Upazila:Nandigram, District:Bogra.
Contract No : PEDP-III/BRG/NAN/Bog/2011-12/
W1.0516 Date
:
To:
M/S. Bani
Constrction ,
Pro : Kh.Altaf Hossain,
Bani Bhabon, Rail Gate,
Puran Bogra, Bogra.
This
is to notify you that your Tender dated 28-08-2012 for the execution of the
works for Re-construction of Chalk Dawla RNGPS, Dola Singra & Birpoli GPS including Furniture Supply, Construction of
Toilet, Electrification Works & Children Park at Nandigram
Upazila under Bogra
District, Package No: PEDP-III/BRG/NAN/Bog/2011-12/W1.0516 under Third Primary Education Development
Program (PEDP-III). for the Contract Price of Tk.1,76,52,448.72 One Core
seventy six lakh
fifty two thousand four hundred forty
eight & paisa seventy two only as corrected and modified in accordance with
the Instructions to Tenderers, has been approved by Upazila Engineer, LGED, Nandigram,
Bogra.
You
are thus requested to take following actions:
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance pursuant to ITT
Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk. 8,82,623.00
(Eight Lac eighty two thousand six hundred twenty three only) within fourteen
(14) days of acceptance of this
Notification of Award but not later than
08-10-2012, in accordance with ITT Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than
You
may proceed with the execution of the works for Re-construction of Chalk Dawla RNGPS, Dola Singra & Birpoli GPS
including Furniture Supply, Construction of Toilet,
We attach the draft Contract and all
other documents for your perusal and signature.
(Md. Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.
CC:
1. The Chief Engineer, LGED, LGED Bhaban, Agergaon, Dhaka-1207.
2. The
Director General, Directorate of Primary Education, Mirpur-2,
3. The Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban, Agargaon, Dhaka-1207.
7. District Primary Education Officer, District:Bogra.
12. Office Copy.
(Md. Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.
Local Government Engineering
Department
Upazila:Nandigram, District:Bogra.
Contract No : PEDP-III/BRG/NAN/Bog/2011-12/
W1.0517 Date
:
To:
M/S. Loba
Constrction ,
Pro : Shamsuddin Shaikh Helal,
Chalk Sutrapur,
Bogra.
This
is to notify you that your Tender dated 28-08-2012 for the execution of the
works for Re-construction of Bailgram GPS, & Mathurapur Community
PS including Furniture Supply, Construction of Toilet, Electrification
Works & Children Park at Nandigram Upazila under Bogra District,
Package No: PEDP-III/BRG/NAN/Bog/2011-12/W1.0517 under Third Primary Education Development
Program (PEDP-III). for the Contract Price of Tk.1,17,67,116.66 One Core
seventeen lakh
sixty seven thousand one hundred sixteen
& paisa sixty six only as corrected and modified in accordance with
the Instructions to Tenderers, has been approved by Upazila Engineer, LGED, Nandigram,
Bogra.
You
are thus requested to take following actions:
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance pursuant to ITT
Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk. 5,88,356.00
(Five Lac eighty eight thousand three hundred fifty six only) within fourteen
(14) days of acceptance of this
Notification of Award but not later than
08-10-2012, in accordance with ITT Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than
You
may proceed with the execution of the works for Re-construction of Bailgram GPS, & Mathurapur Community PS including
Furniture Supply, Construction of Toilet,
We attach the draft Contract and all
other documents for your perusal and signature.
(Md. Abul Kashem)
Upazila
Engineer
LGED
Nandigram,
Bogra.
1. The Chief Engineer, LGED, LGED Bhaban, Agergaon, Dhaka-1207.
2. The
Director General, Directorate of Primary Education, Mirpur-2,
3. The Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban, Agargaon, Dhaka-1207.
7. District Primary Education Officer, District:Bogra.
12. Office Copy.
(Md.
Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.
Local Government Engineering
Department
Upazila:Nandigram, District:Bogra.
Contract No : PEDP-III/BRG/NAN/Bog/2011-12/
W1.0518 Date
:
To:
S/O.
