Local Government Engineering
Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No : LGED/UE/KAl/SAT/11-12/586 Date :
Contract No : |
Date
: |
To : MD. Golam
Rabbany Kalaroa Bazar,
Kalaroa, Satkhira |
|
This is to notify you that your Tender dated 8th May’12 for
the execution of the Works for Re-Construction of Nil Kantha Pur GPS, Dhandia
GPS & Harina Community Primary School including Furniture Supply,
Construction of Toilet & Electrification works (P/NO :
PEDP-III/SKR/KAL/2011-12/W2.0354) at Kalaroa UPazila, District-Satkhira
Under PEDP-III for the Contract Price of TK=1,69,61,911.00 (One Crore Sixty
NIne Lakh Sixty One Thousand Nine Hundred Eleven) only as corrected and
modified in accordance with the Instructions to Tenderers has been approved by the Authority.
You are thus requested to take following actions:
i.
accept in
writing the Notification of Award within seven (7) working days of its issuance
pursuant to ITT Sub Clause 63.1
ii.
furnish a Performance Security in the form as
specified and in the amount of Tk=8,48,100.00 (Eight Lakh Forty Eight
Thousand One Hundred) within fourteen (14) days of acceptance of this
Notification of Award but not later than
18th July’12 in accordance with ITT Clause 65.
iii.
sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/587
Date :
Contract No : |
Date : |
To : MD. Golam
Rabbany Kalaroa Bazar,
Kalaroa, Satkhira |
|
This is to notify you that your Tender dated 8th May’12 for
the execution of the Works for Re-Construction of Nathpur, Kamorpur &
Sreerampur Community Primary School including Furniture Supply, Construction of
Toilet & Electrification works (P/NO : PEDP-III/SKR/KAL/2011-12/W2.0355)
at Kalaroa UPazila, District-Satkhira Under PEDP-III for the Contract Price of
TK=1,68,30,737.36 (One Crore Sixty Eight Lakh Thirty Thousand Seven Hundred Thirty
Seven & Paisa Thirty Six) only as corrected and modified in accordance with
the Instructions to Tenderers has been
approved by the Authority.
You are thus requested to take following actions:
i.
accept in
writing the Notification of Award within seven (7) working days of its issuance
pursuant to ITT Sub Clause 63.1
ii.
furnish a Performance Security in the form as
specified and in the amount of Tk=8,41,600.00 (Eight Lakh Forty One
Thousand Six Hundred) within fourteen (14) days of acceptance of this
Notification of Award but not later than
18th July’12 in accordance with ITT Clause 65.
iii.
sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/588
Date :
Contract No : |
Date : |
To : Asaduzzaman
Salim Itegacha, Satkhira |
|
This is to notify you that your Tender dated 8th May’12 for
the execution of the Works for Re-Construction of Dhanghara RNGPS, Pakuria GPS
& Khalshi Community Primary School including Furniture Supply, Construction
of Toilet & Electrification works (P/NO : PEDP-III/SKR/KAL/2011-12/W2.0356)
at Kalaroa UPazila, District-Satkhira Under PEDP-III for the Contract Price of
TK=1,69,52,406.33 (One Crore Sixty NIne Lakh Fifty Two Thousand Four Hundred Six
& Paisa Thirty Three) only as corrected and modified in accordance with the
Instructions to Tenderers has been
approved by the Authority.
You are thus requested to take following actions:
i.
accept in writing the Notification of Award within seven (7) working
days of its issuance pursuant to
ITT Sub Clause 63.1
ii.
furnish a Performance Security in the form as
specified and in the amount of Tk=8,47,700.00 (Eight Lakh Forty Seven
Thousand Seven Hundred) within fourteen (14) days of acceptance of this
Notification of Award but not later than
18th July’12 in accordance with ITT Clause 65.
iii.
sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/589
Date :
Contract No : |
Date
: |
To : S.M. Samsuzzaman
& Consortium Munshipara Satkhira |
|
This is to notify you that your Tender dated 8th May’12 for
the execution of the Works for Re-Construction of Bamanali RNGPS & Rajnagar
Community Primary School including Furniture Supply, Construction of Toilet
& Electrification works (P/NO : PEDP-III/SKR/KAL/2011-12/W2.0357) at
Kalaroa UPazila, District-Satkhira Under PEDP-III for the Contract Price of
TK=1,13,03,463.59 (One Crore Thirteen Lakh Three Thousand Four Hundred Sixty
Three & Paisa Fifty Nine) only as corrected and modified in accordance with
the Instructions to Tenderers has been
approved by the Authority.
