LGED Tender Banner

Letter of Acceptance

 

 

Government of the People's Republic of Bangladesh

Local Government Engineering Department

Office of the Executive Engineer

District: Satkhira.

www.lged.gov.bd

 

Memo No. LGED/XEN/Sat/2015/61                                                     Date: 07.01.2016 

 

 

To :

       

       ST-ME-DCL (JV)

       H#22, R#12, Nikunjo-2, Khilkhet, Dhaka.

.

 

 

 

 

Subject: Notification of Award Contract No- CCRIP/ADB/SATK/UZR/2015/W-30

 

 

 

This is to notify you that your Bid dated 05.11.15 for execution of the Improvement of (a) Noabenki - Munshigonj - Haronagar - Bhetkhali – Zadaha - Nurnagar hat - Khanpur road from Ch: 18800-26102m (ID No-287862002) Upazil Shyamnagar, District-Satkhira; (b) Parulia GC - Subornabad GC road from Ch: 00-6061m (ID No-287252005) Upazila Debhata, District-Satkhira & (c) Khanpur Baliadanga GCCR - Uzirpur via Gobindokati hat road from Ch: 00-2775m (ID No-287472004) Upazila Kaligonj, District-Satkhira. Package No-CCRIP/ADB/SATK/UZR/2015/W-30 Tender No-02/2015-16 for the Accepted Contract Amount of the equivalent of                             Tk. 17,35,55,543.02 (Taka- Seventeen Crore Thirty Five Lac Fifty Five Thousand Five Hundred Forty Three and Paisa Two) only as corrected and modified in accordance with the Instructions to Bidders is hereby accepted by our Agency.

 

 

 

You are requested to furnish the Performance Security amount of Tk. 1,73,56,000.00 (Taka- One Crore Seventy Three Lac Fifty Six Thousand) only within 28 days in accordance with the Condition of Contract (but not letter than 03.02.2016), using for that purpose the Performance Security Form included in Section 9 (Contract Forms) of the Bidding Document.

 

 

We accept that Mr. Saraj Kumar Sarkar, Ex. Additional Chief Engineer, LGED be appointed as the Adjudicator.

.

 

 

Authorized Signature              :

 

 

Name and Title of Signatory   :  A S M Shahedur Rahim, Executive Engineer.

Name of Agency                     :  LGED, Satkhira.

                                                   email:xen.satkhira@lged.gov.bd

 

 

 

Attachment: Contract Agreement

 

 

   C C.

1.         The Chief Engineer, LGED, LGED Bhaban, Agargaon, Dhaka-1207.

2.         The Director General, CPTU, IMED, Block-12.2nd floor, Sher-e-Bangla Nagar, Dhaka-1207.

 

3.         The Additional Chief Engineer,(Implementation), LGED Bhaban, Agargaon, Dhaka-1207.

4.         The Additional Chief Engineer, LGED, Khulna Division, LGED Bhaban, Khulna.

5.         The Superintending Engineer, LGED, Khulna Region, LGED Bhaban, Khulna.

6.         The Project Director, Coastal Climate Resilient Infrastructure Project (CCRIP). RDEC,

 LGED Bhaban, Agargaon , Dhaka-1207 

7.          The Team Leaders, DSC and MSC, CCRIP, Level-03 RDEC-LGED, Bhaban, Dhaka-1207.

8.         The Senior Assistant Engineer, LGED, Satkhira.

9.         The Senior Assistant Engineer, CCRIP, Khulna Region, District-Khulna.

10..       The Upazila Engineer, LGED, Upazila: Debhata/Kaligonj/Shyamnagar, District: Satkhira.

11.        The Assistant Engineer, LGED GIS Unit, Level-4, LGED Bhaban, Agargaon, Dhaka-1207.

12.        .Asian Development Bamk, Bangladesh Resident Mission, Agargoan, Dhaka.

13.        The Resident Engineer, CCRIP, Khulna Region, District-Khulna. .