Memo No : 46.02.0400.000.07.001.17.1449 Date: 30.08.2017 | |||||||||
Corrigendum for Tender Notice No-04/2017-18 | |||||||||
This is to notify for all concern that the work completion time of Tender Notice No. 04/2016-17 invited vide Memo No : 46.02.0400.000.07.001.17.1429 Date:28-08-2017 has been corrected as follows. This notice will be treated as a part of the tender document. More information will be available at concern office. All other terms and conditions will remain unchanged. | |||||||||
Tender Package No | Tender Completion Time (Days) | ||||||||
LGED/ASSSRBP/Barguna/W-14 Dist: Barguna | Mentioned | Should be | |||||||
365 | 450 | ||||||||
Executive Engineer LGED, Barguna. |
|||||||||
Copy forwarded for favour of information & with circulation
to :- - The Aditional Chief Engineer, LGED, Barisal Division, Barisal. - The Superintending Engineer, LGED,Patuakhali Region, Patuakhali. - The Project Director ASSSRBP, LGED, H/Q, Dhaka. - The Upazila Engineer, LGED, Barguna Sadar, Dist. Barguna. - The Editor “The Daily Amar Sangbad, Dhaka, for Publication in 5"x4 col. Size for one day for one time on or before 01.09.2017 positively". - The Editor “The Daily Financial Express, for Publication in 5"x4 col. Size for one day for one time on or before 01.09.2017 positively". |
|||||||||