashava, Patuakhali.
(B). Improvement of Carpating Road R&H to Bauphal-Patuakhali BC Sarak Via Jommadder Bari (Janata Road) (ch.1096.00-1963.00=867.00m) at ward no-03 Under Bauphal Paurashava, Patuakhali.
"(C). Improvement of Carpating Road from MB Bridge East side slope of Bauphal -Dhandi BC Sarok ( ch.275.00 +
283 .00m+152.00m=710.00m) at ward no-08 Under Bauphal Paurashava, Patuakhali."
(D). Improvement of Carpating road from Nurul Haq Master house to Noni Mistre Bari Via Salaheya Dinia Complex Madrasha at ward no-06 (ch.0.00-470.00m) Under Bauphal Paurashava, Patuakhali.
|
2.2970
|
274.966
|
M/S Shupty Arman-Mahabub (JV) Swapnil
|
274.966
|
15/02/2024
|
04/02/2025
|
67
|
08/10/2024
|
|
3
|
UIIP-BC/PCO/W-552
|
(a). Construction of shed for public transport Passenger (28.00 spm) at Bauphal Poura Tempu Stand Near H/Q Eng. Faraque North Side od RHD Under Bauphal Pourashava, Patuakhali.
(b). Construction of single storied public Toilet (Type-A) near poraton Samaj kallan Gano Milonatan Under Bauphal Pourashava, Patuakhali
|
|
55.677
|
M/S Mahatab Enterprise
|
55.677
|
25/02/2024
|
14/02/2025
|
22
|
08/10/2024
|
|
4
|
UIIP-BC/PCO/W-559
|
A) Improvement of BC Road from R&H road to South side of Poura end area (Sher-E-Bangla Road) in ward no. 07 ( Ch:0.00-885.00m) under Bauphal Paurashava, Patuakhali.
B) Improvement of BC Road from Shre-E-Bangla road to Md. Yousuf Sarder Bari (Bangla Link Sarak) in ward no. 06 ( Ch:0.00-500.00m) under Bauphal Pourashava, Patuakhali
C) Improvement of BC Road from R&H road to North Side Bangla Bazer Bridge under Bauphal Paurashava in ward no. 07 ( Ch:0.00-173.00m) under Bauphal Pourashava, Patuakhali
D) Construction of RCC Road from Dr. Momin Sarak to Md. Aziz Member Bari via Daspara Dakhil Madrasha in ward no. 09 ( Ch:360.00-512.00m=152.00m) and Link road of Aziz Membar Bari ( Ch:0.00-16.50m) under Bauphal Paurashava, Patuakhali .
|
1.7270
|
127.769
|
DEEP-SAHINOOR (JV)
|
127.769
|
30/04/2023
|
29/04/2024
|
100
|
08/10/2024
|
|
5
|
UIIP-BC/PCO/W-558
|
(A). Construction of RCC Road Bangla Bazer to Napter Khal Via Mohila Collage Bridge Approch end side (Mohila Collage Road) under Bauphal Paurashava in ward No-08. Ch.000-562m)
(B). Construction of RCC Road Napiter Khal Culvert road end point to Jor poll RCC Road in ward No-08. Ch.960.00-1128.00=168m).
(C).Construction of RCC Drain Md. Mahadi House Back side to South side Mrs. Rakha Begum front side via Khalil Bari at ward no.09 Under Bauphal Paurashava, Patuakhali. (Ch.000-548.00m).
|
0.7300
|
211.256
|
M/S Arman Builders & Rupali Construction
|
211.256
|
02/02/2023
|
01/02/2024
|
100
|
08/10/2024
|
|
6
|
UIIP-BC/PCO/W-428
|
A) Improvement of Carpating Sarak From R&H road to Jommader Bari (Janata Sarak) Ch.0.00-2000.00m at ward No-03 under BauphalPaurashava.
B) Construction of BC road from Muslimpara Poura Bhaban Front side to Fredom Fighter Wayadut Mia Sarak Via Basur Bari in ward No.-03 Under Bauphal Paurashava.Ch.0.00-1400.00m & With 02 Nos Box Culvert.
C) Construction of RCC Culvert on Muslimpara BC Sarak front side of Dr. Ramij Uddin Bari in ward No.-05 under Bauphal Paurashava.
D) Construction of RCC Box Culvert on Muslimpara Sarak Near Bot tola in ward No.-03 under Bauphal Paurashava. at Ch.80m.
|
3.4000
|
190.907
|
M/S SH Etnr. & Shupty Cons.
|
190.907
|
10/02/2021
|
09/02/2022
|
100
|
08/10/2024
|
|
7
|
UIIP-BC/PCO/W-427
|
A) Construction of RCC Drain front side of master Monir Existing RCC Drain to East side of Haji Golam Mostofa House under BauphalPaurashava in ward No.-08. Ch.0.00-281.00m.
