Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Bagha
1 UIIP-BC/PCO/W-495 A) Construction of Shed for Public Transport Passenger (28.00sqm) at Bagha New Bus Terminal Ward No.01 Under Bagha Pourashava Rajshahi. B) Construction of One Storied Public Toilet (Type A=56.00sqm) at Bagha Upazilla Health Complex Ward No.07 Under Bagha Pourashava Rajshahi. C) Construction of One Storied Vegetables & Agricultural Products Market of 5 Storied Foundation (Floor Area=314 sqm) at Bagha Hat Area Ward No.01 Under Bagha Pourashava Rajshahi. 150.516 Liton Traders & M/S Mamun Traders (JV) 150.516 01/07/2022 30/06/2023 20 27/09/2022 5.90% Less
2 UIIP-BC/PCO/W-413 (A)Improvement of Road with RCC from Pakuria BC Road To H/O Shohidul Islam at Pakuria Ward No-02 Under Bagha Pourashava Bagha Rajshah. Ch.( 0+000 - 0+ 460)m. (B)Rehabilitation of BC road from Sorokghat Pakuria BC road near at Mr.Serajul Islam House to Mr. Mazdar Dofader House at kaligram word no-03 under Bagha pourashava Bagha Rajshahi Ch:(0+090-0+810)m. (C)Rehabilitation of BC road from Murshidpur Kheya Ghat to Narayonpur Bazar GC road at ward no-04 05 & 09 Under Bagha Pourashava Bagha Rajshahi. Ch.(0+000 - 1+500)m. (D)Rehabilitation and widening of BC road from Bagha-Arani main road to Nischintapur Jame mosque at word no- 07 Under Bagha Pourashava Bagha Rajshahi Ch:(0+000-0+570)m. (E)Improvement of road with BC from Bagha lalpur main road near Bottola to land of Mr.Chanda to South Milikbagha at word no-08 Under Bagha PourashavaBagha Rajshahi Ch:(0+000-0+402)m. (F)Rehabilitation of BC road from Mr.Sakandor Ali House to Mr. Abdur Razzaq house near at Monmohon Primary school at word no-09 Under Bagha Pourashava Bagha Rajshahi Ch:(0+000-0+440)m. 4.1820 229.085 MM Development Engineering LTD. 229.085 10/03/2022 09/03/2023 10 27/09/2022 18.27% Less
3 UIIP-BC/PCO/W-412 Construction of RCC drain from Mr. Rafique house to Existing Box Culvert and toward Padma River side at South Gaonpara at Ward No-05 Under Bagha Pourashava Bagha Rajshahi Ch: (0+000 - 0+577)m. 77.710 MM Development Engineering LTD. 77.710 02/03/2022 09/03/2022 0 27/09/2022 20.036% Less
4 UIIP-BC/PCO/W-411 Improvement of Road with BC from Bagha Brack office to at Hat Bolihar Government Primary School road at Bolihar ward no-1 Under Bagha Pourashava Bagha Rajshahi. 1.3150 95.669 M/S Shammy Enterprise 95.669 10/03/2022 09/03/2023 15 27/09/2022 19.57% Less
5 UIIP-BC/PCO/W-165 Construction of RCC Road from Mr. Anarul Islam house to Mr. Abdul Mannan house at Pakuria at ward no.02 under Bagha Pourashava, Bagha, Rajshahi. Ch:(0+000-0+640)m. 0.6400 68.302 M/S Hossain 68.302 13/12/2021 100 27/09/2022 27.50% Less, Final Bill Done
6 UIIP-BC/PCO/W-164 Improvement of Road with BC from Bagha-Arani BC Road to Bolihar more BC Road at Ward No: 06 & 01 Under Bagha Pourashava, Bagha, Rajshahi. Ch: (0+000-1+200)m. 1.2000 95.647 M/S Hossain 95.647 13/12/2021 100 27/09/2022 18.50% Less, Final Bill Done
