SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Savar
|
1
|
UIIP-BC/PCO/W-621
|
Improvement of RCC Road starting from Ganda Mr. Roton Matbor Store to Engr. Abul Kalam Azad house in ward no-09, Savar Pourashava, Savar Dhaka
|
|
21.940
|
|
21.940
|
|
|
0
|
17/10/2024
|
|
2
|
UIIP-BC/PCO/W-619
|
Improvement of BC road at starting from Dhaka-Aricha Road Chourongi Super Market to Rajasion Vission Garments in ward no-08 under Savar Pourashava ( Ch.30.00-2565.00m) Salvage Amount=6,24,461.00)
|
2.5350
|
301.320
|
Shikder Builders
|
301.320
|
18/02/2024
|
17/02/2025
|
45
|
17/10/2024
|
|
3
|
UIIP-PCO/BCO/W-471
|
1.Construction of RCC u-Drain Starting from Dhaka-Aricha high way near Talbag Grave yeard to Thana road near woman collage. (Ch- 0.00+000-0+215.00m), in ward no - 06, SavarPourashava, Savar, Dhaka. 2.Improvement of RCC Road from Dhaka-Aricha high way near Talbag Grave yeard to Thana road near woman collage. (Ch- 0.00+000-0+215.00m), in ward no - 06, SavarPourashava, Savar, Dhaka.
|
0.2150
|
75.003
|
Buildex & MNC (JV.)
|
75.003
|
07/05/2022
|
28/04/2023
|
100
|
17/10/2024
|
|
4
|
UIIP-PCO/BCO/W-470
|
Construction of RCC Drain with slab at starting from Dhaka-Aricha Road JamanTreders(Near Rana Plaza) to RobindronathBabu to Mojidpur Road Mridha Bari. (ch-0.00-235.00 m)
2.Construction of R.C.C Road at starting from Dhaka-Aricha Road JamanTreders(Near Rana Plaza) to RobindronathBabu to Mojidpur Road Mridha Bari. (ch-0.00-235.00 m)
|
0.2350
|
72.710
|
M/S JAHAN ENTERPRISE
|
72.710
|
07/05/2022
|
28/04/2023
|
100
|
17/10/2024
|
|
5
|
UIIP-PCO/BCO/W-469
|
Construction of RCC Drain with slab at starting from Kotbari Kamal Garments Road Kobba Mosque to Balumath to Paramount school in ward no - 02, SavarPourashava, Savar, Dhaka. (Ch. 0.00-345.00m)
Construction of R.C.C Road at starting from Kotbari Kamal Garments Road Kobba Mosque to Balumath to Paramount school in ward no - 02, SavarPourashava, Savar, Dhaka. (Ch. 0.00-345.00m)
|
0.3450
|
120.464
|
G2G Tech Limited
|
120.464
|
07/05/2022
|
28/04/2023
|
100
|
17/10/2024
|
|
6
|
UIIP-BC/PCO/W-215
|
1) Improvement of RCC road at Banpukar Main road joynal abedin house to kamal garments road (Ch. 0.00+000-0+505.00m) & Partly Drain top slab, in ward no - 03, Savar, Pourashava, Dhaka2) Improvement of RCC road starting from rajashoin Palowan para more to house to sufia bakary in w and no - 08, Savar Pourashava, Savar, Dhaka (Ch. 0.00+000-0+525.00m)
|
1.0300
|
160.934
|
M/S JAHAN ENTERPRISE
|
160.934
|
03/12/2020
|
25/05/2021
|
100
|
17/10/2024
|
|
7
|
UIIP-PCO/BCO/W-468
|
1.Construction of RCC Drain with slab at starting from Nama Bazar Jet Ghat Road to KheyaGhatFokirstore in ward no - 02, SavarPourashava, Savar, Dhaka. (Ch. 0.00-205.00m) 2.Construction of R.C.C Road at starting from Nama Bazar Jet Ghat Road to KheyaGhatFokir store in ward no -02, SavarPourashava, Savar, Dhaka. (Ch. 0.00-205.00m) 3.Construction of RCC Drain with slab at starting from Nama Bazar Banjaramraic via taramollah to bongsirever (Ch. 0.00-75.00m) & Link-1-tara mollah-vandary (Ch. 0.00-50.00m) & link-2,4,5,6 (Link-2,4,5,6-Ch. 0.00-18.75m x 4= 75.00m) in ward no -02, SavarPourashava, Savar, Dhaka. 4.Construction of R.C.C Road at starting from Nama Bazar Banjaramraic via taramollah to bongsirever (Ch. 0.00-75.00m) & Link-1-tara mollah-vandary (Ch. 0.00-50.00m) & R.C.C Road at link-2,4,5,6 (Link-2,4,5,6-Ch. 0.00-18.75m x 4= 75.00m) in ward no - 02, SavarPourashava, Savar, Dhaka.5.Construction of RCC Drain with slab at starting from Nama Bazar Jonu store to Bongsi River in ward no - 02, SavarPourashava, Savar, Dhaka. (Ch. 0.00-105.00m)
|
0.4050
|
165.179
|
M/S JAHAN ENTERPRISE
|
165.179
|
07/05/2022
|
28/04/2023
|
0
|
27/09/2022
|
work is not started yet.
