Mahalchari, Khagrachari.
Contract No: PEDP-III/KHG/MAH/2011-12/W1.0041/2 Date : 24/12/2012.
To,
M/S. Rip
Propritor.
Mr. Rip Rip Chakma.
C/o : Narayan Khaiya,
Khagrachari.
This is to notify you that your Tender dated 29/08/2012
for the execution of the Works for Re-Construction of 2(Two) nos Primary School Including Furniture Supply at (i) Kalachan Para RNGPS & (ii)
East Datkupya GPS. Package
No.PEDP-III/KHG/MAH/2011-12/W1.0041 for the Contract Price of Tk.1,27,46,975/56 (In Words: One Core twenty seven lac forty six thousand nine hundred seventy five &
Paisa fifty six) only as corrected and modified in accordance with the
Instructions to Tenderers, has been approved by the Competent
Authority.
You
are thus requested to take following actions :-
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance
pursuant to
ITT Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk.6,38,,000.00
(In Words : Six lac thirty eight thousand) only within fourteen (14) days of acceptance of
the Notification of Award but not later than 07-01-2013, in accordance with ITT
Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than 21-01-2013, in
accordance with ITT Sub Clause 69.2.
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which
shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
Estimate
Cost |
Tk.1,02,80,000.00 |
Contract
Amount |
Tk.1,27,46,975/56
|
Latest
Date of Commencement |
29-01-2013. |
Intended
Date of Completion |
28-04-2014. |
Upazila
Engineer
LGED
Mahalchari, Khagrachari.
Copy to Information for Nassesary Action :-
01. The Director General, CPTU,
IMED, Block-12, 2nd Floor, Sher-e-Bangla Nagar, Dhaka-1207. Request to
publish
on the CPTU web site.
02. The
Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban(Level-3),
Agergaon, Sher-e-Bangla
nagar, Dhaka-1207.
03. The Executive Engineer,
LGED, District : Khagrachari.
04. The Executive Engineer(Primary
Education & Training), LGED, Chittagong Zone, District :
06. The District Primary
Education officer, District : Khagrachari.
09. The Head Master, (i) Kalachan
Para RNGPS & (ii) East Datkupya GPS, Upazila : Mahalchari, District :
Khagrachari.
Upazila Engineer
LGED
Mahalchari,
Khagrachari.
Mahalchari, Khagrachari.
Contract No: PEDP-III/KHG/MAH/2011-12/W1.0042(3) Date : 24/12/2012.
To,
M/S. Rip
Propritor.
Mr. Rip Rip Chakma.
C/o : Narayan Khaiya,
Khagrachari.
This is to notify you that your Tender dated 29/08/2012
for the execution of the Works for Re-Construction of 2(Two) nos Primary School Including Furniture Supply at (i) Satgharia GPS & (ii) Kalapuna GPS. Package No.PEDP-III/KHG/MAH/2011-12/W1.0042
for the Contract Price of Tk.1,24,52,741/71(In Words: One Core twenty four lac
fifty two thousand seven hundred forty one & Paisa seventy one) only as
corrected and modified in accordance with the Instructions to Tenderers, has been approved by the Competent Authority.
You
are thus requested to take following actions :-
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance
pursuant to
ITT Sub-clause 63.1
ii.
furnish a Performance
Security in the form as specified and in the amount of Tk.6,23,,000.00 (In
Words : Six lac twenty three thousand) only within fourteen (14) days of acceptance of
the Notification of Award but not later than 07-01-2013, in accordance with ITT
Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than 21-01-2013, in
accordance with ITT Sub Clause 69.2.
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which
shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
Estimate
Cost |
Tk.1,02,80,000.00 |
Contract
Amount |
Tk.1,24,52,741/71 |
Latest
Date of Commencement |
29-01-2013. |
Intended
Date of Completion |
28-04-2014. |
Upazila
Engineer
LGED
Mahalchari, Khagrachari.
Copy to Information for Nassesary Action :-
01. The Director General, CPTU,
IMED, Block-12, 2nd Floor, Sher-e-Bangla Nagar, Dhaka-1207. Request to
publish
on the CPTU web site.