7 UIIP-BC/PCO/W-163 (A)iConstruction of Road with BC from Mr.Mokbul Hossain house to Mr.Kamal Mondal house at Jotsayesta& From Mr. Abul Hossain house to Musidpur Dakkinpara Jame Mosque at Musidpur at Ward no.09 under Bagha Pourashava, Bagha,Rajshahi. Ch: (0+000-0+600)m& Ch: (0+000-0+100)m. (ii) Construction of RCC Road crossing drain at Ch: (0+350)m. (B) Construction of RCC drain near at Bottoly old drain forward east along Bagha-Lalpur Highway road at Baniapara at Ch:(0+000-0+120)m at ward No.08 under Bagha Pourashava, Bagha, Rajshahi. (C) Construction of RCC drain near at Mr.Mahabul house at Kaligram Westpara at Ch:(0+000-0+030)m & near at Mr.Akram Ali house at Kaligram Kazipara at Ch:(0+000-0+030)m at ward No.03 under Bagha Pourashava, Bagha, Rajshahi. 0.7000 77.149 M/S Hossain 77.149 20/12/2020 09/12/2021 95 27/09/2022 21.49% Less, Final Bill Done
8 UIIP-BC/PCO/W-162 (A) Construction of BC Road at Bagha Upazila Healh Complex at Uttor Milikbagha at ward No.07 under Bagha Pourashava, Bagha, Rajshahi. Ch:(0+000-0+210)m. (B) Construction of RCC Road from Mr.Shahidul Islam house to Mr.Mokbul hossain house,Baniapara Graveyeard, Caigary Pond to Late Kader Master house at Baniapara at ward No.08 under Bagha Pourashava, Bagha, Rajshahi. Ch:(0+000-0+470)m. (C) Construction of Road by BC from Mr.Karim house to Sree Assini Shah house at Pakuria Shahpara at ward no.02 under Bagha Pourashava, Bagha,Rajshahi. Ch: (0+000-0+400)m. 1.0800 74.513 M/S Hossain 74.513 20/12/2020 09/12/2021 100 27/09/2022 18.50% Less
9 UIIP-BC/PCO/W-143 (A) Construction of BC road from Mr.Shafi house via BaliharJame Mosque & Mr. Hasem Ali house to Mr. Ainal Ali house at Balihar at ward No.01 under BaghaPourashava. Ch:(0+000-0+360)m. (B) Construction of R.C.C Palisading workat Mr.Tozammel Haque pond side at South Gaonpara at ward no.05 under BaghaPourashava, Bagha,Rajshahi.Ch: (0+000-120)m. (C) Construction of road with B.C from BaghaUpazila Election office to BaghaUpazila Police station gate at ward no.06 under BaghaPourashava.Bagha,Rajshahi. Ch: (0+000-0+205)m. (D) Construction of R.C.C coverd drain from Mr.Mominul Islam Mill house via Mr. Hossain Ali house to Mr.Masud shop at UttorMilikbagha at ward no.07 under BaghaPourashava, Bagha,Rajshahi.Ch: (0+000-0+300)m. 0.6850 82.335 Fariva Auto 82.335 08/10/2020 07/10/2021 100 27/09/2022 1.00% Less
10 UIIP-BC/PCO/W-100 (A)iConstruction of RCC road from Sree Sunil house to Mr. Kalim Uddin house at Hat Balihar at ward No.1 under Bagha Pourashava. (Ch 0+000-0+240)m.(ii) Construction of RCC Palisading work at (Ch 0+030-0+100)m, (Ch 0+110-0+170)m, (Ch 0+190-0+220)m.B) Construction of BC road from Mr Akkal Ali House via Mr. Moser Ali house to Malitapara Jame Mosque road & Mr. Mahabub house road Malitapara & Mr. Mozir Uddin house road at Karigorpara at ward No. 02 under Bagha Pourashava.(Ch 0+000-0+544)m. 0.7840 69.697 Fariva Auto 69.697 08/10/2020 07/10/2021 100 27/09/2022 1.00% Less, Final Bill Done
