LGED Tender Banner
GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
Local Government Engineering Department
Office of the Project Director
South-Western Bangladesh Rural Development Project (SWBRDP)
LGED Bhaban, Level- 10, Agargaon, Sher-e-bangla Nagar, Dhaka-1207


Memo No. LGED/PD/SWBRDP/BRG(LB)-01/2012/913                                                                                     Date:10.06.2012
IFPQ : 01/2011-12
Invitation for Pre-qualification
1 Ministry/Division  Local Government, Rural Development & Co-operatives/ Local Government Division
2  Agency   Local Government Engineering Department (LGED)
3 Procuring Entity Name  Project Director, South-Western Bangladesh Rural Development Project (SWBRDP)
4 Procuring Entity Code  N/A
5 Procuring Entity District  Dhaka
6 Invitation for  Pre-qualification of  Construction of 560.00m long PC Girder Bridge over Kocha River at ch. 23520m on Shanuhar-Dhamura-Satla via Jolla Road (ID No. 506942003) under Uzirpur Upazila, District: Barisal, Bangladesh.  
7 Invitation Ref. No.  Memo No. LGED/PD/SWBRDP/BRG(LB)-01/2012/913
8 Date  10.06.2012
KEY INFORMATION      
9 Procurement Method  Local Competitive Bidding (LCB)
FUNDING INFORMATION      
10 Budget and Source of Funds  GOB & JICA
11 Development Partner  Japan International Cooparation Agency (JICA) 
PARTICULAR INFORMATION      
12 Project / Programme Code   N/A
13 Project / Programme Name   South-Western Bangladesh Rural Development Project (SWBRDP)
14 Proposed Tender Package No. SWBRDP/BRG(LB)/BARI-56
15 Proposed Tender Package Name  Pre-qualification of  Construction of 560.00m long PC Girder Bridge over Kocha River at ch. 23520m on Shanuhar-Dhamura-Satla via Jolla Road (ID No. 506942003) under Uzirpur Upazila, District: Barisal  
16 Pre-qualification Publication Date   within 14th June,2012
17 Pre-qualification Document Last Selling Date 17th July,2012 upto normal office hour
18 Pre-qualification Closing (Submission)Date&Time  18th July,2012 & 2:00 PM
19 Pre-qualification Opening Date and Time 18th July,2012 & 2:30 PM
20 Name & Address of the Office(s)  
  -Selling Pre-qualification Document(Principal)   Office of the Project Director, South-Western Bangladesh Rural Development Project (SWBRDP), LGED Bhaban, Level- 10, Agargaon, Sher-e-bangla Nagar, Dhaka-1207
  -Selling Pre-qualification Document(Others)   1. Office of the Superintending Engineer, LGED, Barisal Region, Barisal.                                             2. Office of the Executive Engineer, LGED, Barisal.
  -Receiving Pre-qualification Document   Office of the Project Director, South-Western Bangladesh Rural Development Project (SWBRDP), LGED Bhaban, Level- 10, Agargaon, Sher-e-bangla Nagar, Dhaka-1207
  -Opening Pre-qualification Document   Office of the Project Director, South-Western Bangladesh Rural Development Project (SWBRDP), LGED Bhaban, Level- 10, Agargaon, Sher-e-bangla Nagar, Dhaka-1207
21 Place/Date/Time of Pre-qualification Meeting  Place : Office of the Project Director, South-Western Bangladesh Rural Development Project (SWBRDP), LGED Bhaban, Level- 10, Agargaon, Sher-e-bangla Nagar, Dhaka-1207.
Date : 27th June,2012 & Time : 11:00 AM
INFORMATION FOR APPLICANT      
22 Eligibility of Applicant (a) Valid Trade License, Tax Identifacation Number (TIN) with up-to-date Income tax clearance certificate, VAT registration certificate etc;                                                                                                                                    (b) The period of general experience of the applicant in the construction work shall be at least last 5(five) years and with activity at least nine(9) months in each year;                                                                         (c) The required number of similar contract constructed shall be 2(two) over a period of last 10(ten) years and must have experience of constructing at least 1(one) 500m long PC Girder bridge over a river in a single contract;                                                                                                                                      (d) The required average annual construction turnover within the last 5(five) years shall be minimum Tk.48 (forty eight) crore.                                                                                                                                                            All qualification criteria described in detail under section-III of the pre qualification document 
23 Brief Description of Works  a) Appxoimate length of bridge: 560.00m (14 Span, Each span length=39.95m) b) Two lane bridge with bothside walkway; c) Pile dia : 800-1000mm, Length of pile: 28-34m d) Approach road with slope protection work.
24 Brief Description of Related Services  N/A
25 Pre-qualification Document Price Tk. 20,000.00
LOT INFORMATION    
 
  Lot No  Identification of Lot                           Location                                                           Completion Time
26 1 Pre-qualification of  Construction of 560.00m long PC Girder Bridge over Kocha River at ch. 23520m on Shanuhar-Dhamura-Satla via Jolla Road (ID No. 506942003) under Uzirpur Upazila, District: Barisal, Bangladesh.          Upazila- Uzirpur, District- Barisal               30 Months from the date of signing of contract
PROCURING ENTITY DETAILS      
27 Name of Official Inviting Pre-qualification Noor Mohammad
28 Designation of Official Inviting Pre-qualification Project Director, South-Western Bangladesh Rural Development Project (SWBRDP)
29 Address of Official Inviting Pre-qualification Office of the Project Director, South-Western Bangladesh Rural Development Project (SWBRDP), LGED Bhaban, Level- 10, Agargaon, Sher-e-bangla Nagar, Dhaka-1207
30 Contact details of Official Inviting Pre-qualification Tel. No. 9132653, Fax No. 9133474, E-mail : pd.swbrdp@lged.gov.bd
31 The procuring entity reserves the right to accept or reject all pre-qualifications.  
(Noor Mohammad)
Projrct Director, SWBRDP
LGED, Dhaka
Copy for kind information &necessary action
1. CE, LGED HQ, LGED Bhaban, Agargaon, Dhaka.
2. SE,LGED, Barisal Region, Barisal.
3. Senior Representative, JICA Bangladesh Office- A pre qualification document is enclosed herewith for his kind perusal.
4. EE, LGED, Barisal.
5. The Editor,The daily Star/New Nation/Samakal/Ittefaq- He is requested to publish the aforsaid notice in his daily within 14.06.2012   
for a single issue only.
6. Notice Board ……………………………………………
(Noor Mohammad)
Projrct Director, SWBRDP
LGED, Dhaka