OFFICE
OF THE
KHAGRACHARI
POURASAVA
DISTRICT:
KHAGRACHARI
Invitation for Bid (IFB)-No:01/2015-2016/UGIIP-III
(Works)
|
|
|||||||||||
1 |
Ministry / Division |
Local Government
Rural Development and Cooperatives /
Local Government Division |
||||||||||
2 |
Agency |
Khagrachari Pourasahva |
||||||||||
3 |
Procuring Entity Name |
Mayor,
Khagrachari Pourashava |
||||||||||
4 |
Procuring Entity Code |
|
||||||||||
5 |
Procuring Entity
District |
Khagrachari |
||||||||||
6 |
Invitation for |
Bid of 01 no
sub-project |
||||||||||
7 |
Invitation Ref No |
LGED/PD/UGIIP-III/P-54/2015/2040(1) |
||||||||||
8 |
Date |
29-11-2015 |
||||||||||
|
KEY
INFORMATION |
|||||||||||
9 |
Procurement Method |
National Open Biding
Method |
||||||||||
|
FUNDING INFORMATION |
|||||||||||
10 |
Budget and Source of
Funds |
GoB & ADB. |
||||||||||
11 |
Development Partners (if applicable) |
Asian Development
Bank (ADB) & OFID |
||||||||||
|
PARTICULAR
INFORMATION |
|||||||||||
12 |
Project / Programme
Code |
39295-013 BAN |
||||||||||
13 |
Project
/ Programme Name |
Third Urban
Governance and Infrastructure Improvement (Sector)
Project (UGIIP-III) |
||||||||||
14 |
Bid Sub-Project No. |
UGIIP-III-I / KHAG / UT+DR / 01 / 2015 |
||||||||||
15 |
Bid Sub-Project Name |
Improvement,
Construction & Rehabilitation of Roads & Construction of Drains. (As described in Sl.
No. 26), |
||||||||||
16 |
Bid Publication Date |
05/11/2015 |
||||||||||
|
|
Date |
Time |
|||||||||
17 |
Bid Last Selling Date
and Time |
06/12/2015 |
5 : 00 PM |
|||||||||
18 |
Bid Closing Date and
Time |
07/12/2015 |
2 : 00 PM |
|||||||||
19 |
Name & Address of
the office(s) |
Name: |
Address: |
|||||||||
|
Selling Bid Document (Principal) |
The
Executive Engineer, Khagrachari Pourashava, District:
Khagrachari. |
||||||||||
Selling Bid Document (Others) |
1.
Deputy
Commissioner, District: Khagrachari. 2.
Superintendent
of Police, District:
Khagrachari. 3.
Executive
Engineer, LGED / DPHE District: Khagrachari. |
|||||||||||
Places of Receiving Bid Document |
The Executive
Engineer, Khagrachari Pourashava, District:
Khagrachari. |
|||||||||||
Place of Opening Bid Document |
The Executive Engineer,
Khagrachari Pourashava, District:
Khagrachari. |
|||||||||||
|
|
Date |
Time |
|||||||||
20 |
Time of Opening Bid |
07/12/2015 |
2 : 30 PM |
|||||||||
|
|
Date and place |
Time |
|||||||||
21 |
Pre-Bid Meeting |
23/11/2015 |
11.00 AM |
|||||||||
|
INFORMATION FOR
BIDDER |
|||||||||||
22 |
Eligibility of Bidder |
No nationality restrictions apply, other than any restrictions arising
from Clause ITT 5.11. |
||||||||||
23 |
Brief Description
of Works |
As stated in the SL
no 26 |
||||||||||
24 |
Brief Description of