11 UIIP-BC/PCO/W-99 (A)iConstruction of RCC drain from Mr.Tozammel Haque Pond via Mr. Abu Hossain house to Mr.Motaleb Ali house at South Gaonpara at ward no.05 under Bagha Pourashava Rajshahi. (Ch 0+000-0+260)m. (ii) Road crossing drain at (Ch 0+060)m & (Ch 0+215)m.(B)i Construction of RCC road from Mr.Bokul house to Mr. Altaf Ali house at Chalk- Ahammedpur at ward No.06 under Bagha Pourashava (Ch 0+000-0+600)m.(ii) Construction of RCC Palisading work at (Ch 0+455-0+520)m.(iii) Construction of road crossing drain at(Ch 0+210)m & (Ch 0+485)m. 0.8540 105.987 Fariva Auto 105.987 08/10/2020 07/10/2021 95 27/09/2022 1.00% Less, Final Bill Done
12 UIIP-BC/PCO/W-98 (A)i Construction of RCC road from Mr. Bikom Master house to Mr. Muku house at Kaligram at ward No.03 under Bagha Pourashava.(Ch 0+075-0+345)m. (ii) Construction of RCC Palisading work at (Ch 0+285-0+310)m. (B) Construction of RCC road near at Doctor Sree Mithun house at Ghospara& from Sarakghat-Pakuria BC road to Kalidaskhali High School & Primary School road at Kaligram at ward No.03 under Bagha Pourashava. (Ch 0+000-0+100)m. & (Ch 0+000-0+150)m. (C) Rehabilitation of BC road from Sree Bhobash Pandey house to Dairitola Jame Mosque at Chalk-Narayanpur at ward no.04 under Bagha Pourashava, Rajshahi. Ch:(0+000-0+555)m. (D) Construction of RCC drain from Mr. Dulal Professor house to Dairitola Jame Mosque at Chalk-Narayanpur at ward no.04 under Bagha Pourashava, Rajshahi.(Ch 0+000-0+330)m. 1.0750 101.645 Fariva Auto 101.645 08/10/2020 07/10/2021 100 27/09/2022 1.00% Less, Final Bill Done
13 UIIP-BC/PCO/W-296 Construction of Rcc Box Culvert Ward no 01-09 Under Arani Pourashava,Bagha ,Rajshahi 85.071 Bashundra House Builder 85.071 08/03/2022 07/03/2023 30 27/09/2022 25.19% Less
14 UIIP-BC/PCO/W-295 Rehabilitation & Widening of station road & In side of arani Bazer ch 000-2750 ward no 04,06 Under Arani Pourashava,Bagha,Rajshahi 2.7500 187.110 Bashundra House Builder 187.110 08/03/2022 07/03/2023 90 27/09/2022 26.65% Less
15 UIIP-BC/PCO/W-294 1 Construction of B/C Road i) In Kusabari from h/o Jillu to Jamnagar Ghat & j/o Nuruzzaman Ch.000-0920. ii )From Kusabari Main Road near Eid Ghah to h/o Yousuf Ch. 000-0250. iii) In Shahpur from Main Road to h/o Rahman Shah Ch.000- 0600 ward no. 01 05 under Arani Pourshava Bagha Rajshahi. 1.7700 121.626 Bashundra House Builder 121.626 08/03/2022 07/03/2023 80 27/09/2022 22.76% Less
2 Bagmara
1 UIIP-BC/PCO/W-344 Construction Box Culvert on Mothurapur Khal Near Younus house at word no 04 under Taherpur Pourashava, Rajshahi. 31.154 Md. Anwar Hosain, Bisupara 31.154 07/06/2021 30/05/2022 100 27/09/2022 0.49% Less
2 UIIP-BC/PCO/W-343 Construction of Rcc road from Mothurapur Idris House to Pabnapara Road & front of Hafiz Master house (ch.00-570m) under Taherpur Pourashava, Rajshahi. 0.5700 71.981 Md. Mamunur Rashid Khan 71.981 07/06/2021 30/05/2022 100 27/09/2022 0.50% Less
3 UIIP-BC/PCO/W-342 Extention & Re Construction of Dense Carpeting road with Retaining wall from Jamgram Korim shop to Gaidoa Mosque (ch.00-2100m) under Taherpur Pourashava, Rajshahi. 2.1000 160.214 Md. Anwar Hosain, 160.214 07/06/2021 30/05/2022 100 27/09/2022 0.40% Less
