1
|
UIIP-BC/PCO/W-624
|
A) Improvement of existing BC road by DC starting from Nagarkasba Ayna Cinema Hall more to Mirkadim Bazar Mosque Ch. 0.00m-1290.00m in ward no 07, 08 & 09 under Mirkadim Pourashava. (Salvage Amount 106236.00 BDT)
B) Improvement of existing damaged brick drain beside road starting from Nagarkasba Ayna Cinema Hall more to Mirkadim bazar Mosque with RCC Ch. 0.00m-110.00m in ward no. 07, 08 & 09 under Mirkadim Pourashava (Salvage Amount 98843.00 BDT)
|
|
161.735
|
|
161.735
|
|
|
0
|
04/11/2024
|
|
2
|
UIIP-BC/PCO/W-608
|
A) Improvement of BC Road from Ramgopalpur Mosque to Rikabibazar Bridge (Ch.+0.00 to +770.00m), Under Mirkadim Pourashava, District: Munshiganj.
B) Improvement of BC Road from Rikabibazar Bridge to Ayna Cinema Hall (Ch.+770.00m to +1340.00m) Including RCC Side Drain Under Mirkadim Pourashava, District: Munshiganj.
|
1.3400
|
200.507
|
Rafiq Construction Co. (Pvt.) Ltd.
|
200.507
|
11/06/2023
|
10/06/2024
|
100
|
04/11/2024
|
|
3
|
UIIP-BC/PCO/W-533
|
(A) Construction of 01 No Box Culvert (2x2.5x3.0x6.0m) Near Rekabi Bazar Fish Market on Rekabi Bazar Main Road Under Mirkadim Pourashava.
(B) Construction of RCC Road from Sipahipara Main Road to Chondontola Bridge at (Ch.00.00 to 0+612.00m) including palasiding work at (Ch.0+333.00m to 0+365.00m & Ch:0+536.00m to 0+612.00m) & R.C.C Drain (Ch:00.00 to 0+125.00m) Under Mirkadim Pourashava, Munshiganj.
|
|
142.319
|
M/S Khan Enterpise
|
142.319
|
27/10/2022
|
27/10/2023
|
100
|
04/11/2024
|
|
4
|
UIIP-BC/PCO/W-430
|
Construction of RCC Road from Rikabi Bazar- Sipahipara main road towards east near H/O Selim at Golapbag (Ch: 0+00 to 0+154m) Link (Ch: 0+00 to 0+076m) towards South near Golapbag mosjid Under Mirkadim Pourashava Munshiganj (Including Side Drain 154.00m)
|
0.2300
|
57.715
|
M/S Khan Enterpise
|
57.715
|
27/10/2022
|
27/10/2023
|
100
|
04/11/2024
|
|
5
|
UIIP-BC/PCO/W-432
|
Construction of RCC Road from H/O Akber at Goppara to Rikabi Bazar Isamoti khal at bot tolar moor opposite site of Sajib telecom including RCC side drain at Ch00.00-30.00m. under Mirkadim pourashava District : Munshiganj.
|
0.3000
|
80.476
|
M/S Samrat Traders
|
80.476
|
05/06/2022
|
04/06/2023
|
100
|
04/11/2024
|
|
6
|
UIIP-BC/PCO/W-431
|
Construction of RCC Road from BADC Godown towards west upto H/O Hanif Bapary at Shariatnagar including side Drain Ch00.00-300.00m under Mirkadim pourashava District : Munshiganj.
|
0.3000
|
96.427
|
M/S Samrat Traders
|
96.427
|
21/06/2022
|
20/06/2023
|
100
|
04/11/2024
|
|
7
|
UIIP-BC/PCO/W-282
|
Construction of RCC Drain from Godi of Eusuf Mia at Kamalarhat to Harishora road via nagarkasba bridge Ch00.00-360.00m.
|
|
52.113
|
M/S Samrat Traders
|
52.113
|
05/07/2021
|
04/07/2022
|
100
|
04/11/2024
|
|
8
|
UIIP-BC/PCO/W-281
|
Construction of RCC Road from Mirkadem Fire Serfvice Office to Saudia Rice Mill at Tilardichor Ch00.00-250.00m.
|
0.2500
|
43.770
|
Rafiq Construction Co (PVT) Ltd
|
43.770
|
05/07/2021
|
04/07/2022
|
100
|
04/11/2024
|
|
9
|
UIIP-BC/PCO/W-280
|
Construction of RCC Road from Mirkadim Fire Serfvice Office to BADC Godown Ch00.00-300.00m.
|
0.3000
|
68.416
|
Rafiq Construction Co (PVT) Ltd
|
68.416
|
05/07/2021
|
29/06/2022
|
100
|
04/11/2024
|
|
10
|
UIIP-BC/PCO/W-278
|
Construction of RCC Drain from Mirkadem Fire Serfvice Office to Saudia Rice Mill at Tilardichor Ch00.00-205.00m.
|
|
29.594
|
Rafiq Construction Co (PVT) Ltd
|
29.594
|
05/07/2021
|
04/07/2022
|
100
|
04/11/2024
|
|
11
|
UIIP-BC/PCO/W-283
|
Construction of RCC Road from Godi of Eusuf Mia at Kamalarhat to Harishora road via nagarkasba bridge Ch00.00-360.00m.
|
0.3600
|
74.021
|
M/S Samrat Traders
|
74.021
|
|
04/07/2022
|
85
|
27/09/2022
|
0.11%
Less
Work done, final bill will be submit, August-22.
|
12
|
UIIP-BC/PCO/W-15
|
Construction of RCC road from Godi of Nizam uddin at Kamalaghat to Munshiganj Polytechnic Institute Ch00.00-300.00m.
|
0.3000
|
97.000
|
M/S Samrat Traders
|
97.000
|
|
25/10/2021
|
100
|
27/09/2022
|
0.15%
Less
Final Bill Done
|
13
|
UIIP-BC/PCO/W-14
|
Construction of RCC Box drain from Godi of Nizam uddin at Kamalaghat to to Munshiganj Polytechnic Institute Ch 00.00-300.00m.
|
|
59.500
|
M/S Redoy Enterprise
|
59.500
|
|
25/10/2021
|
100
|
27/09/2022
|
0.04%
Less
Final Bill Done
|
14
|
UIIP-BC/PCO/W-13
|
Construction of RCC road from house of Salahuddin at Kalindipara to Mirapara main road near Mirapara Mosjid Ch. 00.00-430.00m
|
0.4300
|
84.000
|
Rafiq Construction Co (PVT) Ltd
|
84.000
|
|
27/10/2021
|
100
|
27/09/2022
|
2.36%
Above
Final Bill Done
|
15
|
UIIP-BC/PCO/W-12
|
Construction of RCC drain from house of Salahuddin at Kalindipara to Mirapara main road near Mirapara Mosjid Ch. 00.00-430.00m.
|
|
61.500
|
Rafiq Construction Co (PVT) Ltd
|
61.500
|
|
27/10/2021
|
100
|
27/09/2022
|
0.09%
Less
|