Kahaloo Bazar, Bogra.
This
is to notify you that your Tender dated 28-08-2012 for the execution of the
works for Re-construction of Thalgachi RNGPS & Kuchma Community PS
including Furniture Supply, Construction of Toilet, Electrification Works &
Children Park at Nandigram Upazila
under Bogra District, Package No: PEDP-III/BRG/NAN/Bog/2011-12/W1.0518
under Third Primary Education Development Program (PEDP-III). for the Contract
Price of Tk.1,17,66,992.94 One Core seventeen lakh sixty six thousand nine hundred ninety two & paisa
ninety four only as corrected and modified in accordance with
the Instructions to Tenderers, has been approved by Upazila Engineer, LGED, Nandigram,
Bogra.
You
are thus requested to take following actions:
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance pursuant to ITT
Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk. 5,88,350.00
(Five Lac eighty eight thousand three hundred fifty only) within fourteen (14)
days of acceptance of this Notification
of Award but not later than 08-10-2012,
in accordance with ITT Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than
You
may proceed with the execution of the works for Re-construction of Thalgachi RNGPS & Kuchma
Community PS including Furniture Supply,
Construction of Toilet, Electrification Works & Children Park at Nandigram Upazila under Bogra District, Package No: PEDP-III/BRG/NAN/Bog/2011-12/W1.0518 only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which
shall become binding upon you.
We attach the draft Contract and all
other documents for your perusal and signature.
(Md. Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.
CC:
1. The Chief Engineer, LGED, LGED Bhaban, Agergaon, Dhaka-1207.
2. The
Director General, Directorate of Primary Education, Mirpur-2,
3. The Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban, Agargaon, Dhaka-1207.
7. District Primary Education Officer, District:Bogra.
12. Office Copy.
(Md. Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.
Local Government Engineering
Department
Upazila:Nandigram, District:Bogra.
Contract No : PEDP-III/BRG/NAN/Bog/2011-12/W2.0265 Date
:
To:
M/S. Nahian International
Pro :
Collage road, Kalitolahat, Bogra.
This
is to notify you that your Tender dated 28-08-2012 for the execution of the
works for Construction of Additional Class Room
of Chandpur, Badlason
RNGPS, & Bhag Bazar GPS including
Furniture Supply, Electrification Works.at Nandigram Upazila under Bogra District,
Package No: PEDP-III/BRG/NAN/Bog/2011-12/W2.0265 under Third Primary Education Development
Program (PEDP-III). for the Contract Price of Tk.1,23,65,749.66 One Core twenty
three lakh sixty
five thousand seven hundred forty nine
& paisa sixty six only
as corrected and modified in accordance with the Instructions to Tenderers, has been approved by Upazila
Engineer, LGED, Nandigram, Bogra.
You
are thus requested to take following actions:
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance pursuant to ITT
Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk. 6,18,288.00
(Six Lac eighteen thousand two hundred
eighty eight only) within fourteen (14) days of
acceptance of this Notification of Award but not later than 08-10-2012, in accordance with ITT Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than
You
may proceed with the execution of the works for Construction of Additional
Class Room of Chandpur,
Badlason RNGPS,
& Bhag
Bazar GPS including Furniture Supply, Electrification Works at Nandigram Upazila under Bogra District, Package No: PEDP-III/BRG/NAN/Bog/2011-12/W2.0265
only upon completion of the above tasks.
You may also please note that this Notification of Award shall constitute the
formation of this Contract which shall become binding upon you.
We attach the draft Contract and all
other documents for your perusal and signature.
(Md. Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.
CC:
1. The Chief Engineer, LGED, LGED Bhaban, Agergaon, Dhaka-1207.
2. The
Director General, Directorate of Primary Education, Mirpur-2,
3. The Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban, Agargaon, Dhaka-1207.
7. District Primary Education Officer, District:Bogra.
12. Office Copy.
(Md.
Abul Kashem)
Upazila
Engineer
LGED
Nandigram, Bogra.