02. The
Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban(Level-3),
Agergaon, Sher-e-Bangla
nagar, Dhaka-1207.
03. The Executive Engineer,
LGED, District : Khagrachari.
04. The Executive Engineer(Primary
Education & Training), LGED, Chittagong Zone, District :
06. The District Primary
Education officer, District : Khagrachari.
09. The Head Master, (i) Satgharia
GPS & (ii) Kalapuna GPS, Upazila : Mahalchari, District :
Khagrachari.
Upazila Engineer
LGED
Mahalchari,
Khagrachari.
Mahalchari, Khagrachari.
Contract No: PEDP-III/KHG/MAH/2011-12/W1.0043(4) Date : 24/12/2012.
To,
S. Ananta Bikas Tripura.
C/o : Milonpur, Sadar,
Khagrachari.
This is to notify you that your Tender dated 29/08/2012
for the execution of the Works for Re-Construction of 2(Two) nos Primary School Including Furniture Supply at (i) Khulang Para RNGPS & (ii) Manikchari Jaisen Para GPS. Package
No.PEDP-III/KHG/MAH/2011-12/W1.0043 for the Contract Price of Tk.1,24,52,244/19(In Words: One Core twenty four lac
fifty two thousand two hundred forty four & Paisa ninteen)
only as corrected and modified in accordance with the Instructions to Tenderers, has been approved by the Competent Authority
You
are thus requested to take following actions :-
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance
pursuant to
ITT Sub-clause 63.1
ii.
furnish a Performance
Security in the form as specified and in the amount of Tk.6,23,,000.00 (In
Words : Six lac twnty three
thousand) only within fourteen (14) days
of acceptance of the Notification of Award but not later than 07-01-2013, in
accordance with ITT Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than 21-01-2013, in
accordance with ITT Sub Clause 69.2.
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which
shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
Estimate
Cost |
Tk.1,02,80,000.00 |
Contract
Amount |
Tk.1,24,52,244/19 |
Latest
Date of Commencement |
29-01-2013. |
Intended
Date of Completion |
28-04-2014. |
Upazila
Engineer
LGED
Mahalchari, Khagrachari.
Copy to Information for Nassesary Action :-
01. The Director General, CPTU,
IMED, Block-12, 2nd Floor, Sher-e-Bangla Nagar, Dhaka-1207. Request to
publish
on the CPTU web site.
02. The
Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban(Level-3),
Agergaon, Sher-e-Bangla
nagar, Dhaka-1207.
03. The Executive Engineer,
LGED, District : Khagrachari.
04. The Executive Engineer(Primary
Education & Training), LGED, Chittagong Zone, District :
06. The District Primary
Education officer, District : Khagrachari.
09. The Head Master, (i) Khulang
Para RNGPS & (ii) Manikchari Jaisen
Para GPS, Upazila : Mahalchari, District :
Khagrachari.
Upazila Engineer
LGED
Mahalchari,
Khagrachari.
Mahalchari, Khagrachari.
Contract No: PEDP-III/KHG/MAH/2011-12/W2.0944(5) Date : 24/12/2012.
To,
Mr. Kanchan Shil.
C/o : Mahalchari, Khagrachari.
This
is to notify you that your Tender dated 29/08/2012 for the execution of the
Works for Construction of Additional Class Room for 2(Two) nos
Primary School Including Furniture Supply at (i) Changrachari GPS & (ii) Singhinala
GPS. Package No.PEDP-III/KHG/MAH/2011-12/W2.0944 for the Contract Price of Tk. 1,27,46,985/09(In Words: One Core twenty seven lac forty six thousand nine hundred eighty five & Paisa
nine) only as corrected and modified in
accordance with the Instructions to Tenderers, has
been approved by the Competent Authority.
You
are thus requested to take following actions :-
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance
pursuant to
ITT Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk.6,38,,000.00
(In Words : Six lac thirty eight thousand) only within fourteen (14) days of acceptance of
the Notification of Award but not later than 07-01-2013, in accordance with ITT
Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than 21-01--2013, in
accordance with ITT Sub Clause 69.2.
