Memo no.LGED/UE/Mat(Uttar)/2012/590 Date : 18/06/2012.
To M/S TECHNO
HVAC SYSTEM LTD Pro-Md
Mizanur Rahman.
190/Tejgon,C/A Dhaka |
Latest Date of Commencement :
25/06/2012. Date of Completion: : 24/09/2013. |
This is to
notify you that your Tender dated 09-05-2012 for the execution of
the Works for Project: Third Primary
Education Development Program(PEDP-III) Re-Construction
of Probati Shishu Kanon RNGPS & 67No Madhay Eklaspur,Chengerchar Ahamadia
GPS Including Furniture Supply Package No-PEDP-III/CHD/MAU/2011-2012/W1.0316 for the Contract Price of Tk 1,69,55,804.90(One
Core Sixty Nine Lac Fifty Fivey Thousend Eight Hunered Four Point Paisa Ninty
only) as corrected and modified in accordance with the Instructions
to Tenderers, has been
approved by Additional
Chief Engineer, LGED,Agargon,Sher E Bangla Nagar,Dhaka-1207, Memo
No-LGED/PEDP-III/D-5/ 2012(Part-33)2644 Dated: 13/06/2012.
You are thus
requested to take following actions:
i.
accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to
ii.
furnish a Performance Security in the form as specified and in the amount of
Tk 8,47,800.00(Eight Lac Forty Seven
Thousend Eight Hundered)within fourteen (14) days of acceptance of this
Notification of Award but not later than
01/07/2012, in
accordance with
iii.
sign the Contract within twenty
eight (28) days of issuance of this Notification of Award but not later than 15/07/2012, in accordance with
You may
proceed with the execution of the Works only upon completion of the
above tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract and all other documents for
your perusal and signature.
|
(Ratan Lal Sarkar) |
|
Upazila
Engineer Matlab
Uttar,Chandpur. |
C.C
01. The Additional Chief
Engineer(Maintanance),LGED H/Q,(3rd Floor),Agargone,Sarabangla
Nagar,Dhaka-1207.
02. The Executive
Engineer,LGED,Chandpur.
03. The Executive
Engineer(Training & Primary),LGED,Comilla Rezon,Comilla.
04. The District Education
Officer,Chandpur.
05. The Upazila Nirbahi
Officer,Matlab Uttar,Chandpur.
06. The Upazila Education
Officer,Matlab Uttar,Chandpur.
07.Mr.................................................................................SAE,LGED,Matlab
Uttar,Chandpur.
08.
Mr.................................................................Work
Assistant,LGED,Matlab Uttar,Chandpur.
09.HeadMaster
.................................................. Primary School.Matlab
Uttar,Chandpur.
10.Office
Copy.
Government
of the People’s Republic of
Local Government Engineering Department
Office of the Upazila Engineer
Matlab Uttar, Chandpur.
Memo no.LGED/UE/Mat(Uttar)/2012/591 Date : 18/06/2012.
To M/S
Kasam & Brothers and Nahar Traders(JV)
Nahar
Shopping Complex.
Sengarchar
Bazar,Matlab Uttar,Chandpur |
Latest Date of Commencement :
25/06/2012. Date of Completion: : 24/09/2013. |
This is to
notify you that your Tender dated 09-05-2012 for the execution of
the Works for Project: Third Primary
Education Development Program(PEDP-III) Re-Construction
of Rajurkandi & Bahadurpur GPS Including Furniture Supply Package No-PEDP-III/CHD/MAU/2011-2012/W1.0317 for the Contract Price of Tk 1,13,03,669.83(One
Core Thirteenth Lac Three Thousend Six Hunered Sixty Nine Point Paisa Eighty
Three only) as corrected and modified in accordance with the
Instructions to Tenderers, has been approved by Additional Chief Engineer, LGED,Agargon,Sher E Bangla
Nagar,Dhaka-1207, Memo No-LGED/PEDP-III/D-5/ 2012(Part-33)2644 Dated:
13/06/2012.
