Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Betagi
1 UIIP-BC/PCO/W-39 Construction of RCC road from Daser Bridge to RCC road via Akon Bari & Wazed commander home at ward no.02 & 03.Ch. 00.00m-1073.00m. 1.0730 93.056 M/S Khan Enterprise 93.056 16/08/2020 15/08/2020 100 28/09/2022 0.10% Less
2 UIIP-BC/PCO/W-406 A) Construction of RCC Drain from (i) Natun Dack Bangla to Khal (Ch:0.00-125.00m) ward no. 06 (ii) Old Drain to Govt Collage (Ch:0.00-150.00m) ward no 05 (iii) Montu Khan’s House to Khal par (Ch:0.00-150.00m) word no 06 Under Betagi Pourashava District: Barguna. B) Construction of RCC Drain from (i) RCC Road to boro Khal via Paltu Comisoner Home (Ch 0.00-40.00m) word no 07 (ii) RCC Road to boro Khal via Babul Kazi Home Ch. 0.00-36.00mm word no 07 (iii) Sankor Home to Hospital Gate (Ch. 0.00-170.00m) word no 07 (iv) Nazmul Huda home to boro Khal (Ch. 0.00-250.00m) word no 05 (v) Sabdar Chand Munsir Mazar to Faysal Home (Ch.0.00-168.00m) word no 08 (vi) RCC Road to baro Khal via Manik Roy Home (Ch. 0.00-250.00m) word no. 07 Under Betagi Pourashava District: Barguna. 171.698 M/S Khan Entr. 171.698 08/11/2022 100 27/09/2022 As Per
3 UIIP-BC/PCO/W-405 A) Construction of 01 No. 1-Vent Culvert size (3.00X3.00)m of Bapari Bari fornt site word no. 03 Under Betagi Pourashava District: Barguna. B) Construction of 01 No. 1-Vent Culvert size (3.00X3.00)m of Samsul Islam Doctor Bari fornt site word no. 09 Under Betagi Pourashava District: Barguna. C) Construction of 01 No. 1-Vent Culvert size (2.00X2.00)m of Sharif Bari fornt site word no. 02 Under Betagi Pourashava District: Barguna. D) Construction of 01 No.1-Vent Culvert size (2.00X2.00)m of Prashanda's Danga word no 03 Under Betagi Pourashava District: Barguna. E) Construction of 01 No. 1-Vent Culvert size (3.00x3.00)m of Habib Comisonar House Khal fornt site word no. 03 Under Betagi Pourashava District: Barguan. F) Construction of 01 No. 1-Vent size (2.00x2.00)m of Dilip House fornt site word no. 02 Under Betagi Pourashava District: Barguna. 79.066 M/S Hakkanur Entr. 79.066 11/08/2022 100 27/09/2022 0.08% Less
4 UIIP-BC/PCO/W-404 A) Construction of RCC Road with Guide wall from Upazila Parished Gate to South Side Upazila Parished Complex (Ch:0.00-124.00m) all side of Upazila Parished Pond (Ch:0.00-360.00m) Upazila Parished to KG School Via DPHE Office (Ch:0.00-260.00m) at ward No.07 (B) Salamer Barir Culvert to Betagi-Niamoti road (Ch:0.00-176.00m) at ward No.03 under Betagi Pourashava District : Barguna Total Length=920m. 0.9200 129.476 M/S Shikder Enterprise 129.476 16/05/2023 32 27/09/2022 0.131% less
5 UIIP-BC/PCO/W-201 A Construction of RCC road form Betagi Niamoti Highway Road to Dafi Howlader Bari via Purbo Betagi Primary School Ch 00.00-518.40 m at Ward no2. Under Betagi Pourashava. B Construction of RCC road form by pass road to Upazila chairman bari Ch 00.00-180.0 m at Ward no9 Under Betagi Pourashava C Construction of RCC work for Khas Kachari Math of Agriculture & Product Market Length-32.00m B-15.00m at ward No. 07 Under Betagi Pourashava. 0.7300 81.236 M/S Khan Enterprise 81.236 28/10/2021 100 27/09/2022 0.22% Less
6 UIIP-BC/PCO/W-200 A Construction of RCC Drain from Captain Selim home to Jelepara Mondir via Govt College to Manik Khan home Ch. 00.00-410.00mat ward No. 05. Under Betagi Pourashava Barguna and ii. Construction of RCC Drain in front of Babul Mia home and kacha bazar to Madrasha Ch 00.00-190.00 m at Ward no 08. Under Betagi Pourashava Barguna B Construction of RCC road from College Pond to Humayun Professor via College Mosque 220.00m Betagi-Patuakhali road to Sayed Jakir home 60.00m College road to Harun Fakir home 75.00m at ward no.05 & 1 No. Ward Carpeting road to Tota Member home 200.00m at ward no. 01 Under Betagi Pourashava Barguna. 1.1500 122.331 M/S Shikder Enterprise 122.331 28/10/2021 100 27/09/2022 0.19% Less
7 UIIP-BC/PCO/W-199 i. Construction of RCC road form Mahasarak to Baro Khal via Mridha Bari Ch 00.00-250.00m at Ward no:4, ii. Construction of RCC road form Food Godown with palasiding (Ch. 90.00-250.00m ) to Mahamudar Gola Via Khal Par 00.00-300.00m at Ward no:1. Under Betagi Pourashava, iii. Construction of RCC road form Hijoltala Primary School to Joynal Fakir home Ch 00.00-100.00m at Ward no:3 Under Betagi Pourashava, Barguna and iv. Construction of RCC road with side Guide Wall form Upazila Quqrter to WAPDA road via Muslim Koloni Ch 00.00-192.00 m at Ward no: 08 Under Betagi Pourashava, Barguna 0.8420 85.287 M/S Hakkanur Enterprise 85.287 01/11/2020 24/10/2021 100 27/09/2022 0.22% Less
8 UIIP-BC/PCO/W-42 A Construction of RCC road form Mahamudar gola to Hafizia Madrasha Ch 00.00-620.0 m at Ward no1 B Construction of RCC road with side Guide Wall Ch. 00.00-35.00m form Rafil Haji bari to Montu commissioner bari via Juwel and Sabina Yeasmin Doly Home Ch. 00.00-275.00m and Biswas bari to Habib commissioner home Ch 00.00-200.0m Total 475.00m at Ward no 03. 1.0950 96.833 M/S Shikder Enterprise 96.833 16/08/2020 15/08/2020 100 27/09/2022 0.07% Less
9 UIIP-BC/PCO/W-41 Construction of RCC road form Basonda Govt. Primary School to Carpating Road Via Dali kandha Pul Ch 00-1132 at Ward no3. 1.1320 98.174 M/S Khan Enterprise 98.174 16/08/2020 15/08/2020 100 27/09/2022 0.05% Less
10 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
11 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
12 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
13 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
14 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
15 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
16 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
17 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
18 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
19 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
20 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
21 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
22 UIIP-BC/PCO/W-40 A. Construction of RCC road with road side Guide Wall form Baily Bridge to By pass Road Via Goni Howlader Bari Ch 00-627 at Ward no 9 B. Construction of RCC road with side Guide Wall Ch. 302.00-332.00m form Baro khaler par to WAPDA road via Mazibar Howlader bari Ch 00.00-332.0 m at Ward no8. 0.9890 86.337 M/S Khan Enterprise 86.337 16/08/2020 15/08/2020 100 27/09/2022 0.10% Less
Total : 19.7990 (Km) 2079.54 (Lac) 2079.54 (Lac)