Physical Services |
As stated in the SL
no 26 |
||||||||||
25 |
Price of Bid Document |
As stated in the SL
no 26 |
||||||||||
26 |
Sub-project No |
Identity of Scheme
in PDP |
Identification of Package |
Location |
Price of Bid Document (Tk) |
Amount of Bid Security (Tk) |
Completion Time in Days |
|||||
UGIIP-III-I / KHAG / UT+DR / 01 / 2015 |
Lot-1 (UT+DR) |
Khagrachari
Pourashava |
11,000.00 |
1,100,000.00 |
365 |
|||||||
Roads
: Lot-1 (UT) |
||||||||||||
14011 & 14012 |
Rehabilitation
& widening of road starting from Culvert of Pankhaiyapara Road up to APBN
Gate. (ch-0+000 to 1+083)m and Connecting road starting from main road chainage 650 to khal (ch-0+000 to
0+016)m by DBC. including Footpath. |
|||||||||||
14012 |
Improvement
of connecting road by HBB starting from end of Existing HBB road and just
infront of H/O Shilip Paul to the Anondonagar H/O Rabon Kormokar (ch-0+000 to
0+210)m & 2 nos. connecting road starting from main road to Proposed CC
road (ch-0+000 to 0+098)m, (0+000 to 0+093)m at Anondonagar area. |
|||||||||||
14011 & 14012 |
Improvement
of connecting road by HBB starting from end of Existing HBB road and infront
of H/O Shilip Paul up to Rupnagar HBB Road. (ch-0+000 to 0+353)m. |
|||||||||||
14011 & 14012 |
Construction
of connecting road by CC starting from
Existing Box Culvert of APBN road up to end of HBB road infront of H/O
Shilip Paul to (ch-0+000 to 0+354)m. |
|||||||||||
14011 & 14012 |
Rehabilitation
of connecting road by CC starting from
Existing Box Culvert of Pankhaiyapara Road via Anondonogar Kali Mondir
up to Sluice Gate (ch-0+000 to 0+932)m |
|||||||||||
Drains : Lot-1 (DR) |
||||||||||||
14012 |
Construction
of RCC Drain starting from APBN Road up to Anandanagor Canal. (Ch 0+000 to
0+676)m |
|||||||||||
14016 |
Construction
of Drain (Part-A) Starting from Pankhiyapara existing Culvert to Primary
Drain. (Ch 0+000 to 0+501m. |
|||||||||||
14016 |
Construction
of Drain (Part-B) Starting from H/O. Rabon Kormokar to Primary Drain. (Ch
0+000 to 0+431)m. |
|||||||||||
14016 |
Construction
of Drain (Part-C) Starting from H/O. Mridul Babu Via Kali Mondir to Part A
secondary Drain. (Ch 0+000 to 0+405)m |
|||||||||||
14016 |
Construction
of Drain (Part-D) Starting from H/O. Kanchankor to Part-C Tertiary Drain. (Ch
0+000 to 0+120)m |
|||||||||||
Lot-2 (UT+DR) |
|
|||||||||||
Roads
: Lot-2 (UT) |
||||||||||||
14016 |
(a) Rehabilitation &
widening of road by CC starting from Pankhaiyapara Road to Milonpur road via
Bouddhayo Mondir. (ch-0+000 to 0+570)m. (b) Improvement of connecting road
starting from Pankhaiyapara road to main road.(ch-0+000 to 0+254)m ©
Improvement of connecting road starting from main road ch 172 to Khal Ghat.
