Memo No.LGED/ XEN/Chua/2016/524                                                                                           Dated:   13-04-2016

 

 

Notification of Award (Form PW3-6)

 

 

      Latest date of Commencement:  17-05-2016           Intended of Completion  :     17-05-2017

To

            M/S. Saiful Hasan Joardar

Contractor

Baro Bazar, Chuadanga.

 

This is to notify you that your tender dated 23-02-2016 for the execution of the works Part-A: Improvement of  Gholdari GC-Sarajgonj R&H (Alamdanga Portion) road from at (Ch.0.0m to 1080m) UZR, E.L=1.08kmm, Road ID:218072010, Upazila: Alamdanga & Part-B: Improvement of  Nilmonigonj GC- Dingada GC road from at (Ch: 0.0m-6500m) & (10750m-11650m) UZR, E.L=7.40km,Road ID: 215232003 Upazila: Sadar, District: Chuadanga. (Package No: LGED/SRIIP/CHU/W-244  under Sustainable Rural Infrastructure Improvement Project (SRIIP) for the Contract Price of  Tk. 1,90,31,384.26  (Taka One  Crore Ninety  Lac Thirty one Thousand Three Hundred Eighty four & paisa twenty  six only) as corrected and modified in accordance with the instructions to Tenderer  has been  approved by Project Director.

 

You are thus requested to take following actions:

 

·                     accept in writing the Notification of Award within seven(7) working days of its issuance Pursuant

to ITT Sub Clause 63.1.

 

·                     Furnish a performance Security in the form as specified and in the amount Tk.9,52,000.00 ( Nine Lac Fifty Two Thousand ) within fourteen (14) days of acceptance of this Notification of Award but not letter than 26-04-.2016 in accordance with ITT Clause 65.

 

·                     Sign the Contract within twenty eight (28) days of issuance of this Notification of Award but not later than 10-05-2016 in accordance with ITT Sub Clause 69.2.

 

 You may proceed with the execution of the works only upon completion of the above tasks. You may also please note that this Notification of Award shall constitute the formation of this Contract. Which shall become binding upon you.

 

We attach the draft Contract and all other documents for your perusal and Signature.

 

                                                                                                                     Sd/=

 

                                                                                                        (Md. Ashraful Islam)

                                                                                                         Executive Engineer

                                                                                                         LGED, Chuadanga       

Copy  to:-

01.          The Director General, CPTU, IMED, Dhaka.Request for published in CPTU Website.

02.          The Superintending Engineer, LGED, Jessore Region, LGED Bhaban, Dist: Jessore

03.          The  Project Director, SRIIP, LGED, LGED Bhaban, Agargaon, Dhaka-1207.

04.          The Deputy Project Director, SRIIP, Jessore Region, LGED Bhaban, Dist: Jessore

05.          The District Accounts Officer, Dist: Chuadanga.

06.          The Upazila Engineer, Upazila: Chuadanga Sadar/Alamdanga, Dist: Chuadanga.

07.          The Assistant Engineer,GIS Unit,LGED, H/Q, Dhaka-1207.He is requested for published in LGED Website.

08.          The Team Leader, D&S Consultant, SRIIP, LGED H/Q, Agargaon, Dhaka.

09.          Office Copy.