B) Construction of Muslimpara RCC road from R&H Road to Pauro Bhabon at ward No.-03 under Bauphal Paurashava. Ch.0.00-492m.
C) Construction of RCC road from Sher-E-Bangla Sarak to Chan Mia House at word No.-07 under Bauphal Paurashava. Ch.0.00-64.00m.
|
0.5560
|
147.224
|
M/S Arman Builders & Rupali Construction
|
147.224
|
03/02/2022
|
22/02/2023
|
100
|
08/10/2024
|
|
8
|
UIIP-BC/PCO/W-221
|
A) Contruction of Earth filling & HBB Sarak ward no.-01 Bangabandhu Sarak to ward no.-03 al Modina Jame Mosque via Abdus Samad Jame Mosque under Bauphal Paurosava, District-Patuakhali. Ch. 0.00-1067m.
B) Contruction of RCC Road & Drain from Saha Para existing Drain to Paurosava Bhaban via Councilor Miss Rina Begum House in ward no.-03 under under Bauphal Pourosava, District-Patakhali. Ch.0.00-182m.
C). Construction of RCC Culvert front side of Md. Zakir Surveyer House ward no.-03 under Bauphal Paurosava, District-Patuakhali
|
1.2490
|
109.721
|
Md. Abul Kalam Azad
|
109.721
|
|
30/05/2022
|
100
|
08/10/2024
|
|
9
|
UIIP-BC/PCO/W-274
|
(a). Construction of RCC Digital Sarak to Fakir Bari via A Razzak Fokir, Mulai Fakir, & Athar Gazi in ward-O9, under Bauphal Pauroshava, District: Patuakhali. Ch.000-219m
(b). Construction of RCC Sarak Chairpara Existing RCC road to fredonm fighter AKM khalak mia house in ward -09, under Bauphal Pauroshava, District: Patuakhali. Ch.000-107m.
(c). Construction of RCC Sarak Nazirpur Board School Sarak to Ponchiyed Bari in ward-08, under Bauphal Pauroshava, District: Patuakhali. Ch.000-275m.
(d). Construction of RCC Sarak Nazirpur Board School to Mirda Bari in ward no-08 under Bauphal Pauroshava, District: Patuakhali. Ch.000-141m
(e). Construction of RCC Sarak Kazi Nazrul lslam Saroni Baitul Hamed lame Mosque to Gopal Sill front side Existing RCC road (Sill Para Sarak) via Madop Mondol Bari in ward-03, under Bauphal Pauroshava, District: Patuakhali. Ch.000-348m
|
1.0900
|
127.595
|
M/S Deip Enterprise
|
127.595
|
12/04/2021
|
11/04/2022
|
100
|
27/09/2022
|
0.41%
Less
|
10
|
UIIP-BC/PCO/W-273
|
(a). Construction of RCC Drain Girl School more to Kali Bari Existing Drain via Sakender pesker, Councilor Kabir, Jarnalist Shohag in ward No-04, under Bauphal Paurashava, District: Patuakhali. Ch.000-415m
(b). Construction of RCC Drain & road R&H sarak to Santh Bag Md, Balayet Kanongo Back side Existing RCC Drain via Rngr. Jafor House in ward No07, under Eauphal Paurashava, District: Patuakhali. Ch.000-177m
|
|
121.847
|
M/S Roza & Saom Enterprise - M/S Sawda Enterprise (JV)
|
121.847
|
12/11/2021
|
12/04/2022
|
100
|
27/09/2022
|
0.58%
Less
|
11
|
UIIP-BC/PCO/W-272
|
(a). Construction of BC Sarak Noni Mistary Bari to Md. yousuf Sarder Bari in ward-06, under Bauphal Paurashava, District: Patuakhali. Ch.000-580m
(b). Construction of Hisbullah BC Sarak from yousuf Sarder Bari via Alom Sikder Bari more in ward-06, under Bauphal Paurashava, District: Patuakhali. Ch.000-314m
(c). Construction of BC Sarak from Darun Sunna Sarak to front side of sikder Bari (Bakultala Sarak) in ward-o7, under Bauphal Paurashava, District: Patuakhali. Ch.000-520m
(d). Construction of BC Sarak Dr, momin Sarak to 5ha-E-Bangla Sarak (Assai Sarak) in ward09, under Bauphal Paurashava, District: Patuakhali. Ch.000-488m.
|
1.9020
|
106.563
|
M/s Sh Enterprise & Shupty Construction (JB)
|
106.563
|
12/04/2021
|
11/04/2022
|
100
|
27/09/2022
|
1.08%
Less
|
12
|
UIIP-BC/PCO/W-222
|
Construction of RCC Road & Drain from Romijuddin Sarak to Md. Mannan Khan House ward no.-03 under Bauphal Paurosava, District Patuakhali. Ch. 0.00-475m.
|
0.4570
|
105.214
|
Md. Jamal Hossain
|
105.214
|
|
19/12/2021
|
100
|
27/09/2022
|
1.50%
Less
|
13
|
UIIP-BC/PCO/W-132
|
(A). Construction of RCC Drain Dr. Abul Kalam Farmacy front side of Bauphal khal in ward-04, under Bauphal Pauroshava, District: Patuakhali. ch.000-170m.