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which
shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
Estimate
Cost |
Tk.1,03,72,000.00 |
Contract
Amount |
Tk.1,27,46,985/09 |
Latest
Date of Commencement |
29-01-2013. |
Intended
Date of Completion |
28-01-2014. |
Upazila
Engineer
LGED
Mahalchari, Khagrachari.
Copy to Information for Nassesary Action :-
01. The Director General, CPTU,
IMED, Block-12, 2nd Floor, Sher-e-Bangla Nagar, Dhaka-1207. Request to
publish
on the CPTU web site.
02. The
Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban(Level-3),
Agergaon, Sher-e-Bangla
nagar, Dhaka-1207.
03. The Executive Engineer,
LGED, District : Khagrachari.
04. The Executive Engineer(Primary
Education & Training), LGED, Chittagong Zone, District :
06. The District Primary
Education officer, District : Khagrachari.
09. The Head Master, (i) Changrachari
GPS & (ii) Singhinala GPS, Upazila : Mahalchari, District :
Khagrachari.
Upazila Engineer
LGED
Mahalchari,
Khagrachari.
Mahalchari, Khagrachari.
Contract No: PEDP-III/KHG/MAH/2011-12/W2.0945(6) Date : 24/12/2012.
To,
M/S. Rip
Propritor.
Mr. Rip Rip Chakma.
C/o : Narayan Khaiya,
Khagrachari.
This is to notify you that your Tender dated 29/08/2012
for the execution of the Works for Construction of Additional Class Room for
2(Two) nos Primary School Including Furniture Supply
at (i) Khyangsa Para GPS
& (ii) Karalya Chari GPS. Package
No.PEDP-III/KHG/MAH/2011-12/W2.0945 for the Contract Price of Tk.1,27,54,717/91(In Words: One Core twenty seven lac fifty four thousand seven hundred seventeen & Paisa
ninty one) only as corrected and modified in
accordance with the Instructions to Tenderers, has
been approved by the Competent Authority.
You
are thus requested to take following actions :-
i.
accept in writing
the Notification of Award within seven (7) working days of its issuance
pursuant to
ITT Sub-clause 63.1
ii.
furnish a
Performance Security in the form as specified and in the amount of Tk.6,38,,000.00
(In Words : Six lac thirty eight thousand) only within fourteen (14) days of acceptance of
the Notification of Award but not later than 07-01-2013, in accordance with ITT
Clause 65.
iii.
sign the Contract within twenty eight (28) days of
issuance of this Notification of Award but not later than 21-01-2013, in
accordance with ITT Sub Clause 69.2.
You may proceed with the execution of the Works only
upon completion of the above tasks. You may also please note that this
Notification of Award shall constitute the formation of this Contract which
shall become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
Estimate
Cost |
Tk.1,03,72,000.00 |
Contract
Amount |
Tk.1,27,54,717/91 |
Latest
Date of Commencement |
29-01-2013. |
Intended
Date of Completion |
28-01-2014. |
Upazila
Engineer
LGED
Mahalchari, Khagrachari.
Copy to Information for Nassesary Action :-
01. The Director General, CPTU,
IMED, Block-12, 2nd Floor, Sher-e-Bangla Nagar, Dhaka-1207. Request to
publish
on the CPTU web site.
02. The
Additional Chief
Engineer(Maintenance), LGED, LGED Bhaban(Level-3),
Agergaon, Sher-e-Bangla
nagar, Dhaka-1207.
03. The Executive Engineer,
LGED, District : Khagrachari.
04. The Executive Engineer(Primary
Education & Training), LGED, Chittagong Zone, District :
06. The District Primary
Education officer, District : Khagrachari.
09. The Head Master, (i) Khyangsa
Para GPS & (ii) Karalya Chari GPS, Upazila : Mahalchari, District :
Khagrachari.
Upazila Engineer
LGED
Mahalchari,
Khagrachari.