4 UIIP-BC/PCO/W-341 Construction of Rcc road with Retaining wall front of Basiapara Mosque, Palisading Basiapara Ibrahim Pond (Ch 00-75m) under Taherpur Pourashava, Rajshahi. 0.0750 33.457 M/S Rifath Enterprise 33.457 07/06/2021 30/05/2022 100 27/09/2022 0.50% Less
5 UIIP-BC/PCO/W-340 Construction of Rcc Retaining wall & pointing road Front of Poura Tohsil Office Pond to high school mosque(ch140-240m). under Taherpur Pourashava, Rajshahi. 0.1000 65.126 M/S Rifath Enterprise, Md. Rafiqul Islam Pk 65.126 07/06/2021 30/05/2022 100 27/09/2022 0.30% Less
6 UIIP-BC/PCO/W-339 Construction of Rcc Covered Drain from Chokirpara Moajjem shek house to Main Drain (ch.00-130m) under Taherpur Pourashava, Rajshahi. 0.1300 29.883 Md. Abu Bakkar Mridha Munsur 29.883 07/04/2022 100 27/09/2022 0.40% Less
7 UIIP-BC/PCO/W-338 Construction of Rcc road with drain from Poura Auditorium to Main road near Police Fari Ch 00-250m under Taherpur Pourashava, Rajshahi. 0.2500 58.332 Md. Abu Bakkar Mridha Munsur 58.332 07/04/2022 100 27/09/2022 0.45% Less
8 UIIP-BC/PCO/W-213 a) Re-Construction of Rcc road from Koalipara Primary School to Rosulpur Mosque under Taherpur Pourashava (ch.00-600). B)Construction of Rcc road from Nurpur Rhaman more to Patketola more (ch 00-950m) under Taherpur Pourashava, Rajshahi. 0.6000 155.127 M/S Mishad International 155.127 23/08/2021 100 27/09/2022 0.37% Less
9 UIIP-BC/PCO/W-212 a)Construction of Rcc Road from Chankhali Bridge to mohongonj main road, under Taherpur Pourashava, (ch00-850m).b)Construction of Rcc road from Poura Auditorium to Mohongonj main road via Mohila collage under Taherpur Pourashava, (ch 00-1000m) 1.8500 172.018 M/S Mishad International 172.018 23/08/2021 100 27/09/2022 0.23% Less
10 UIIP-BC/PCO/W-47 Construction of Rcc Retaining wall & road Front of Poura Tohsil Office to high school mosque under Taherpur Pourashava, Rajshahi. 0.1400 64.764 Md. Mamunur Rashid Khan 64.764 22/07/2021 100 27/09/2022 4.38% Above
11 UIIP-BC/PCO/W-46 (A) Construction of Rcc Covered drain from LGED Godawn to River via Piaz hata mosque under Taherpur Pourashava, (ch220-440m).(B) Construction of 9 Nos Rcc road from- (a) Jamgram mosque to Bahar house, (ch. 00-325m) (b) RosulpurSefatulla house to Akkas house,(ch. 00-270) (c) Amtoli Mosque to Sohel house, (ch.00-m160) (d) Front of Munsur house, (ch. 00-50m) (e) RosulpurRoidul house to Salam house, (ch.00-130) (f) Side of Jomuna Shoe room, (ch.00-130) (g) Front of JalaparaMondir(ch.00-145) (h) JamloiLalu house to Somser house.ch.(00-150) (i) BisuparaSohidkhondokar main rode ch. (00-180 1.4900 163.791 Md. Abu Bakkar Mridha Munsur 163.791 22/07/2021 100 27/09/2022 4.30% Above
12 UIIP-BC/PCO/W-45 (A) Construction of Rcc Covered drain from Horitola more to LGED Godown under Taherpur Pourashava, (ch00-220m). (B) Re-Construction of Dens carpeting road with Retaining wall from Dighipara Babul house to Hejatipara Mojnu house, (ch. 00-1500m). 1.5000 142.986 M/S Rifath Enterprise 142.986 22/07/2021 100 27/09/2022 4.47% Above, Revise Done
3 Paba