(B). Construction of RCC Drain Md. Sultan Ahammad House to North side of Bauphal Khal via Abdul Khalek Police, Md. Sultan Gazi, Jebon Kormokar in ward-03, under Bauphal Paurosova, District: Patuakhali ch. 000-290
|
|
80.615
|
Md. Iqbal Hossain
|
80.615
|
07/09/2020
|
06/09/2021
|
100
|
27/09/2022
|
13.17%
Less
|
14
|
UIIP-BC/PCO/W-131
|
(a) Contruction of Earth filling & HBB Sarak…… Ch.000-670m
(b) Contruction of Earth filling & HBB Sarak…… Ch.000-396m
|
1.0660
|
83.097
|
M/S Arman Builders
|
83.097
|
14/12/2020
|
30/05/2022
|
100
|
27/09/2022
|
1.50%
Less
(Time Extended)
|
15
|
UIIP-BC/PCO/W-130
|
(a) Contruction of Earth filling & HBB Sarak…… Ch.000-518m
(b) Contruction of Earth filling & HBB Sarak……… Ch.000-548m
(c) Construction of RCC Sarak………. Ch.000-225m
|
1.2910
|
92.785
|
M/s Hasan Construction & Shupty Construction (JB)
|
92.785
|
14/12/2020
|
30/05/2022
|
100
|
27/09/2022
|
1.01%
Less
Land Problem for the Scheme No. (b) under this Package
|
|
2
|
Kalapara
|
1
|
UIIP/PCO/G-40
|
Implementation & Supply 863 nos Waste Basket (120 ltr) & 4 nos Non-motorized vehicle (van) under Kalapara Pourashava District: Patuakhali.
|
|
39.980
|
RFL Plastrics Limited
|
39.980
|
09/02/2024
|
08/06/2024
|
0
|
09/10/2024
|
|
2
|
UIIP-BC/PCO/W-561
|
A) Construction of RCC Road Starting from WAPDA Road to Sobahan Sikder Model Academy Road at Ward No-09 Under Kalapara Pourahava, Dist: Patuakhali (Ch. 0.00m to 189.00m)
B) (i) Construction of RCC Drain Starting from WAPDA Road Adv. Abdur Rob House via Jahangir Mridha House via Abdul Awal Shannomot to Ferdous Matubbar House at Ward No-08 Under Kalapara Pourahava, Dist: Patuakhali (Ch. 0.00m to 235.00m)
(ii) Construction of RCC Drain Starting from Kalapara Thana to Press Club at Ward No-02 Under Kalapara Pourahava, (Ch. 0.00m to 85.00m)
|
0.1890
|
105.655
|
AT_JAKIR
|
105.655
|
25/07/2023
|
25/07/2024
|
100
|
09/10/2024
|
|
3
|
UIIP-BC/PCO/W-560
|
Construction of Road by RCC, Starting from RHD Road to Sayed Uddin Super Market via Dak-Bangla Road via Sheikh Kamal Auditorium via Mohila College at Ward No-01 & 02 Under Kalapara Pourahava, Dist: Patuakhali (Ch. 0.00m to 215.00m & 363.00m to 906.00m) Total Length- 758.00m
|
0.7580
|
134.045
|
MD. Kamal Hossain
|
134.045
|
25/07/2023
|
23/04/2024
|
100
|
09/10/2024
|
|
4
|
UIIP-BC/PCO/W-567
|
Improvement of BC Road from Fery Ghat Chowrasta to Shantibagh Road at Ward No: 01, 02 & 06 Under Kalapara Pourashava , District: Patuakhali(Ch. 0.00-1000m)
|
1.0000
|
92.440
|
MZH-ST (JV)
|
92.440
|
09/08/2023
|
01/08/2024
|
100
|
09/10/2024
|
|
5
|
UIIP-BC/PCO/W-538
|
Construction of Parks and Playgrounds under Kalapara Pourashava. Dist. Patuakhali, (Boundary Wall -117.000m , Surface Drain -131.40m , Footpath-131.40, Gate-02no, Ticket Conner -01no , Food Coner -01 no, Toilet-01 no and Bench-15Nos).
|
|
124.010
|
M/S Mahmud Kamal, South Sabujbagh, Patuakhali
|
124.010
|
21/09/2022
|
13/09/2023
|
100
|
09/10/2024
|
|
6
|
UIIP-BC/PCO/W-528
|
A) Construction of Shed for Public Transport Passenger (28.00sqm) at ward No.01 Under Kalapara's Pourashava.