You are thus
requested to take following actions:
i.
accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to
ii.
furnish a Performance Security in the form as specified and in the amount of
Tk 5,65,200.00 (Five Lac Sixty Five
Thousend Two Hundered)within fourteen (14) days of acceptance of this
Notification of Award but not later than
01/07/2012, in
accordance with
iii.
sign the Contract within twenty
eight (28) days of issuance of this Notification of Award but not later than 15/07/2012, in accordance with
You may
proceed with the execution of the Works only upon completion of the
above tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract and all other documents for
your perusal and signature.
|
(Ratan Lal Sarkar) |
|
Upazila
Engineer Matlab
Uttar,Chandpur. |
C.C
01. The Additional Chief
Engineer(Maintanance),LGED H/Q,(3rd Floor),Agargone,Sarabangla
Nagar,Dhaka-1207.
02. The Executive
Engineer,LGED,Chandpur.
03. The Executive
Engineer(Training & Primary),LGED,Comilla Rezon,Comilla.
04. The District Education
Officer,Chandpur.
05. The Upazila Nirbahi
Officer,Matlab Uttar,Chandpur.
06. The Upazila Education
Officer,Matlab Uttar,Chandpur.
07.Mr.................................................................................SAE,LGED,Matlab
Uttar,Chandpur.
08. Mr.................................................................Work
Assistant,LGED,Matlab Uttar,Chandpur.
09.HeadMaster
.................................................. Primary School.Matlab
Uttar,Chandpur.
10.Office
Copy.
Government
of the People’s Republic of
Local Government Engineering Department
Office of the Upazila Engineer
Matlab Uttar, Chandpur.
Memo no.LGED/UE/Mat(Uttar)/2012/592 Date : 18/06/2012.
To M/s
S.Jaman & Co
543/Sawrapara, Mirpur, |
Latest Date of Commencement :
25/06/2012. Date of Completion: : 24/09/2013. |
This is to
notify you that your Tender dated 09-05-2012 for the execution of
the Works for Project: Third Primary
Education Development Program(PEDP-III) Re-Construction
of Mohanpur & Failakandi GPS Including Furniture Supply Package No-PEDP-III/CHD/MAU/2011-2012/W1.0318 for the Contract Price of Tk 1,13,05,019.17(One
Core Thirteenth Lac Five Thousend Nineteenth Point Paisa Sevntheenth only)
as corrected and modified in accordance with the Instructions to Tenderers, has been approved by Additional Chief Engineer,
LGED,Agargon,Sher E Bangla Nagar,Dhaka-1207, Memo No-LGED/PEDP-III/D-5/ 2012(Part-33)2644
Dated: 13/06/2012.
You are thus
requested to take following actions:
i.
accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to
ii. furnish
a Performance Security in the form as specified and in the amount of
Tk 5,65,300.00 (Five Lac Sixty Five
Thousend Three Hundered)within fourteen (14) days of acceptance of this
Notification of Award but not later than
01/07/2012, in
accordance with
iii. sign
the Contract within twenty eight (28) days of issuance of this Notification of
Award but not later than 15/07/2012,
in accordance with
You may
proceed with the execution of the Works only upon completion of the
above tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract and all other documents for
your perusal and signature.
|
(Ratan Lal Sarkar) |
|
Upazila
Engineer Matlab
Uttar,Chandpur. |
C.C
01. The Additional Chief
Engineer(Maintanance),LGED H/Q,(3rd Floor),Agargone,Sarabangla
Nagar,Dhaka-1207.
02. The Executive
Engineer,LGED,Chandpur.
03. The Executive
Engineer(Training & Primary),LGED,Comilla Rezon,Comilla.
04. The District Education
Officer,Chandpur.
05. The Upazila Nirbahi
Officer,Matlab Uttar,Chandpur.
06. The Upazila Education
Officer,Matlab Uttar,Chandpur.
07.Mr.................................................................................SAE,LGED,Matlab
Uttar,Chandpur.
08.
Mr.................................................................Work
Assistant,LGED,Matlab Uttar,Chandpur.
09.HeadMaster
.................................................. Primary School.Matlab
Uttar,Chandpur.
10.Office
Copy.
Government
of the People’s Republic of
Local Government Engineering Department
Office of the Upazila Engineer
Matlab Uttar, Chandpur.
Memo no.LGED/UE/Mat(Uttar)/2012/594 Date : 18/06/2012.
