Tender Notice No.-21/2011-12
The Government of the People’s Republic of
Bangladesh has received an ODA loan ( BD-P64
dated 24th March 2010 ) from JAPAN INTERNATIONAL CO-OPERATION AGENCY (
hereinafter referred to as JICA ), in the amount of Yen towards the cost of
South-Western Bangladesh Rural Development Project, and intends to apply “a
portion of” the loan to payments under the contracts for civil works ( the “Works” ).
Sealed Tenders
are hereby invited from the eligible tenderers as defined in the tender
document for the under mentioned works as per terms and conditions stated
below.
Package No. |
Name of Works |
Tender Security (Tk) |
Time for Completion (days) |
Price of tender documents (Tk) |
SWBRDP/ BRG/BARI-43 |
Part-1: Construction of 20.00m RCC Girder
Bridge at chainage 2654m, on Chowmohona GC-Banaripara H/Q via Biserkandi
Umarerper Batiaghata Wazedia, Baisari road under Banaripara Upazila, Dist:
Barisal (ID No.506102001) (Structural Works for Bridge). Part-2: Construction of 20.00m RCC Girder
Bridge at chainage 2654m on the same road (protection works of approch road). Part-3: Construction of 20.00m RCC Girder
Bridge at chainage 2654m on the same road (works of approch road). Part-4: Construction of 22.00m RCC Girder
Bridge at chainage 3780 m on the same road (Structural Works for Bridge). Part-5: Construction of 22.00m RCC Girder
Bridge at chainage 3780m on the same road (protection works of approch road). Part-6: Construction of 22.00m RCC Girder
Bridge at chainage 3780m on the same road (works of approch road). |
600000.00 |
365 days |
4000.00 |
SWBRDP/ BRG/BARI-44 |
Part-1: Construction of 4.00mx4.00m RCC Box
Culvert at chainage 4020m, on Chowmohona GC-Banaripara H/Q via Biserkandi
Umarerper Batiaghata Wazedia, Baisari road under Banaripara Upazila, Dist:
Barisal (ID No.506102001)(Structural Works for Bridge). Part-2: Construction of 2.00mx2.00m RCC Box
Culvert at chainage 4103m on the same road (protection works of approch
road). Part-3: Construction of 4.00mx4.00m RCC Box
Culvert at chainage 4290m on the same road (works of approch road). Part-4: Construction of 3.00mx3.00m RCC Box
Culvert at chainage 4780 m on the same road ) (Structural Works for Bridge). Part-5: Construction of 3.00mx3.00m RCC Box
Culvert at chainage 5006 m on the same road ) (Structural Works for Bridge). |
300000.00 |
365 days |
2000.00 |
|
Part-6: Construction of 2.00mx2.00m RCC Box
Culvert at chainage 5150 m on the same road ) (Structural Works for Bridge). Part-7: Construction of 2.00mx2.00m RCC Box
Culvert at chainage 5410 m on the same road ) (Structural Works for Bridge). Part-8: Construction of 3.00mx3.00m RCC Box
Culvert at chainage 5665 m on the same road ) (Structural Works for Bridge). |
|
|
|
SWBRDP/ BRG/BARI/45 |
Part-1: Construction of 20.00m RCC Girder Bridge at chainage 4526 m
on Chowmohona GC-Banaripara H/Q via Biserkandi Umarerper Batiaghata Wazedia,
Baisari road under Banaripara Upazila, Dist: Barisal (ID No.506102001)
(Structural Works for Bridge) Part-2: Construction of 20.00m RCC Girder
Bridge at chainage 4526m on the same road (protection works of approch road). Part-3: Construction of
20.00m RCC Girder Bridge at chainage4526m on the same road (works of approch
road). Part-4: Construction of
15.00m RCC Girder Bridge at chainage 5327m on the same road (Structural Works
for Bridge) Part-5: Construction of
15.00m RCC Girder Bridge at chainage 5327m on the same road (protection works
of approch road). Part-6: Construction of
15.00m RCC Girder Bridge at chainage 5327m on the same road (works of approch
road). |
550000.00 |
365 days |
4000.00 |
SWBRDP/ BRG/BARI/46 |
Part-1: Construction of 20.00m RCC Girder Bridge at chainage 5511m
on Chowmohona GC-Banaripara H/Q via Biserkandi Umarerper Batiaghata Wazedia,
Baisari road under Banaripara Upazila, Dist: Barisal (ID No.506102001)
(Structural Works for Bridge) Part-2: Construction of 20.00m RCC Girder
Bridge at chainage 5511m on the same road (protection works of approch road). Part-3: Construction of
20.00m RCC Girder Bridge at chainage5511m on the same road (works of approch
road) Part-4: Construction of 15.00m RCC Girder
Bridge at chainage 5790m on the same road. (Structural Works for
Bridge) Part-5: Construction of 15.00m RCC Girder
Bridge at chainage 5790m on the same road (protection works of approch road). Part-6: Construction of