B) Construction of One Storied Public Toilet (Type A=56.00sqm) at ward No.02 Under Kalapara's Pourashava.
C) Construction of One Storied Vegetables & Agricultural Product Market of 5 Storied Foundation (Floor Area=314 sqm) at ward No.02 Under Kalapara's Pourashava.
|
|
198.831
|
ATC-KCD (JV)
|
198.831
|
13/07/2022
|
12/07/2023
|
100
|
09/10/2024
|
15.89%
Less
|
7
|
UIIP/PCO/G-38
|
Implementation & Supply 500 nos Waste Basket (120 ltr) & 25 nos Non-motorized vehicle (van) under Kuakata Pourashava District: Patuakhali.
|
|
39.090
|
RFL Plastrics Limited
|
39.090
|
|
|
0
|
08/10/2024
|
|
8
|
UIIP-BC/PCO/W-522
|
A) Construction of Shed for Public Transport Passenger (28.00sqm) at Kuakata Bus Terminal Front Side Under Kuakata Pourashava.
B) Construction of One Storied Public Toilet (Type A=56.00sqm) at North Panjupara, ward No.08 Under Kuakata Pourashava.
|
|
47.330
|
M/S Mamun Construction
|
47.330
|
23/11/2022
|
15/11/2023
|
100
|
08/10/2024
|
|
9
|
UIIP-BC/PCO/W-521
|
A) Improvement of BC Road from Nilonjona Road (Faraje Bari Mosque) to Anchar Camp (Very Bandth) (Ch:0.00-265.00m) Ward No.-07, Under Kuakata Pourashava, Kalapara, Patuakhali.
B) Construction of 01 Nos X-Culvert (Size 1.35mX1.80m) of BC Road from Nilonjona Road (Faraje Bari Mosque) to Anchar Camp (Very Bandth) at Ch:180m, Ward No.-07, Under Kuakata Pourashava, Kalapara, Patuakhali.(dropped)
C) Improvement of Earthen Road by BC from Mala Para 02 No. Ward BC Road To Sorifpur Primary School West side 01 No. Ward BC Road, (via Habib Soref house), (Ch:0.00-290.00m), Ward No-01, Under Kuakata Pourashava, Kalapara, Patuakhali.
D) Construction of 01-Vent RCC Box Culvert (Size: 2.00m x2.50m) of Mala Para 02 No. Ward BC Road To Sorifpur Primary School West side 01 No. Ward BC Road, (via Habib Soref house) at Ch:150m, Ward No -01, Under Kuakata Pourashava, Kalapara, Patuakhali.
E) Construction of RCC Drain starting from 07 No Ward Rakin Market Field No LGED Training Center (Councilor Asraf Sikder House Front Road Side), (Ch.0.00-200.00m), Ward No.-07, Under Kuakata Pourashava, Kalapara, Patuakhali.
|
0.6670
|
150.376
|
M/S Najmus Shahadat Traders, Patuakhali
|
150.376
|
23/11/2022
|
31/05/2024
|
100
|
08/10/2024
|
|
10
|
UIIP-BC/PCO/W-400
|
A) Construction of RCC Box Culvert (2x4.00mx3.00m) near at Taher Khan Jame Mosque in Asriaon Ward No. 04, Under Kalapara's/ Kuakata Pourashava.
B) Construction of RCC Box Culvert (1x4.30mx3.00m) near at Mr.Kalam & Mr. Afjal house Side Nabinpur Khal in Word No-06, Under Kalapara's/ Kuakata Pourashava.
