OFFICE OF THE
PATUAKHALI POURASAVA
DISTRICT: PATUAKHALI
Invitation for Bid (IFB) – No 15 (2016 – 17).
(Works)
Memo
No. Patua. / Poura.
/ Engg / 2017/02 (21) Date : - 08/01/2017.
|
|
|
|
|||||||||||||
1 |
Ministry / Division |
Local Government Rural Development and Cooperatives / Local Government Division |
|
|||||||||||||
2 |
Agency |
Patuakhali Pourasahva |
|
|||||||||||||
3 |
Procuring Entity Name |
Mayor, Patuakhali Pourashava |
|
|||||||||||||
4 |
Procuring Entity Code |
N/A |
|
|||||||||||||
5 |
Procuring Entity District |
Patuakhali |
|
|||||||||||||
6 |
Invitation for |
Bid of 01 no sub-project |
|
|||||||||||||
7 |
Invitation Ref No |
Patua/ Pou/Engg./2017/02(21) |
|
|||||||||||||
8 |
Date |
Date :
08/01/2017. |
|
|||||||||||||
|
KEY
INFORMATION |
|
|
|||||||||||||
9 |
Procurement Method |
National Open Bidding Method |
|
|
||||||||||||
|
FUNDING INFORMATION |
|
|
|||||||||||||
10 |
Budget and Source of Funds |
GoB
& ADB. |
|
|
||||||||||||
11 |
Development
Partners (if applicable) |
Asian Development Bank (ADB) & OFID |
|
|
||||||||||||
|
PARTICULAR INFORMATION |
|
|
|||||||||||||
12 |
Project / Programme Code |
39295-013 BAN |
|
|||||||||||||
13 |
Project / Programme Name |
Third Urban Governance and Infrastructure Improvement (Sector) Project (UGIIP-III) |
|
|||||||||||||
14 |
Bid Sub-Project No. |
UGIIP-III-2/WB/PATU/UT+DR-01/2016
|
|
|||||||||||||
15 |
Bid Sub-Project Name |
Construction of 5,650 m Roads & Construction of 3,300 m
Drains. (As described in Sl. No. 26), |
|
|||||||||||||
16 |
Bid Publication Date |
11/01/2017 |
|
|
||||||||||||
|
|
Date |
Time |
|
|
|||||||||||
17 |
Bid Last
Selling Date andTime |
08/02/2017 |
5 : 00 PM |
|
||||||||||||
18 |
Bid Closing
Date and Time |
09/02/2017 |
2 : 00 PM |
|
||||||||||||
19 |
Name &
Address of the office(s) |
Name: |
Address: |
|
|
|||||||||||
|
Selling Bid Document (Principal) |
The Executive
Engineer, Patuakhali Pourashava,
District: Patuakhali. |
|
|
||||||||||||
Selling Bid Document (Others) |
01.Deputy Commissioner, District:
Patuakhali. 02.Superintendent of Police, District: Patuakhali. 03.Executive
Engineer, LGED / DPHE District: Patuakhali. |
|
|
|||||||||||||
Places of Receiving Bid Document |
The Executive Engineer, Patuakhali Pourashava, District: Patuakhali. |
|
|
|||||||||||||
Place of Opening Bid Document |
The Executive Engineer, Patuakhali Pourashava, District: Patuakhali. |
|
|
|||||||||||||
|
|
Date |
Time |
|
|
|||||||||||
20 |
Time of
Opening Bid |
09/02/2017 |
2 : 30 PM |
|
|
|||||||||||
|
|
Date and place |
Time |
|
|
|||||||||||
21 |
Pre-Bid Meeting |
17/01/2017, Patuakhali Pourashava |
11:00 am |
|
|
|||||||||||
|
INFORMATION FOR BIDDER |
|
|
|||||||||||||
22 |
Eligibility of Bidder |
No nationality
restrictions apply, other than any restrictions arising from Clause ITB 5.11. |
|
|
||||||||||||
23 |
Brief Description of
Works |
As stated in the SL no 26 |
|
|
||||||||||||
24 |
Brief
Description of Physical Services |
As stated in the SL no 26 |
|
|
||||||||||||
25 |
Price of Bid Document |
As stated in the SL no 26 |
|
|
||||||||||||
26 |
Sub-project
No |
Identity
of Scheme in PDP |
Identification
of Package |
Location |
Price
of Bid Document (Tk) |
Amount
of Bid Security (Tk) |
Completion
Time in Days |
|
||||||||
UGIIP-III-2
/ WB / PATU / UT+DR / 01 / 2016 |
Roads : (UT) |
Patuakhali Pourashava |
11,000.00 |
35,00,000.00 |
365 Days |
|
||||||||||
R-1 |
Construction of road from Town Zoinkati
Hazi Hamezuddin Mridha Collage morr East side (Nizam Councilor shop back side) to Arapol
mur (Via Al-Amin Nurani Hafizi Madrasha) by CC. (Ch.
0.00-1700.00)m. |
|
|
|
|
|
||||||||||
R-2 |
Construction of road from Town Zoinkati
Younus Member House front to Pal Bari road (via Mr.
Ahmed Ali Maridha Talukdar
|
|
||||||||||||||
R-3 |
Construction of road from Town Bohalgasia
Main BC road to East side Md. Aiub Ali house back
side South side Md. Akkas Gazi
house south side and Mannan Navy house south side
to east side pal bari road by CC. (Ch.