(ch-0+000 to 0+098)m |
|||||||||||
|
|
14016 |
Part A : Rehabilitationt of road by CC starting from
Pankhaiyapara road up to Khagrachari Khal Ghat (0+000 to 0+100)m and
connecting road just infront of H/O Afcer up to Pankhaiyapara road under
Milonpur area (ch-0+000 to 0+70)m. Part
B : Rehabilitation of connecting road by CC starting from
Pankhaiyapara road up to infront of Hotel Gairing (ch-0+000 to 0+236)m |
|
|
1,450,000.00 |
|
|||
14011 |
Rehabilitation of connecting
road by RCC starting from the Existing
CC road infront of H/O Banker Mohsin via Primary School cum Kali Mondir up to
Existing CC road (ch-0+000 to 0+254)m
& connecting road start from Pankhaiyapara Khal to main road (ch-0+000 to
0+264)m |
|||||||||
14024 |
Rehabilitation of road by DBC
starting from Khagrachari main road via bank of Changi river .(ch-0+000 to
0+287)m. and connecting near Changi River to Bus Terminal.(ch-0+270 to
0+539)m with 2 nos. of connectin road (a) starting from the infront of H/O
All-Osmani up to Mushlimpara road (ch-0+000 to 0+78)m & (b) starting from the infront of H/O Abdul
Jalil up to existing HBB road (ch-0+000
to 0+118)m |
|||||||||
14112 |
Rehabitation of Hospital Road
starting from Khagrachari Police Station via Mollapara connecting Road to
Khagrachari Hospital by seal coat. (ch 0+000 to 0+932)m |
|||||||||
Drains : Lot-2 (DR) |
||||||||||
14016 |
Construction of RCC Drain
within Kollonpur area Starting from Pankhiyapara Road Via H/O. Milton Burua
up to Khagrachari Khal. Ch 0+000 to 0+407m) and Connecting Drain (a) starting
from Bouddhayo Mondir up to Khal. (Ch 0+000 to 0+098)m, Connecting Drain (b)
Starting from Pankhiyapara Road to Khagrachari Khal. (Ch 0+000 to 0+223)m,
Connecting drain (c) starting from near Bouddhya Mondir up to Main Drain. (Ch
0+00 to 0+045)m |
|||||||||
14016 |
Construction of Drain from
Pankhiyapara Road to Khagrachari Khal Ghat. Ch 0+000 to 0+097m and
Construction of Connecting Drain starting from Pankhiyapara Road up to Main
Drain. (Ch 0+000 to 0+070)m. |
|||||||||
14016 |
Construction of Drain starting
from Pankhiyapara Road to near existing Wooden Bridge. (Ch 0+000 to 0+118)m |
|||||||||
14016 |
Construction of Outfall Drain
at Anandanagor Area. (Ch.0+000 to
1+500)m |
|||||||||
|
PROCURING ENTITY
DETAILS |
|||||||||
27 |
Bid Validity Period |
120 Days |
||||||||
28 |
Name of Official
Inviting Bid |
Name : Dilip Kumar
Biswas |
||||||||
29 |
Designation of
Official Inviting Bid |
The
Executive Engineer, Khagrachari.
Pourashava, District:
Khagrachari. |
||||||||
30 |
Address of Official
Inviting Bid |
Khagrachari
Pourashava, District:
Khagrachari. |
||||||||
31 |
Contact details of
Official Inviting Bid |
Tel. No. |
Fax No. |
e-mail |
||||||
|
|
0371-61884 |
0371-61049 |
khagracharipoura@gmail.com |
||||||
32 |
The Procuring Entity
reserves the right to reject all the
Bids or annul the Bid proceedings |
|||||||||
(Name : Dilip Kumar
Biswas)
Executive
Engineer
Khagrachari Pourashava
Memo
No.Khag/poura/engg.dept./2015-2016/110 Date: 03/11/2015
C.C
1.
DG,
CPTU, IMED, He is requested to Publish
the Bid Notice in the CPTU website
2.
Superintending
Engineer, (Urban Management) RDEC Bhaban,
LGED, Dhaka-1207
3.
Superintending
Engineer, LGED, Chittagong Region / DPHE, Chittagong Circle.
4.
The
Project Director, UGIIP-III, Level-12, LGED Bhavan, Agargaon, Sher-e-Bangla
Nagar, Dhaka-1207.
5.
The
Deputy Commissioner, District: Khagrachari.
6.
The
Mayor, Khagrachari Pourashava, District
: Khagrachari.
7.
The
Superintendent of police, District : Khagrachari.
8.
The
Executive Engineer, LGED/R&H/WDB/ DPHE, District : Khagrachari.
9.
The
Team Leader, MDS Consultants, UGIIP-III, Level -12, LGED Bhavan, Agargaon,
Sher-e-Bangla Nagar, Dhaka-1207.
10.
Notice
Board UGIIP-III, Level -12, LGED Bhavan, Agargaon, Sher-e-Bangla Nagar,
Dhaka-1207.
11.
Notice
board.
(Name Dilip Kumar
Biswas.)
Executive
Engineer
Khagrachari Pourashava