|
|
71.636
|
M/S Bakshi Enterprise
|
71.636
|
04/03/2021
|
05/03/2022
|
100
|
08/10/2024
|
15.44% Less
|
11
|
UIIP-BC/PCO/W-399
|
Construction of RCC Drain Work Starting from 03 no. Ward Main BC Road (LGED Rest House West Side) to Shohed Nurujjaman Sorok, (Via Elish Park), Under Kalapara's/ Kuakata Pourashava. (Ch-0+000-0+985.00m)
|
|
177.418
|
M/S Libati Traders & Rezwanul Masud (JV)
|
177.418
|
08/03/2022
|
07/03/2023
|
100
|
08/10/2024
|
20.30% Less
|
12
|
UIIP-BC/PCO/W-398
|
A) Construction of RCC Drain Work starting from 80 Ghare Area, Ward No.01, Under Kalapara's/ Kuakata Pourashava. (Ch:0+000-0+572.00m)
|
|
51.897
|
M/S Mayer Doya Enterprise
|
51.897
|
08/03/2022
|
07/03/2023
|
100
|
08/10/2024
|
16.02% Less
|
13
|
UIIP-BC/PCO/W-397
|
Construction of RCC Road Starting From 03 no. ward Main BC Road (LGED Rest House West Side) to Shohed Nurujjaman Sorok (Via Elish Park).Ward No-07, Under Kalapara's/ Kuakata Pourashava. (Ch.0+000-0+380m)
|
0.3800
|
104.093
|
Rezwanul Maksud
|
104.093
|
08/03/2022
|
30/04/2024
|
100
|
08/10/2024
|
15.58% less
|
14
|
UIIP-BC/PCO/W-396
|
Improvement of Earthen Road by the BC from the House of Jabber Chawdary’s Culvert to Wapda Very Bandth at ward No-01, Under Kalapara's/ Kuakata Pourashava. (Ch-1+300m-1+965m)
|
0.6650
|
114.184
|
M/S Delowar Hossain
|
114.184
|
08/03/2022
|
07/03/2023
|
100
|
08/10/2024
|
11.29% less
|
15
|
UIIP-BC/PCO/W-172
|
1. Improvement of Soling & Earthen Road by the BC from Monir Shorif house to Asrayan 03 Three Road More Ch.000m0730m730.00m at Ward No-03 Under Kalapara's/ Kuakata Pourashav Patuakhali.
2. Construction of 01 One Nos of 1-Vent RCC Box Culvart
2.00m x2.50m at Ch-390m Under Kalapara's/ Kuakata Pourashava
Patuakhali
|
0.7300
|
137.305
|
M/S Palli Store
|
137.305
|
05/01/2021
|
31/05/2024
|
100
|
08/10/2024
|
4.50% Less
Work delay because of material carrying problem
|
16
|
UIIP-BC/PCO/W-171
|
1.Improvement of Earthen Road by the BC from the house of
Jabber Chawdarys Culvert to Wapda Very Bandth Ch.690m - Ch. 1300m = 610 m at Ward No -01 Under Kalapara's/ Kuakata Pourashava Patuakhali.
2.Construction of UIIP/BC/PCO/W-17201one Nos of 1-Vent RCC Box Culvart 1.50m x1.80mat Ch-1085.00m at Ward No -01 Under Kalapara's/ Kuakata Pourashava Patuakhali.
3. Construction of 01one Nos X-Drain 0.750x1.80m at Ch1147.00m Ward No -01 Under Kalapara's/ Kuakata Pourashava.
|
0.6100
|
124.654
|
M/S Palli Store
|
124.654
|
05/01/2021
|
31/05/2024
|
100
|
08/10/2024
|
11.58%
Less
Work delay because of material carrying problem
|
17
|
UIIP-BC/PCO/W-170
|
1 Improvement of Earthen Road by the BC from Rahman Kha Mosque To Culvert of Rustum Musully Ch.00 m-690m at Ward No-01 Under Kalapara's/ Kuakata Pourashava. Patuakhali.
2. Construction of 01one Nos of 1-Vent RCC Box Culvart 1.50m x1.80m at Ch- 690m at Ward No -01 Under Kalapara's/ Kuakata Pourashava Patuakhali
|
0.6900
|
125.730
|
M/S Palli Store
|
125.730
|
05/01/2021
|
31/05/2024
|
100
|
08/10/2024
|
11.29%
Less
Work delay because of material carrying problem
|
18
|
UIIP-BC/PCO/W-18
|
Improvement of Soling & Earthen Road by the BC from Toyeb Member house to Mahabub Talukder Sarak Ch.0+00m0+520m = 520.00m at Ward No-08 Under Kalapara's/ Kuakata Pourashava Patuakhali. (Salvage Cost Tk.103664.00)
|
0.5200
|
85.800
|
M/S Palli Store
|
85.800
|
07/10/2020
|
31/05/2024
|
100
|
08/10/2024
|
2.71%
Less
Progress is less due to negligence of the assigned Contractor
|
19
|
UIIP-BC/PCO/W-455
|
A) Construction of RCC 01 ( one) Vent Box Culvert ( 5m x4m x3m) over Kalibari road west side near Yeasin mia House at ward no-01 under Kalapara's Pourashava.
B) Construction of RCC 01 ( one) Vent Box Culvert ( 5m x4m x3m) over Nachnapara Khal near Suny Cottage at ward No.-01 under Kalapara's Pourashava.