0.00-620.00)m. |
|
||||||||||||||
R-4 |
Construction of road from Town Bohalgasia
Main BC Road to East side Gogon Aliand
Latif Mia house by CC. (Ch. 0.00-370.00)m. |
|
||||||||||||||
R-5 |
Construction of road from Town Zoinkati
Main BC Road to (Via East Side Side Mira Bari) BWDB
road by CC. (Ch. 0.00-370.00)m. |
|
||||||||||||||
R-6 |
Construction of road from Town Bohalgasia
Main BC Road to West side Soraf Molla
Lalu Pal Bari and Nironzon
Master Bari by CC. (Ch. 0.00-200.00)m, (Ch. 0.00-220.00)m & (Ch.
0.00-160.00)m. |
|
||||||||||||||
R-7 |
Construction of
road from Town Bohalgasia Main B.C road to West
side (Via Barak Gazi) Md. Emdad
Hossain house and Gazi
Bari Main road to South Side (Via khal Par) Pal
Bari by CC. (Ch. 0.00-260.00)m. & (Ch. 0.00-400.00)m. |
|
||||||||||||||
Drains : (DR) |
|
|
|
|
|
|||||||||||
D-1 |
Construction of RCC Drain from Town Bohalgasia Main BC road to East side Md. Aiub Ali house back side South side Md. Akkas Gazi house south side and
Mannan Navy house south side to east side pal bari road (Ch. 0.00-620.00)m. |
|
|
|
|
|
||||||||||
D-2 |
Construction of RCC Drain from Part-A: Puran
Bazar Mosque to North side Near Puran Stolll Ghor Easte
side Up to River (Via Yousuf Khan Hotel) (Ch.
0.00-300.00)m. & Part-B: Bonik Potti Drain (Ch. 0.00-160.00)m. |
|
||||||||||||||
|
||||||||||||||||
|
|
|
|
|
||||||||||||
D-3 |
Construction of RCC Drain from Town School Eist
Side UP to River (Via kartik Master House) (Ch.
0.00-200.00)m. |
|||||||||||||||
D-4 |
Construction of RCC Drain from Puran
Bazar Dholu Bapari Ghat East side sham lal Roy
house to shonali Bank Front lhal
(Via Dr. Shiddhartto Shankar house bank side) (Ch.
0.00.220.00)m. & (Ch. 0.00-350.00)m. |
|||||||||||||||
D-5 |
Construction of RCC Drain from Shimulbag
RCC Road East side Bannu Bakary
(Via Noimul House) to Main Drain (Via Rob Sir house
to Main Drain Darain) (Ch. 0.00-1150.00)m. |
|||||||||||||||
D-6 |
Construction of RCC Drain from Center para
Kutti Sharker house khal North Side (Via Adalot
Para) to Post Office (Ch. 0.00-300.00)m. |
|||||||||||||||
|
PROCURING ENTITY DETAILS |
|
|
|||||||||||||
27 |
Bid Validity Period |
120 Days |
|
|||||||||||||
28 |
Name of Official Inviting Bid |
Md. Abdul Halim, Executive Engineer, Patuakhali
Pourashava. |
|
|||||||||||||
29 |
Designation of Official Inviting Bid |
The Executive
Engineer, Patuakhali Pourashava,
District: Patuakhali. |
|
|
||||||||||||
30 |
Address of Official Inviting Bid |
Patuakhali
Pourashava, District: Patuakhali. |
|
|
||||||||||||
31 |
Contact details of Official Inviting Bid |
Tel. No. |
Fax No. |
e-mail |
|
|||||||||||
|
|
0441-65101 |
0441 - 62012 |
enghalimxen@gmail.com |
|
|||||||||||
32 |
The Procuring Entity reserves the right to reject all the Bids or annul the Bid proceedings |
|
||||||||||||||
|
|
(Md. Abdul Halim)
Exicutive Engineer
Patuakhali Pourashava.
Memo
No. Patua. / Poura.
/ Engg / 2017/02 (21)
Date : - 08/01/2017
C.C.
1.
DG,
CPTU, IMED, He is requested to Publish
the Bid Notice in the CPTU website
2.
Superintending
Engineer, (Urban Management) RDEC Bhaban, LGED, Dhaka-1207
3.
Superintending
Engineer, LGED, Patuakhali Region / DPHE,
4.
The
Project Director, UGIIP-III, Level-12, LGED Bhavan, Agargaon, Sher-e-Bangla Nagar,
Dhaka-1207.
5.
The
Deputy Commissioner, District: Patuakhali.
6.
The
Mayor, Patuakhali Pourashava,
District : Patuakhali.
7.
The
Superintendent of police, District : Patuakhali.
8.
The
Executive Engineer, LGED/R&H/WDB/ DPHE, District :
Patuakhali.
9.
The
Team Leader, MDS Consultants, UGIIP-III, Level -12, LGED Bhavan,
Agargaon, Sher-e-Bangla
Nagar, Dhaka-1207.
10.Notice Board UGIIP-III, Level
-12, LGED Bhavan, Agargaon,
Sher-e-Bangla Nagar,
1207.
11. Notice board – (Patuakhali
Pourashava).
(Md. Abdul Halim)
Exicutive Engineer
Patuakhali Pourashava.