Notification of Award
M/S. ---------------------------
Dhunat, Bogra .
This
is to notify you that your Tender dated
You
are thus requested to take following
action :
to
proceed with the execution of the works on the basis that this Notification of
Award only upon completion of the above tasks. You may also please note that
which only become binding you furnishing a Performance Security amount in Tk.23,900.00 ( Twenty three thousand Nine hundred) Only within fourteen (14) days, in accordance with
ITT Clause 32, and signing the Contract Agreement within twenty-eight (28) days
in accordance with ITT Clause33. The
performance security (Bank guarantee /BD/ Pay
order) should be in the form of Bid document under Form W-5.
We attach the Contract Agreement and
Particular Conditions of Contract for your perusal and signature.
Please note that failure to comply with requirements mentioned above
shall constitute sufficient grounds for cancellation of the award and
forfeiture of the tender security.
|
Upazila Engineer Local
Government Engineering Department Dhunat,Bogra. |
Copy
forward for kind information & necessary action:
1. The Chairman , Upazila Parished, Dhunat, Bogra.
2. The Executive Engineer,
LGED, District: Bogra.
3. The Upazila Nirbahi Officer, Upazila : Dhunat, District:Bogra.
4. The Upazila
Accounts officer, Dhunat, Bogra.
5. Chairman------------------UP, Dhunat, Bogra.
6.
Mr.....................................................................,
SAE, LGED, Dhunat ,Bogra.
7.
Mr................................................................. Work
Assistant, LGED, Dhunat ,Bogra.
Government of the People’s
Republic of
Local Government Engineering Department
Office of the Upazila Engineer
Upazila: Dhunat, District: Bogra
Memo No:
LGED/UE/DHU/BOG/2012/ 465
Date:
Notification
of Award
To: M/S. Alam Dhunat, Bogra . |
|
This
is to notify you that your Tender dated
You are thus requested to take following actions:
i.
accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii.
furnish a Performance Security in form
as specified and in the amount of Tk . 1,34,600.00
( One Lac Thirty four thousand six
hundred )only ,within forteen (14) working days of acceptance of this Notification
of Award but not later than
iii.
sign the Contract within twenty eight (28) working days of issuance of this Notification
of Award but not later than
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which shall become binding upon you.
We attach
the draft Contract and all other documents for your perusal and signature.
|
Upazila Engineer Local
Government Engineering Department Dhunat,Bogra. |
Memo
No: LGED/UE/DHU/BOG/2012/ 465/1(9) Date:
C.C.To.
1.
Additional Chief Engineer (Maintenance ) LGED,Agargaon,Sher-E-Banglanagar,
Dhaka-1207.
2.
Executive Engineer, LGED, Dist: Bogra.
3. District Education Officer,Bogra.
4. Chairman,
Upazila Parishad, Dhunat, Bogra.
5. Upazila Nirbahi officer, Dhunat, Bogra.
6. Upazila Education officer, Dhunat,
Bogra.
7.
The Head master,
8.
Mr....................................................................., SAE,
LGED, Dhunat ,Bogra.
9. Mr.................................................................
Work Assistant, LGED, Dhunat ,Bogra.
Upazila
Engineer
Local Government Engineering Department
Dhunat,Bogra.
Government of
the People’s Republic of
Local Government
Engineering Department
Office of the Upazila Engineer
Upazila: Dhunat, District: Bogra
Notification of Award
To: M/S. Mina Traders Jv.
Sherpur, Bogra . |
|
This
is to notify you that your Tender dated
You are thus requested to take following actions:
i.
accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii.
furnish a Performance Security in form
as specified and in the amount of Tk . 5,01,200.00 ( Five Lac One
thousand two hundred ) only ,within forteen
(14) working days of acceptance of this Notification of Award but not later than
iii.
sign the Contract within twenty eight
(28) working days of issuance of this Notification of Award but not later than
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which shall become binding upon you.
We attach
the draft Contract and all other documents for your perusal and signature.
|
Upazila Engineer Local
Government Engineering Department Dhunat,Bogra. |
Memo
No: LGED/UE/DHU/BOG/2012/468/1(9) Date:
C.C.To.
1.
Additional Chief Engineer (Maintenance ) LGED,Agargaon,Sher-E-Banglanagar,
Dhaka-1207.
2.
Executive Engineer, LGED, Dist: Bogra.
3. District Education Officer,Bogra.
4. Chairman,
Upazila Parishad, Dhunat, Bogra.
5. Upazila Nirbahi officer, Dhunat, Bogra.
6. Upazila Education officer, Dhunat,
Bogra.
7.
The Head master,
8. Mr.....................................................................,
SAE, LGED, Dhunat ,Bogra.
9. Mr.................................................................
Work Assistant, LGED, Dhunat ,Bogra.
Upazila
Engineer
Local Government Engineering Department
Dhunat,Bogra.
Government of
the People’s Republic of
Local Government
Engineering Department
Office of the Upazila Engineer
Upazila: Dhunat, District: Bogra
Notification of Award
To: Md. Abdul Motin Namajgar , Bogra . |
|
This
is to notify you that your Tender dated
You are thus requested to take following actions:
i.
accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii.
furnish a Performance Security in form
as specified and in the amount of Tk . 2,43,700.00 ( Two Lac forty three thousand seven hundred )only ,within forteen
(14) working days of acceptance of this Notification of Award but not later than
iii.
sign the Contract within twenty eight
(28) working days of issuance of this Notification of Award but not later than
You may proceed with the execution of the Works only upon completion of the above tasks. You may also please note that this Notification of Award shall constitute the formation of this Contract which shall become binding upon you.
We attach
the draft Contract and all other documents for your perusal and signature.
|
Upazila Engineer Local
Government Engineering Department Dhunat,Bogra. |
Memo
No: LGED/UE/DHU/BOG/2012/ 469/1(9) Date:
C.C.To.
1.
Additional Chief Engineer (Maintenance ) LGED,Agargaon,Sher-E-Banglanagar,
Dhaka-1207.
2.
Executive Engineer, LGED, Dist: Bogra.
3. District Education Officer,Bogra.
4. Chairman,
Upazila Parishad, Dhunat, Bogra.
5. Upazila Nirbahi officer, Dhunat, Bogra.
6. Upazila Education officer, Dhunat,
Bogra.
7.
The Head master, Bishar Diar
RNGPS,Dhunat.Bogra.
8.
Mr....................................................................., SAE,
LGED, Dhunat ,Bogra.
9. Mr.................................................................
Work Assistant, LGED, Dhunat ,Bogra.
Upazila
Engineer
Local Government Engineering Department
Dhunat,Bogra.