C) Construction of RCC 03 ( Three) Vent Box Culvert( 7.55m x3.70m x3m) over Natun Bazar Canal (Atimkhana) near Yosuf mia House at ward No-04 under Kalapara's Pourashava.
D) Construction of RCC Box Culvert (7.8m x 1.5m x 2.4m) Over Chinguria road at ward No.-05 under Kalapara's Pourashava
|
|
89.803
|
M/S Rupali Construction
|
89.803
|
01/02/2022
|
30/01/2023
|
100
|
27/09/2022
|
15.77%
Less
|
20
|
UIIP-BC/PCO/W-454
|
Construction of RCC drain Starting from Baitul Aman Jame Masjid via Nazrul Islam Sarak to Chinguria road at ward No.-04 under Kalapara's Pourashava.Ch.0.00 to 300m.
|
|
63.350
|
M/S Antora Trading co
|
63.350
|
01/02/2022
|
30/01/2023
|
10
|
27/09/2022
|
18.35%
Less
|
21
|
UIIP-BC/PCO/W-453
|
Construction of Rigid Pavement from Chinguria via Pourashava Office to Rahmat Pur Road at ward no-04 & 05 under Kalapara's Pourashava. Ch.0.00m to 1500m.
|
1.5000
|
204.223
|
M/S Rupali Construction
|
204.223
|
07/02/2021
|
30/01/2023
|
100
|
27/09/2022
|
18.64%
Less
|
22
|
UIIP-BC/PCO/W-271
|
(a)Construction of RCC Drain starting from Upazila Hospital via Ad, chunnu Mia house to Old Drain at ward no. 01 under Kalapara's Pourosava. Ch. 0+500m.
(a)Construction of RCC Drain starting from Madrasa Roadvia Mofij Mia house to Naseria Senior Madrasa at ward no. 07 under Kalapara's Pourosava. Ch. 0+280m.
|
|
133.813
|
Md. Kamal Hossain
|
133.813
|
11/01/2021
|
09/01/2022
|
100
|
27/09/2022
|
13.37%
Less
|
23
|
UIIP-BC/PCO/W-270
|
(a)Construction of RCC Drain starting from Kartik Babu house to Bollov Kormokar house at ward no. 05 under Kalapara's Pourosava. Ch. 0+250m.
(b) Construction of RCC Drain starting from west side of Nur Mohammad Sharif house via Jahirul Islam house, Narayon Shill house to Rahmatpur Khal at ward no. 03 under Kalapara's Pourosava. Ch. 0+152m.
(c)Construction of RCC Drain starting from Shamir Pal house to Nimai Sarker house at ward no. 06 under Kalapara's Pourosava. Ch. 0+100m.
|
|
91.701
|
Md. Kamal Hossain
|
91.701
|
11/01/2021
|
09/01/2022
|
100
|
27/09/2022
|
13.97%
Less
|
24
|
UIIP-BC/PCO/W-269
|
(a) Improvement of road by Rigid Pavement starting from Ukil Patti road via Kacha Bazar to WAPDA road at ward no.-02 under Kalapara's Pourosava. Ch. 0+500m.
(b) Construction of RCC Road starting from Razzak Khan house via Girls School to Kabi Nazrul Islam Road at ward no. 04 under Kalapara's Pourosava. Ch. 0+330m.
|
0.5000
|
109.844
|
Md. Kamal Hossain
|
109.844
|
11/01/2021
|
09/01/2022
|
100
|
27/09/2022
|
16.46%
Less
|
25
|
UIIP-BC/PCO/W-268
|
(a) Construction of RCC Road starting from WAPDA Road to Dak Bangla at ward no.-02 under Kalapara's Pourosava. Ch. 0+150m
(b) Improvement of road by RCC work from WAPDA Road via Hamid Munshi house to Kumar Patti road at ward no.-06 under Kalapara's Pourosava. Ch. 0+150m.
(c) Improvement of road by RCC work from East side of Sukh ranjan house to Rakha Chandi Khola at ward no.-05 under Kalapara's Pourosava. Ch. 0+150m.
(d) Improvement of road by RCC work in Golab Bagh road at ward no.-03 under Kalapara's Pourosava. Ch. 0+200m.