1 UIIP-BC/PCOW-245 (a) Construction of RCC Drain Starting Form Dawonpara EID-GHA to Bakrabaz UttorPara Culvert (Ch.00m - 680.00m) Under Katakhali Pourashava, District Rajshahi. (b)Improvement of DC Road Starting from Samsadipur H/O Monju member to H/O Arshad (Ch.00m -230.00m) by Bituminous Dense Carpeting (DC) RCC Retaining Wall under Katakhali Pourashava, District Rajshahi. 0.2300 124.528 MD. Abdul Mannan 124.528 15/02/2021 15/10/2021 90 27/09/2022 12.55% Less, Due to heavy rain, flood and contractor's negligence work is delayed
2 UIIP-BC/PCOW-244 (a) Improvement of RCC Road Starting from shyampur Boubazar (Ch.00m-470.00m) Under Katakhali Pourashava, District: Rajshahi. (b) Improvement of RCC Road Starting from shyampur thandar para Mosque to Beribadh Bottula (Ch.00m-200.00m) With Retaining Wall Under Katakhali Pourashava, District: Rajshahi. (c) Improvement of RCC Road Starting from Samsadipur Islam Road to Grareg Road ( Ch.00m-250.00m) Under Katakhali Pourashava, District: Rajshahi. (d) Improvement of RCC Road Starting from Hajrapokur Koayl Pond to H/O Shafi uddin (Ch.00m-200.00m) Under Katakhali Pourashava, District: Rajshahi. 1.1200 96.331 M/S Mamun Traders 96.331 15/02/2021 25/06/2022 90 27/09/2022 13.100% Less (Time Extended) Due to heavy rain, flood and contractor's negligence work is delayed
3 UIIP-BC/PCOW-243 (a) Rehabilitation of BC Road Starting from shympur Sayad more to Box Calvert (Ch. 00m -300.00m) by Bituminous Dense Carpeting (DC) Under Katakhali Pourashava, District: Rajshahi. (b)Improvement of DC Road Starting from Shympur Azizur more to Boain shop (Ch.00m -320.00m) by Bituminous Dense Carpeting (DC) RCC Retaining Wall under Katakhali Pourashava, District Rajshahi 0.6200 54.057 M/S Mamun Traders 54.057 15/02/2021 25/06/2022 90 27/09/2022 13.11% Less (Time Extended) Due to heavy rain, flood and contractor's negligence work is delayed
4 UIIP-BC/PCO/W-79 (A)Construction of Two Vent Box Culvert (box size4.0mx4.0m) At near Bakrabag Hossin House Cannal Under Katakhali Pourashava, District; Rajshahi. (b) Construction of RCC Box Drain Strting Form West Comer of Maskatadinghi Hi-School to Horian Cannel (Ch. 00-232.00m) Under Katakhali Pourashava, District; Rajshahi. ( c) Rehabilitation of DC Road Starting from Hajrapukur H/O Shafiuddin to Shop of Rejaul (Ch. 00-150.00m) by Bituminous Dense Carpeting (DC) Under Katakhali Pourashava, District; Rajshahi. 0.1500 100.900 MD. Abdul Mannan 100.900 28/02/2022 90 27/09/2022 10.09% Less (Time Extended) Due to heavy rain, flood and contractor's negligence work is delayed
5 UIIP-BC/PCO/W-43 (A) Rehabilitation of BC Road Starting from Dawonpara Eid-Gha to Bakerbaz Uttor Para Culvert via katakhali Bazar (Ch.00m-945.0m) by Bituminous Dense Carpeting (DC) under Katakhali Pourashava, District: Rajshahi. (B)Rehabilitation of BC Road Starting from Maskatadighi Shop of Samsul to Shop of Zillur (ch.00-370.00m) By Bituminous Dense Carpeting (DC) With RCC Reataining Wall under Katakhali Pourashava, District: Rajshahi. 1.3150 101.224 MD. Abdul Mannan 101.224 28/02/2022 90 27/09/2022 10.08% Less (Time Extended) Due to heavy rain, flood and contractor's negligence work is delayed
Total : 29.2750 (Km) 3247.94 (Lac) 3247.94 (Lac)