GOVERNMENT OF THE PEOPLE’S
LOCAL GOVERNMENT ENGINEERING DEPARTMENT
OFFICE OF THE UPAZILA ENGINEER
CHIRIBANDAR, DINAJPUR.
MEMO. NO.LGED/UE/CHI/DIN/2014/05 DATED: 06/01/2014
Notification of Award (Form W3-7)
To M/S Annesha Enterprize, Uttarbalubari, Dinajpur. |
|
This Is To Notify You That Your Tender
Dated 24/12/2013 For The Execution Of The Works For Construction Of Horizontal Extension Additional Class Room For Khamar Satnala
Gps, Mitrabati Rngps & Dakin Purbo Shitara Community Primary School In/c. Furniture Supply.Package
No.PEDP-III/DIN/CHI2013-14/W2.3303 For The Contract Price Of TK.1,28,05,070.34 (One Core Twenty Eight
Lac Five Thousand Seventy taka & Paisa Thirty Four) Only As Corrected
And Modified In Accordance With The Instructions To Tenderers Has Been Approved
By The Upazila Engineer, LGED, Upazila Chirirbandar, District: Dinajpur.
You
Are Thus Requested To Take Following Actions:
i.
Accept in writing
the Notifications Award within seven (7) working days of its issuance pursuant
to ITT Sub. Clause 63.1.
ii.
furnish a
Performance Security in the form as specified and in the amount of
Tk,6,40,253.52 (Six Lac Forty Thousand Two Hundred Fifty Three taka & Paisa
Fifty Two) Only within fourteen (14) days of acceptance of this Notification of Award but not later than 19.012014 in accordance with ITT Clause
65.
iii.
Sign the Contract
within twenty Eight (28) days of issuance of this Notifications Award but not
later than 02.02.2014 in accordance with ITT Sub
Clause 69.2
You
may proceed with the execution of the work only upon completion of the above
tasks, you may also please not that this Notifications of Award shall constitute the
formation of this contract which shall become binding upon you.
You
are requested to proceed with the execution of the works on the basis that this
Nonfiction of Award shall constitute the formation of a Contract, which shall
become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
|
(Md. Rabiul Islam) Upazila Engineer Chirirbandar, Dinajpur. |
MEMO. NO.LGED/UE/CHI/DIN/2014/ 05 /1(20) DATED:
06 /01//2014
Copy For kind information & necessary
Action:-
01. The Chief Engineer, LGED, LGED
Bhaban Agargaon,
02. The
Director General, Directorate of Primary Education, Mirpur-2,
03. The Additional Chief Engineer (
04. The Director Program, PEDP-III, Primary Education Department, Mirpur-2,
05. The Superintending Engineer, LGED Dinajpur
Region, Dinajpur.
06. The Executive Engineer, LGED,
District: Dinajpur.
07. The Executive Engineer, Office of the
Superintending Engineer, LGED Dinajpur Region, Dinajpur.
08. The District Primary Education
Officers, District: Dinajpur
09. The Upazila Nirbahi Officer, Upazila : Chirirbandar, District: Dinajpur.
10. The Upazila Engineer, Upazila : _________________, District: Dinajpur
11. The Upazila
_____________________________Officer, Upazila : Chirirbandar,
District: Dinajpur
12. The Head Master, Khamar
Satnala GPS,
13.
supervision & ensure quality of work as per
Estimate, Design & Specifications.
14. Mr............................................................................Work
Asstt. LGED, Chirirbandar, Dinajpur
for supervision & ensure quality of work as per Estimate,
Design & Specifications.
15. Office Copy.
|
Upazila Engineer Chirirbandar, Dinajpur. |
GOVERNMENT OF THE PEOPLE’S
LOCAL GOVERNMENT ENGINEERING DEPARTMENT
OFFICE OF THE UPAZILA ENGINEER
CHIRIBANDAR, DINAJPUR.
MEMO. NO.LGED/UE/CHI/DIN/2014/04 DATED: 06 /01/2014
Notification of Award (Form W3-7)
To M/S Haque Trader’s Nimnagar Balubari, Dinajpur. |
|
This Is To Notify You That Your
Tender Dated 24/12/2013 For The Execution Of The Works For Construction Of Construction of
Horizontal Extension Additional
Class room for Roghunathpur & Pataikuri
Community Primary School
in/c Furniture Supply. Package No.PEDP-III/DIN/CHI2013-14/W2.3304 For The
Contract Price Of TK.88,42,390.84 (Eighty
Eight Lac Forty Two Thousand Three Hundred Ninety taka & Paisa Eighty Four)
Only As Corrected And Modified In Accordance With The Instructions To Tenderers
Has Been Approved By The Upazila Engineer, LGED, Upazila Chirirbandar,
District: Dinajpur.
You
Are Thus Requested To Take Following Actions:
i.
Accept in writing
the Notifications Award within seven (7) working days of its issuance pursuant
to ITT Sub. Clause 63.1.
ii.
furnish a
Performance Security in the form as specified and in the amount of
Tk.4,42,119.54 (Four Lac Forty Two Thousand One Hundred Nineteen taka &
Paisa Fifty Four ) Only within fourteen (14) days of acceptance of this Notification of Award but not later than 19.01.2014 in accordance with ITT Clause
65.
iii.
Sign the Contract
within twenty Eight (28) days of issuance of this Notifications Award but not
later than 02.02.2014 in accordance with ITT Sub
Clause 69.2
You
may proceed with the execution of the work only upon completion of the above
tasks, you may also please not that this Notifications of Award shall constitute the
formation of this contract which shall become binding upon you.
You
are requested to proceed with the execution of the works on the basis that this
Nonfiction of Award shall constitute the formation of a Contract, which shall
become binding upon you.
We attach the draft Contract
and all other documents for your perusal and signature.
|
(Md. Rabiul Islam) Upazila Engineer Chirirbandar, Dinajpur. |
MEMO. NO.LGED/UE/CHI/DIN/2014/ 04 /1(20) DATED:
06 /01//2014
Copy For kind information & necessary
Action:-
01. The Chief Engineer, LGED, LGED
Bhaban Agargaon,
02. The
Director General, Directorate of Primary Education, Mirpur-2,
03. The Additional Chief Engineer (
04. The Director Program, PEDP-III, Primary Education Department, Mirpur-2,
05. The Superintending Engineer, LGED Dinajpur
Region, Dinajpur.
06. The Executive Engineer, LGED,
District: Dinajpur.
07. The Executive Engineer, Office of the
Superintending Engineer, LGED Dinajpur Region, Dinajpur.
08. The District Primary Education
Officers, District: Dinajpur
09. The Upazila Nirbahi Officer, Upazila : Chirirbandar, District: Dinajpur.
10. The Upazila Engineer, Upazila : _________________, District: Dinajpur
11. The Upazila
_____________________________Officer, Upazila : Chirirbandar,
District: Dinajpur
12. The Head Master,
13.
supervision & ensure quality of work as per
Estimate, Design & Specifications.
14. Mr............................................................................Work
Asstt. LGED, Chirirbandar, Dinajpur
for supervision & ensure quality of work as per Estimate,
Design & Specifications.
15. Office
Copy.
|
Upazila Engineer Chirirbandar, Dinajpur. |