(e) Construction of RCC Road starting from Kabi Nazrul Islam Road via Army Khalek Mia house to Razzak Miah House at ward no.-03 under Kalapara's Pourosava. Ch. 0+120m
|
0.7700
|
97.113
|
ATC_ NUR, Puran Bazar, Patuakhali
|
97.113
|
11/01/2021
|
09/01/2022
|
100
|
27/09/2022
|
16.59%
Less
|
26
|
UIIP-BC/PCO/W-267
|
(a) (A) Implementation of Road by RCC work from WAODA road Boro Callbari via Kallbari Box Culvert to Fire Service road at ward no- 01 under Kalapara's Pourosava. Ch. 0+000 to 0+930m
|
0.9300
|
113.116
|
M/S Rupali Construction & Rup Store JV
|
113.116
|
11/01/2021
|
09/01/2022
|
100
|
27/09/2022
|
17.85%
Less
|
27
|
UIIP-BC/PCO/W-94
|
(a) Improvement of RCC road starting from behind Girls school to Adom Ali Master house at ward No.-04 Under Kalapara's Pourashava. Ch. 0.00-230.00m
(b) Improvement of RCC road starting from Kumar Potti road via Naya potti Oilmill Mosjid at ward No.-06 Under Kalapara's Pourashava. Ch. 0.00-240.00m.
(c) Improvement of RCC road starting from Pizus Kanti house via Kishor Vender house to Kobi Nazrul Islam road at ward No.-03 Under Kalapara's Pourashava. Ch. 0.00-340.00m.
(d) Construction of road by rigid pavement from Uttam Karmoker house via Akhrabari to Vojohori Kundo at ward No.-06 Under Kalapara's Pourashava. Ch. 0.00-320.00m.
|
1.1300
|
98.235
|
M/S Bokshi Enterprise
|
98.235
|
15/09/2020
|
20/09/2021
|
100
|
27/09/2022
|
10.61%
Less
|
28
|
UIIP-BC/PCO/W-93
|
(a) Improvement of road by rigid pavement from Madrasha road via Altaf Mia house to Rafique mia house at ward No.-07 under Kalapara's Pourashava. Ch. 0.00 to 640.00m.
(b) Improvement of road by rigid pavement starting from west side Nur-E Jame Masjed Nesaria Sarak to Sohel Mia house at ward No.-09 under Kalapara's Pourashava. Ch. 0.00 to 513.00m.
|
1.1530
|
146.810
|
M/S TM Enterprise
|
146.810
|
29/09/2020
|
28/09/2021
|
100
|
27/09/2022
|
14.19%
Less
|
29
|
UIIP-BC/PCO/W-19
|
1) Improvement of Earthen Road by the BC from Panju Para More To End of Pourashava Area Ch. 2+000m-2+760m = 760m at Ward No-08. Under Kalapara's/ Kuakata Pourashava.Patuakhali.
2) Construction of 01 One No of 1-Vent RCC Box Culvert 1.50mx1.80m Ch.2+00m-2+300m at Ward No-08 Under Kalapara's/ Kuakata Pourashava Patuakhali
|
0.7600
|
148.311
|
M/S Mamun Construction
|
148.311
|
07/10/2020
|
17/12/2021
|
100
|
27/09/2022
|
11.28%
Less
Final bill to be submitted
|
|
3
|
Patuakhali-s
|
1
|
UIIP/PCO/G-39
|
Implementation & Supply 358 nos Waste Basket (120 ltr) & 35 nos Non-motorized vehicle (van) under Patuakhali Pourashava District: Patuakhali.
|
|
39.998
|
|
39.998
|
|
|
0
|
09/10/2024
|
|
2
|
UIIP-BC/PCO/W-534
|
A) Construction of Shed for Public Transport Passenger at 4 Lane Road Circuit House South Side of Patuakhali Pourashava
B) Construction of Shed for Public Transport Passenger at 4 Lane Road Sonali Bank South Side of Patuakhali Pourashava
C) Construction of Single Storied Public Toilet Building (Type A) at 4 Lane Road Circuit House South Side of Patuakhali Pourashava
|
|
69.477
|
M/S Jui Enterprise
|
69.477
|
23/02/2024
|
13/02/2025
|
19
|
09/10/2024
|
|
3
|
UIIP-BC/PCO/W-562
|
A) Construction of RCC Road starting fromAd, Aziz house to Shimulbag Shahadat house in Ward No.03 of Patuakhali Pourashava (Ch: 0.00-260m) and Link Road (Ch : 0.00-110m & Ch:0.00-90.00m).