|
8
|
UIIP-BC/PCO/W-216
|
(1) Improvement of RCC Road Starting from Moddah Rajashion Eidgah more to Soleman Mosque, in w ard no - 08, Savar Pourashava, Savar, Dhaka. (Ch. .00+000-0+600.00m)(2) Construction of RCC Road & Brick Drain up with slab from Savar south para Ad. Usuf shaheb's house to Chandon babu house in ward no-04, Savar Pourashava, Savar, Dhaka. (Ch. 0.00+000-0+301.00m), in ward no-04, Savar Pourashava, Savar, Dhaka.
|
0.9010
|
141.360
|
M/S JAHAN ENTERPRISE
|
141.360
|
03/12/2020
|
30/06/2021
|
100
|
27/09/2022
|
In some ch. Practical width found less then actual width
|
9
|
UIIP-BC/PCO/W-214
|
1) Construction of RCC raod starting form Chapain road ala uddin charman market to dogomora house ara house via samad molla house in w and no-07, savar pourashava, savar, dhaka (Ch. 0.00+000-0.250.00m)2) Construction of RCC road & Vertical extension of Brick drain with slab from bank colony alom shaheb house to thana road mohila college via treepti chanachur more, in ward no -05, Savar pourashava, Savar, Dhaka, (Ch. 0.00+000-0+250m)
|
0.5000
|
87.330
|
Raka Enterprise
|
87.330
|
03/08/2020
|
03/08/2021
|
100
|
27/09/2022
|
In Scheme (1)practical length fond-220m, instead of 250m.
|
10
|
UIIP-BC/PCO/W-71
|
Improvement of R.C.C Road Starting from Imandipur chowrasta mor to Khokon Traders more ch.0600-1350m via councilor house at UpazilaSAVARward no 07 under savar pourashava.
|
0.7500
|
127.360
|
M/S Kofil Enterprise
|
127.360
|
02/08/2020
|
01/08/2021
|
100
|
27/09/2022
|
12.02%
Less
Reivsie Done
Original CA was
11,204,569
|
11
|
UIIP-BC/PCO/W-70
|
A) Construction of RCC Road Starting from Care Bridge to Mohendra ghosh shop in w ard no - 02 Savar Pourashava Savar Dhaka. Ch. 0.00000-0200.00m232672-20-20008
B) Improvement of DBC & RCC Road Starting from Jamsing Nobin Market to Joypara Hasmot Alis house Ch. 0.00000-0500.00m. Link-1 North Jamsing Samsul Aloms hose to Hazi Md. Momtaz Uddin house Ch. 0.00000-0295.00m in ward no - 01 Savar Pourashava Savar Dhaka.
|
0.9950
|
129.416
|
M/S Sumon Enterprise
|
129.416
|
04/08/2020
|
31/08/2022
|
100
|
27/09/2022
|
10.00%
Less
Revised Done
Original CA was
10,267,080
(Time Extended)
|
|
Total :
|
7.9110 (Km)
|
1403.02 (Lac)
|
1403.02 (Lac)
|
|
|
|
|
|
|