To M/S Khoku
Enterprise
Adurvity,Sengarchar Bazar,Matlab Uttar,Chandpur |
Latest Date of Commencement :
25/06/2012. Date of Completion: : 24/06/2013. |
This is to
notify you that your Tender dated 09-05-2012 for the execution of
the Works for Project: Third Primary
Education Development Program(PEDP-III) Construction
of Additional Class Room for Dhakkin Sardarkandi & Nadamdi GPS (Rural)
Including Furniture Supply,Package No-PEDP-III/CHD/MAU/2011-2012/W2.0461 for the Contract Price of Tk 65,81,007.90(Sixty
Five Lac Eighty One Thousend Seven Point & Paisa Ninty only) as
corrected and modified in accordance with the Instructions to Tenderers, has been approved by Additional Chief Engineer,
LGED,Agargon,Sher E Bangla Nagar,Dhaka-1207, Memo No-LGED/PEDP-III/D-5/ 2012(Part-33)2644
Dated: 13/06/2012.
You are thus
requested to take following actions:
i.accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to
ii.furnish a Performance Security in the form as specified and in the amount of
Tk 3,29,100.00 (Three Lac Twenty Nine
Thousend One Hundered)within fourteen (14) days of acceptance of this
Notification of Award but not later than
01/07/2012, in
accordance with
iii.sign the Contract within twenty eight (28)
days of issuance of this Notification of Award
but not later than 15/07/2012,
in accordance with
You may
proceed with the execution of the Works only upon completion of the
above tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract and all other documents for
your perusal and signature.
|
(Ratan Lal Sarkar) |
|
Upazila
Engineer Matlab
Uttar,Chandpur. |
C.C
01. The Additional Chief
Engineer(Maintanance),LGED H/Q,(3rd Floor),Agargone,Sarabangla
Nagar,Dhaka-1207.
02. The Executive
Engineer,LGED,Chandpur.
03. The Executive
Engineer(Training & Primary),LGED,Comilla Rezon,Comilla.
04. The District Education
Officer,Chandpur.
05. The Upazila Nirbahi
Officer,Matlab Uttar,Chandpur.
06. The Upazila Education
Officer,Matlab Uttar,Chandpur.
07.Mr.................................................................................SAE,LGED,Matlab
Uttar,Chandpur.
08.
Mr.................................................................Work
Assistant,LGED,Matlab Uttar,Chandpur.
09.HeadMaster
.................................................. Primary School.Matlab
Uttar,Chandpur.
10.Office
Copy.
Government
of the People’s Republic of
Local Government Engineering Department
Office of the Upazila Engineer
Matlab Uttar, Chandpur.
Memo no.LGED/UE/Mat(Uttar)/2012/593 Date : 18/06/2012.
To M/S
Kasam & Brothers and Nahar Traders(JV)
Nahar
Shopping Complex.
Sengarchar
Bazar,Matlab Uttar,Chandpur |
Latest Date of Commencement :
25/06/2012. Date of Completion: : 24/06/2013. |
This is to
notify you that your Tender dated 09-05-2012 for the execution of
the Works for Project: Third Primary
Education Development Program(PEDP-III) Construction
of Additional Class Room for Naobhanga RNGPS & Otarchar GPS (Rural)
Including Furniture Supply,Package No-PEDP-III/CHD/MAU/2011-2012/W2.0460 for the Contract Price of Tk 77,61,156.00(Seventy
Seven Lac Sixty One Thousend One Hunered Fifty Six only) as
corrected and modified in accordance with the Instructions to Tenderers, has been approved by Additional Chief Engineer,
LGED,Agargon,Sher E Bangla Nagar,Dhaka-1207, Memo No-LGED/PEDP-III/D-5/ 2012(Part-33)2644
Dated: 13/06/2012.
You are thus
requested to take following actions:
i.accept in writing the Notification of Award within
seven (7) working days of its issuance pursuant to
ii.furnish
a Performance Security in the form as specified and in the amount of
Tk 3,88,100.00 (Three Lac Eighty
Eignt Thousend One Hundered)within fourteen (14) days of acceptance of
this Notification of Award but not later
than 01/07/2012, in
accordance with
iii.sign the Contract within twenty eight (28)
days of issuance of this Notification of Award
but not later than 15/07/2012,
in accordance with
You may
proceed with the execution of the Works only upon completion of the
above tasks. You may also please note that this Notification of Award shall
constitute the formation of this Contract
which shall become binding upon you.