You are thus requested to take following actions:
i.
accept in
writing the Notification of Award within seven (7) working days of its issuance
pursuant to ITT Sub Clause 63.1
ii.
furnish a Performance Security in the form as
specified and in the amount of Tk=5,65,200.00 (Five Lakh Sixty Five
Thousand Two Hundred) within fourteen (14) days of acceptance of this
Notification of Award but not later than
18th July’12 in accordance with ITT Clause 65.
iii.
sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/610
Date :
Contract No : |
Date : |
To : MD. Golam
Rabbany Kalaroa Bazar,
Kalaroa, Satkhira |
|
This is to notify you that your Tender dated 15th May’12 for
the execution of the Works for Re-Construction of Kumarnal & Mahmudpur Community
Primary School including Furniture Supply, Construction of Toilet &
Electrification works (P/NO : PEDP-III/SKR/KAL/2011-12/W2.0358) at
Kalaroa Upazila, District-Satkhira Under PEDP-III for the Contract Price of
TK=1,12,74,258.12 (One Crore Twelve Lakh Seventy Four Thousand Two Hundred Fifty
Eight & Paisa Twelve) only as corrected and modified in accordance with the
Instructions to Tenderers has been
approved by the Authority.
You are thus requested to take following actions:
i. accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii. furnish a
Performance Security in the form as specified and in the amount of Tk=5,63,800.00
(Five Lakh Sixty Three Thousand Eight Hundred) within fourteen (14) days
of acceptance of this Notification of Award
but not later than 23rd July’12 in accordance with ITT Clause
65.
iii. sign the Contract within twenty eight
(28) days of issuance of this Notification of Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/607
Date : 02-07-2012
Contract No : |
Date : |
To : S.M. Samsuzzaman Munshipara, Satkhira |
|
This is to notify you that your Tender dated
You are thus requested to take following actions:
i. accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii. furnish a
Performance Security in the form as specified and in the amount of Tk=3,73,000.00
(Three Lakh Seventy Three Thousand) within fourteen (14) days of
acceptance of this Notification of Award
but not later than 23rd July’12 in accordance with ITT Clause
65.
iii. sign the Contract within twenty eight
(28) days of issuance of this Notification of Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/609
Date :
Contract No : |
Date : |
To : MD. Golam
Rabbany Kalaroa Bazar,
Kalaroa, Satkhira |
|
This is to notify you that your Tender dated 15th May’12 for
the execution of the Works for Construction of Additional Class Room (V/Ext.)
of Bamankhali Government Primary School including Furniture Supply &
Electrification works (P/NO : PEDP-III/SKR/KAL/2011-12/W2.0667) at
Kalaroa Upazila, District-Satkhira Under PEDP-III for the Contract Price of TK=32,84,852.84
(Thirty Two Lakh Eighty Four Thousand Eight Hundred Fifty Two & Paisa Eighty
Four) only as corrected and modified in accordance with the Instructions to
Tenderers has been approved by the Authority.
You are thus requested to take following actions:
i. accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii. furnish a
Performance Security in the form as specified and in the amount of Tk=1,64,500.00
(One Lakh Sixty Four Thousand Five Hundred) only within fourteen (14)
days of acceptance of this Notification of Award but not later than 23rd July’12 in
accordance with ITT Clause 65.
iii. sign the Contract within twenty eight
(28) days of issuance of this Notification of Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Local Government Engineering Department
Office of the Upazila Engineer
Upazila : Kalaroa, District :
Satkhira
Memo No :
LGED/UE/KAl/SAT/11-12/608
Date :
Contract No : |
Date : |
To : M/S Vhai
Enterprise & Consortium Kalaroa, Satkhira |
|
This is to notify you that your Tender dated 15th May’12 for
the execution of the Works for Construction of Additional Class Room (H/Ext.)
of Damodor Kati Government Primary School including Furniture Supply,
Construction of Toilet & Electrification works (P/NO :
PEDP-III/SKR/KAL/2011-12/W2.1069) at Kalaroa Upazila, District-Satkhira
Under PEDP-III for the Contract Price of TK=56,38,835.94 (Fifty Six Lakh Thirty
Eighty Thousand Eight Hundred Thirty Five & Paisa Ninety Four) only as
corrected and modified in accordance with the Instructions to Tenderers has been approved by the Authority.
You are thus requested to take following actions:
i. accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii. furnish a
Performance Security in the form as specified and in the amount of Tk=2,82,000.00
(Two Lakh Eighty Two Thousand) only within fourteen (14) days of
acceptance of this Notification of Award
but not later than 23rd July’12 in accordance with ITT Clause
65.
iii. sign the Contract within twenty eight
(28) days of issuance of this Notification of Award but not later than
You may
proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497
Memo No :
LGED/UE/KAl/SAT/11-12/
Date :
Copy
Forwaded for Kind information & Necessary action to. :
(Md. Abedur Rahman)
Upazila Engineer
LGED
Kalaroa, Satkhira
04724-75497