" B) Construction of RCC Drain Starting from Ad, Aziz
house to Shimulbag Shahadat house in Ward No,03
of Patuakhali Pourashava (Ch: 0.00-260.00m) and Link
drain (Ch:0-200.00m). "
" C) Construction of RCC Road from Town Joinkati Main
Road to Bagan Bari Road (New Salim Mia Zamia Mosque)
at Ward No : 01 of Patuakhali Pourashava
(Ch: 0.00-145.00m). "
" D) Construction of RCC Drain Starting from Sonali Bank
Turning to Tax Office & 01 No. Cross Drain at Ward
No. 08 of Patuakhali Pourashava (Ch: 0.00-275.00m) "
|
0.6050
|
304.610
|
Gazi Al-Mamun-Ayan (JV)
|
304.610
|
03/04/2023
|
27/03/2024
|
85
|
09/10/2024
|
|
4
|
UIIP-BC/PCO/W-450
|
Construction of RCC Drain with footpath at Sabujbag main road from Govt. College Gate-2 to Boy's Hostel with top slab of existing drain in ward No.-04 of Patuakhali Pourashava. (Ch:0.00-500.00m)
|
|
191.445
|
M/S Jakaullah & Brothers-M/S Ayan Entr.
|
191.445
|
28/02/2022
|
22/02/2023
|
88
|
09/10/2024
|
7.79% Above
|
5
|
UIIP-BC/PCO/W-220
|
1) Improvement of Road at Middle Kolatola Sarok Maik Gazi house to Poura BC road (Via Aziz gazi house), ch 0.00-780.0m, Word No-09, Under Patuakhali Pourashava.
2) Construction of 1 Nos Nox Culvert at Middle Kolatola Sarok Manik gazi house to Poura BC road (Via Aziz gazi house), ch 0.00-330.0m, Word No-09, Under Patuakhali Pourashava.
3) Construction of 2 nos Cross Drain (1.00x1.25x10m) at Middle Kolatola Sarok Maik Gazi house to Poura BC road (Via Aziz gazi house), ch 0.00-780.0m, Word No-09, Under Patuakhali Pourashava.
4) Construction of 5 nos 450m Dia UPVC Pipe wit Inlet Pit at Middle Kolatola Sarok Maik Gazi house to Poura BC road (Via Aziz gazi house), ch 0.00-780.0m, Word No-09, Under Patuakhali Pourashava.
|
0.7800
|
135.010
|
Md. Mizanur Alam
|
135.010
|
03/01/2021
|
01/03/2022
|
100
|
09/10/2024
|
8.44%
Above
Progress is slow due to negligence of the assigned Contractor
|
6
|
UIIP-BC/PCO/W-112
|
1 Improvement of Road at Chowrasta Mirzagong Sarak Mosque to South Side Polli Bidut Main Highway Ch 0.00-660.0m Under Patuakhali Pourashava.2 Construction of 5 nos Cross Drain 1.00x1.25x8m on Rigid Pavement at Chowrasta Mirzagong Sarak Mosque to South Side Polli Bidut Main Highway Under Patuakhali Pourashava.
|
0.6600
|
190.173
|
Md. Mizanur Alam
|
190.173
|
|
07/12/2021
|
100
|
09/10/2024
|
4.85%
Above
(Revise Done)
Work delay due to Recast
|
7
|
UIIP-BC/PCO/W-111
|
1 Improvement of Road at Town Kalikapur Amtoly Main Sarok to West Side Gudigata Sarok Via 93 no Govt. Primary School Ch 0.00-450.0 m WordNo-09 Under Patuakhali Pourashava.
2 Improvement of Road at Town Kalikapur 93 no Govt. Primary School to North Side Md. Abu bakor Munci Goni Munci and Ali Munci house Ch0.00-350.0mWord No-09 Under Patuakhali Pourashava.
3 Construction of 5 nos 450m Dia UPVC Pipe wit Inlet Pit at Town Kalikapur 93 no Govt. Primary School to North Side Md. Abu bakor Munci Goni Munci and Ali Munci house Ch0.00-350.0mWord No-09 Under Patuakhali Pourashava.
|
0.8000
|
145.739
|
M/S Kohinoor Enterprise
|
145.739
|
07/04/2020
|
06/04/2020
|
100
|
09/10/2024
|
4.75%
Above
(Revise Done)
|
8
|
UIIP-BC/PCO/W-219
|
1 Improvement of Road at Puran Feery Ghat Main Road to South Side Mirzagong Main Road Muktizodda SarokCh 0.00-760.0 m Under Patuakhali Pourashava
|
0.7600
|
108.552
|
Md. Mizanur Alam
|
108.552
|
03/01/2021
|
28/02/2022
|
100
|
27/09/2022
|
4.41%
Above
|
9
|
UIIP-BC/PCO/W-218
|
1. Improvement of Road at Nondokanai- Mirzagong Main Road to North Side Akusha Sarok ( Ch0.00-435.0m) in Ward No-09 Under Patuakhali Pourashava.
|
0.4400
|
78.055
|
Md. Mizanur Alam
|
78.055
|
03/01/2021
|
28/02/2022
|
100
|
27/09/2022
|
8.34%
Above
(Revise Done)
|
|
Total :
|
32.7620 (Km)
|
6359.06 (Lac)
|
6359.06 (Lac)
|
|
|
|
|
|
|