15.00m RCC Girder Bridge at chainage5790m on the same road (works of approch
road) Part-7: Construction of 15.00m RCC Girder
Bridge at chainage 5900m on the same road. (Structural Works for
Bridge) Part-8: Construction of 15.00m RCC Girder
Bridge at chainage 5900m on the same road (protection works of approch road). Part-9: Construction of
15.00m RCC Girder Bridge at chainage5900m on the same road (works of approch
road) |
700000.00 |
365 days |
4000.00 |
SWBRDP/ BRG/BARI/47 |
Part-1: Construction of 16.00m RCC Girder
Bridge at chainage 6134m, on Chowmohona GC-Banaripara H/Q via Biserkandi
Umarerper Batiaghata Wazedia, Baisari road under Banaripara Upazila, Dist:
Barisal (ID No.506102001) (Structural Works for Bridge). |
850000.00 |
365 days |
5000.00 |
|
Part-2: Construction of 16.00m RCC Girder
Bridge at chainage 6134m on the same road (protection works of approch road). Part-3: Construction of 16.00m RCC Girder
Bridge at chainage 6134m on the same road (works of approch road). Part-4: Construction of 2 nos 3.00mx3.00m RCC Box Culvert at chainage 6400m &6489m on the same
road Part-5: Construction of 45.00m RCC Girder
Bridge at chainage 6780m on the same road (protection works of approch road). Part-6: Construction of 45.00m RCC Girder
Bridge at chainage6780m on the same road (works of approch road). Part-7: Construction of 45.00m RCC Girder
Bridge at chainage6780m on the same road (Structural Works for Bridge). |
|
|
|
1.
Source of Funds
: South-western Bangladesh Rural development Project
(Development
Budget
Aid-credit)
2. Date,time and place of : Date: January 29, 2012, Time :11.00
AM.
pre-tendering meeting Office of the Executive Engineer ,
LGED, Barisal.
3. Last date, time and places :
February 07, 2012, Time : 5.00 pm and
of selling tender
documents Places :
a) Office of the Executive Engineer , LGED, District: Barisal..
b) Office of the Project Director,SWBRDP,LGED Bhaban,
Agargoan, Sher-e Bangla Nagar , Dhaka –1207.
c) Office of the Deputy Commissioner, District: Barisal.
d) Office of the Superintendent of police,
District: Barisal.
e) Office of the Executive Engineer,LGED,District: Jhalakati
f) Office of the Deputy Project
Director, SWBRDP,
LGED Bhaban, District: Barisal. .
g) Office of the Upazila Engineer,LGED,Upazila: Banaripara,
District: Barisal.
4. Last date, time and Places : February 08,
2012, Time : 1.00 pm and
of receiving
tender Places :a)
Office of the Executive Engineer , LGED, District: Barisal..
b) Office of the Deputy Commissioner, District: Barisal.
c) Office of the Executive Engineer,LGED,District: Jhalakati
d) Office of the Upazila Engineer, LGED,
Upazila: Banaripara,
District:
Barisal
5.
Date, time and place of :
February 08, 2012, Time : 3.00 pm and
Opening of tender Place: Office of the Executive Engineer , LGED,
District: Barisal..
6. Tender Shall be valid for a
period of 120 days after bid opening and
must be accompanied by the tender
security specified above. Interested tenderer may obtain further information
from the undersigned and purchase the tender documents in cash/treasury
chalan/bank draft from the places mentioned above. The tenderer or their
authorized representatives are allowed to attend the opening of tenders. The
authority reserves the right to accept or reject any or all the tenders without
assigning any reasons whatsoever.
This
invitation for tender is available on the website www.lged.gov.bd
and www.cptu.gov.bd & in the The Financial Express & The Bangla Bazar
newspapers.
(Kazi Mizanur Rahman)
Executive Engineer
LGED, Barisal.
Ph: 0431-71054
Memo
No. LGED/XEN/Bari/2011/01/1(30) Dated : 01/01/2012
CC
for information and necessary action
1. The Chief
Engineer,LGED,LGED Bhaban,Agarhaon,Dhaka-1207.
2. The Director
General, CPTU, IMED, Block-12, 2nd Floor, Sher-e-BanglaNagar,
Dhaka1207
3. The Superintending
Engineer(PM&E),LGED,LGED Bhaban,Agargaon,Dhaka.
4. The Superintending
Engineer,LGED,Barisal Region,Barisal
5. The Project Director,
LGED,SWBRDP, LGED Bhaban, Level-10, Agorgoan, Dhaka-1207.
6. The Team Leader,
SWBRDP, LGED Bhaban,,Agorgoan, Dhaka.
7.The
Deputy Project Director, LGED, SWBRDP, LGED Bhaban,Barisal.
8. The Upazila
Engineer,Upazila-Banaripara,Barisal
9. Notice Board (All)
CC For information
1. The Deputy Commissioner, Barisal.
2.
The Superintendent of Police, Barisal
3.
The Senior Assistant Secretary,Ministry of Information.
(Kazi Mizanur Rahman)
Executive Engineer
LGED, Barisal.