We attach the draft Contract and all other documents for
your perusal and signature.
|
(Ratan Lal Sarkar) |
|
Upazila
Engineer Matlab
Uttar,Chandpur. |
C.C
01. The Additional Chief
Engineer(Maintanance),LGED H/Q,(3rd Floor),Agargone,Sarabangla
Nagar,Dhaka-1207.
02. The Executive
Engineer,LGED,Chandpur.
03. The Executive
Engineer(Training & Primary),LGED,Comilla Rezon,Comilla.
04. The District Education
Officer,Chandpur.
05. The Upazila Nirbahi
Officer,Matlab Uttar,Chandpur.
06. The Upazila Education
Officer,Matlab Uttar,Chandpur.
07.Mr.................................................................................SAE,LGED,Matlab
Uttar,Chandpur.
08.
Mr.................................................................Work
Assistant,LGED,Matlab Uttar,Chandpur.
09.HeadMaster
.................................................. Primary School.Matlab
Uttar,Chandpur.
10.Office
Copy.
Government
of the People’s Republic of
Local Government Engineering Department
Office of the Upazila Engineer
Matlab Uttar, Chandpur.
Memo no.LGED/UE/Mat(Uttar)/2012/595 Date : 18/06/2012.
To M/S Khoku
Enterprise
Adurvity,Sengarchar Bazar,Matlab Uttar,Chandpur |
Latest Date of Commencement :
25/06/2012. Date of Completion: : 24/06/2013. |
This is to
notify you that your Tender dated 09-05-2012 for the execution of
the Works for Project: Third Primary
Education Development Program(PEDP-III) Construction
of Additional Class Room for Choto Haldia GPS (Rural) Including Furniture
Supply,Package No-PEDP-III/CHD/MAU/2011-2012/W1.0970
for the Contract Price of Tk 57,00,115.54(Fifty Seven Lac One Hundred
Fifteenth Point & Paisa Fifty Four
only) as corrected and modified in accordance with the Instructions
to Tenderers, has been
approved by Additional
Chief Engineer, LGED,Agargon,Sher E Bangla Nagar,Dhaka-1207, Memo
No-LGED/PEDP-III/D-5/ 2012(Part-33)2644 Dated: 13/06/2012.
You are thus
requested to take following actions:
i.accept
in writing the Notification of Award within seven (7) working days of its
issuance pursuant to
ii.furnish a Performance Security in the form as specified and in the amount of
Tk 2,85,100.00 (Two Lac Eighty Five
Thousend One Hundered)within fourteen (14) days of acceptance of this
Notification of Award but not later than
01/07/2012, in
accordance with
iii.sign the Contract within twenty eight (28)
days of issuance of this Notification of Award
but not later than 15/07/2012,
in accordance with
You may proceed
with the execution of the Works only upon completion of the above tasks.
You may also please note that this Notification of Award shall constitute the
formation of this Contract which shall
become binding upon you.
We attach the draft Contract and all other documents for
your perusal and signature.
|
(Ratan Lal Sarkar) |
|
Upazila
Engineer Matlab
Uttar,Chandpur. |
C.C
01. The Additional Chief
Engineer(Maintanance),LGED H/Q,(3rd Floor),Agargone,Sarabangla
Nagar,Dhaka-1207.
02. The Executive Engineer,LGED,Chandpur.
03. The Executive
Engineer(Training & Primary),LGED,Comilla Rezon,Comilla.
04. The District Education
Officer,Chandpur.
05. The Upazila Nirbahi
Officer,Matlab Uttar,Chandpur.
06. The Upazila Education
Officer,Matlab Uttar,Chandpur.
07.Mr.................................................................................SAE,LGED,Matlab
Uttar,Chandpur.
08.
Mr.................................................................Work
Assistant,LGED,Matlab Uttar,Chandpur.
09.HeadMaster ..................................................
Primary School.Matlab Uttar,Chandpur.
10.Office
Copy.