SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Daganbhuiyan
1 UIIP-BC/PCO/W-310 A) Construction Of Box Culvert Double vent From Freedom Fighter Abdul Malak Road, Word No 3. CH: 0.00m-10.00m B) Construction of box Culvert Double Vent From Mayor Omar Faruk Khan Road, Word no 3. Ch0.00m- 10.00m 104.993 M/S Century Traders 104.993 15/04/2021 14/04/2022 100 27/09/2022 0.75% Less ( Final bill done)
2 UIIP-BC/PCO/W-309 A )Construction of RCC Drain From Feni Road to Nipu Bhaban Word No: 9 Ch 0.00 - 228.5m B) Construction of RCC Drain From Feni Road to Nipu Bhaban to Faziler Ghat Link Road Word No: 9 : Ch 228.5m - 457mC) Construction Of RCC Drain from Nur Masjid Road, word no 3 . Ch 0.00m- 305.00mD) Construction Of RCC Drain From Sudra Bari (Alipur Road) to Dadnar khal Word no 3. Ch 0.00m-300m 234.567 M/S Chowdari Enterprise 234.567 18/04/2021 01/07/2022 80 27/09/2022 0.11% Less ( Due recast in PCO)
3 UIIP-BC/PCO/W-308 A) Rehabilitation and widening of bitumenous Carpeting of Faziler Ghat Link Road, word No :9 Ch 0.00m - 475.00m B) Rehabilitation and Widening of Bitumenous Carpeting Road From Nur Mosjid to Sultan miar Bari, Word No :3 Ch: 33m- 275.00m 0.7170 65.338 M/S Chowdari Enterprise 65.338 18/04/2021 01/07/2022 0 27/09/2022 0.04% Less ( Due recast in PCO)
4 UIIP-BC/PCO/W-187 Improvement of Bitumenous Carpeting Road from Feni road (Gonipur Bazaar) to Udrazpur Ruhul Amin Shop W-8 Ch:0.00m-1433.00m. 1.4300 113.264 M/S Chowdari Enterprise 113.264 24/08/2020 23/08/2021 65 27/09/2022 (Material preserved at site,but DC undone due to rain.)
5 UIIP-BC/PCO/W-186 Improvement of Bitumenous Carpeting Fazilargat Road from to Muharibari via Engineer Nurul Huda Road W-6 Ch:0.00m-1060.00m 1.0600 74.993 M/S H.K Enterprise 74.993 24/08/2020 23/08/2021 100 27/09/2022 0.30% Less ( Final bill done)
6 UIIP- BC/PCO/W-185 Improvement of Bitumenous Carpeting Road from Satara Mojil to (Chairman Mohammded Hoshain) Road W-4, Ch:0.00m-1805m. 1.8100 129.915 M/S Chowdari Enterprise 129.915 24/08/2020 23/08/2021 60 27/09/2022 0.02% Less (Material preserved at site,but DC undone due to rain.)
7 UIIP-BC/PCO/W-31 Improvement of Bitumenous Carpeting Road from North SedarPur to Khajur Gas Tola W-1 Ch:0.00m-680.00m 0.6800 48.898 M/S H.K Enterprise 48.898 07/10/2020 06/10/2021 100 27/09/2022 0.11% Less ( Final bill done)
8 UIIP-BC/PCO/W-31 Improvement of Bitumenous Carpeting Road from North SedarPur to Khajur Gas Tola W-1 Ch:0.00m-680.00m 0.6800 48.898 M/S H.K Enterprise 48.898 07/10/2020 06/10/2021 100 27/09/2022 0.11% Less ( Final bill done)
9 UIIP-BC/PCO/W-31 Improvement of Bitumenous Carpeting Road from North SedarPur to Khajur Gas Tola W-1 Ch:0.00m-680.00m 0.6800 48.898 M/S H.K Enterprise 48.898 07/10/2020 06/10/2021 100 27/09/2022 0.11% Less ( Final bill done)
10 UIIP-BC/PCO/W-31 Improvement of Bitumenous Carpeting Road from North SedarPur to Khajur Gas Tola W-1 Ch:0.00m-680.00m 0.6800 48.898 M/S H.K Enterprise 48.898 07/10/2020 06/10/2021 100 27/09/2022 0.11% Less ( Final bill done)
11 UIIP-BC/PCO/W-31 Improvement of Bitumenous Carpeting Road from North SedarPur to Khajur Gas Tola W-1 Ch:0.00m-680.00m 0.6800 48.898 M/S H.K Enterprise 48.898 07/10/2020 06/10/2021 100 27/09/2022 0.11% Less ( Final bill done)
12 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
13 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
14 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
15 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
16 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
17 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
18 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
19 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
20 UIIP-BC/PCO/W-30 Improvement of Bitumenous Carpeting Road from Fathama Monjil FazilerGat Road to Taltoli Link Road W-4 Ch:0.00m-1611.00m 1.6100 112.422 M/S Chowdari Enterprise 112.422 07/10/2020 06/10/2021 100 27/09/2022 0.04% Less ( Final bill done)
21 UIIP-BC/PCO/W-29 Improvement of Bitumenous Carpeting Road from X-Mayor Akbar Hoshain Road W-1 Ch:0.00m-700.00m 0.7000 51.419 M/s Sajin Corporation 51.419 07/10/2020 06/10/2021 100 27/09/2022 0.13% Less ( Final bill done)
22 UIIP-BC/PCO/W-28 Improvement of Bitumenous Carpeting Road form Krisna-Rampur New Briz to Motin Miar Bari Road W-7 Ch:0.00m-745.00m. 0.7500 51.367 M/S Hoque Enterprise 51.367 06/10/2020 05/10/2021 100 27/09/2022 0.15% Less ( Final bill done)
23 UIIP-BC/PCO/W-27 Improvement of bitumenus carpeting Road From Pentagon Hospital to Bash tola Road W-9 Ch 72-805m 0.7300 57.064 M/s Hasanuzzaman Bhuiyan 57.064 12/04/2021 11/04/2022 100 27/09/2022 1.3% Above ( Final bill done)
Total : 25.0870 (Km) 2139.21 (Lac) 2139.21 (Lac)