Annual Work Plan (Workplan) (2021-22)
* Duration:July/2018 to June/2022
* Project Approved Estimated Costঃ(Tk Lakh)
Total ঃ 37533.00
* Cumulative expenditure till June/2021(in Lakh)ঃ
Total ঃ 20220.52
* 2021-22 fiscal year ADP allocation(in Lakh)ঃ
Total ঃ 4197.50
* The project is sheduled to be completed in this financial year ঃ
yes
* The project will be completed in this financial year ঃ
no
*The revise ADP will require an increase/decrease in allocation ঃ
Name of Component
Phycial target(nos,m,man month,km etc)
Financial Target (Lakh taka)
Total
Taka
Project Aid
1
2
3
4
5
A)Revinue Components
1)Manpower(salary/allowance)
LS
25.00
allowance
30.70
2)Supply and serviece(Contingency)
115.80
3)Foreign training
0.00
4)Consultency (Soil testing,Topo survey,Design,Drawing,Estimate preparation and supervision etc)
30.00p
30.00
5)Hydrology and Morphology survey
6)Repair Preservation and Rehabilitation
3.50
Total revinue =
205.00
B)Capital Expenditure
Collection/Purchase of assete
1)Motorcycle
2)Computer and Hardware
3)Office equipment
4)Furniture
5)Telephone
6)tree plantation
20.00
7)Land aquisition
1acr.
100.00
Subtotal =
120.00
Construction and work
1)Upazila Road by BC
3.66km
395.25
2)Union Road by BC
5.77km
490.25
3)Village Road by BC
16.91km
1437.00
4)Construction of bridge on Upazila road
21m
210.00
5)Construction of bridge on Union Road
115.56m
1040.00
6)Construction of bridge on Village Road
22.22m
200.00
7)Construction of culvart on Village road
00m
00
8)Maintanence of village road
4.49Km
km
350.00
3872.50
Total capital =
3992.50
Total =
4197.50