Government of the People’s Republic of
Local Government
Engineering Department
Office of the Upazila
Engineer
Badargonj,Rangpur.
Notification
of Award (Form PW3-7)
To:
M/s. Sakib Enterprise
Badarganj,Rangpur.
This
is to notify you that your Tender dated 18-11-2013 for Construction of
Additional Class Room for Gopinathpur Khiar Para &Munshipara Primary
School ( Including furniture Supply).Package No: PEDPIII/RNP/BAD/2013-14/W2.2360 for
the Contract Price of Tk.88,36,568.99 (Taka Eighty
eight lac Thirty Six Thousand Five hunderd Sixty eight
& ninety nine Paisa only ) as corrected and
modified in accordance with the Instructions to Tenderers, has been approved by
the competent authority.
You are thus
requested to take following actions:
i.
Accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
ii.
Furnish
a Performance Security in the form as specified and in the amount of Tk 4,41,850,00(Taka Four Lac Forty One thousand Eight
Hundred Fifty only)within fourteen (14) days of acceptance of this Notification
of Award but not later than 26-12-2013 in accordance with ITT Clause 65.
iii. Sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than
You
may proceed with the execution of the Works only upon completion of the above tasks.
You may also please note that this Notification of Award shall constitute the
formation of this Contract which shall become binding upon you.
We
attach the draft Contract and all other documents for your perusal and
signature.
( Md. Abu Taleb
sarker)
Upazila Engineer
LGED, Badargonj,Rangpur
C.C:
1. The Additional
Chief Engineer, (Maintenance),LGED, LGED Bhaban, Agargaon, Dhaka-1207.
2. The Executive
Engineer, LGED, Rangpur
3. The Executive Engineer, Office of the
Superintendent Engineer, LGED, Rangpur.Region,Rangpur
4. The District
primary Education Officer, Rangpur.
5. The Upazila Nirbahi Officer,
Badarganj, Rangpur.
6. The Upazila Education Officer, Badarganj,Rangpur
7 The Upazila Asstt. Engineer, LGED, Badarganj Rangpur
8.The Head Master Gopinathpur Khiar
Para GPS&Munshipara RNGPS, Badarganj,Rangpur.
9.Office copy.
( Md. Abu Taleb
sarker)
Upazila Engineer
LGED, Badargonj,Rangpur
Government of the People’s Republic of
Local Government
Engineering Department
Office of the Upazila
Engineer
Badargonj,Rangpur.
Notification
of Award (Form PW3-7)
To:
M/s. Tarin Construction
Badarganj,Rangpur
This
is to notify you that your Tender dated 18-11-2013 for Construction of
Additional Class Room for Jamubari Shurirdanga RNGPS (
Including furniture Supply).Package No: PEDPIII/RNP/BAD/2013-14/W2.2361 for the
Contract Price of Tk.48,94,198.58 (Taka Forty eight
lac Ninety Four Thousand One hunderd Ninety eight & Fifty Eight Paisa only ) as corrected and modified in accordance with
the Instructions to Tenderers, has been approved by the competent authority.
You are thus
requested to take following actions:
iii.
Accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to ITT Sub Clause 63.1
iv.
Furnish
a Performance Security in the form as specified and in the amount of Tk 2,44,800.00 (Taka Two Lac Forty Four Thousand Eight
Hundred only)within fourteen (14) days of acceptance of this Notification of
Award but not later than 26-12-2013 in accordance with ITT Clause 65.
iii. Sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than
You
may proceed with the execution of the Works only upon completion of the above
tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract which shall become binding upon you.
We
attach the draft Contract and all other documents for your perusal and
signature.
( Md. Abu Taleb
sarker)
Upazila Engineer
LGED, Badargonj,Rangpur
C.C:
1. The Additional
Chief Engineer, (Maintenance),LGED, LGED Bhaban, Agargaon, Dhaka-1207.
2. The Executive
Engineer, LGED, Rangpur
3. The Executive Engineer, Office of the
Superintendent Engineer, LGED, Rangpur.Region,Rangpur
4. The District
primary Education Officer, Rangpur.
5. The Upazila Nirbahi Officer,
Badarganj, Rangpur.
6. The Upazila Education Officer, Badarganj,Rangpur
7 The Upazila Asstt. Engineer, LGED, Badarganj Rangpur
8.The Head Master Jamubari Shurirdanga
RNGPS, Badarganj,Rangpur.
9.Office copy.
( Md. Abu Taleb
sarker)
Upazila Engineer