Government
of the People’s Republic of Bangladesh
Local
Government Engineering Department
Office of the
Executive Engineer District: Narail
Memo No:LGED/XEN/NAR/Pro-270
/2012/118 Date:16-01-2013
Invitation
for Bids (IFB) No-10/2012-13.
Deadline for Bids : 10 February
2013 up to 12.00 hours (Closing Date & Time).
1. The
2. The Local Government Engineering Department ("the
Employer") invites
sealed bids from eligible bidders
FOR THE construction and completion of Package No. & NAME:
(I) Package No. LGED/SWAIWRPMP/Nar/01/2012-13:
Construction of Simakhali R&H – Naldi Ferrighat road with Bituminous Carpeting from Km. 2.800 to Km. 4.650
& Km 7.150 to Km 8.150 = 2.85 Km. under LGED, Narail (SWAIWRPMP BWDB)
during the year 2012-13.
(II) Package No. LGED/SWAIWRPMP/Nar/02/2012-13:
Construction of Jaddoppur -
Perulistan road with Bituminous
Carpeting from Km. 4.620 to Km. 7.350 =2.73 Km. under LGED, Narail (SWAIWRPMP
BWDB) during the year 2012-13.
3. Only eligible bidders with the
following key qualifications should participate in this bidding:
a.
Specific construction Experience:
(I) Package No. LGED/SWAIWRPMP/NAR/01/2012-13:
Bidder must have the Experience of at least 1 (One)
Construction contract of BDT Tk. 182.00 Lakh. or more in Construction of
Bituminous Carpeting road during the last 5 (five) years. Single entity or all
joint venture (JV) Partners together (With the Experience of each Partner
multiplied by the JV share) must meet the requirement while one (Lead) partner
must meet minimum 40% of the requirement.
(II) Package No. LGED/SWAIWRPMP/NAR/02/2012-13:
Bidder must have the Experience of at least 1 (One)
Construction contract of BDT Tk. 180.00 Lakh. or more in Construction of Bituminous Carpeting road during
the last 5 (five) years. Single entity or all joint venture (JV) Partners
together (With the Experience of each Partner multiplied by the JV share) must
meet the requirement while one (Lead) partner must meet minimum 40% of the
requirement.
b. Average annual construction turnover:
(I) Package No. LGED/SWAIWRPMP/NAR/01/2012-13:
Minimum Average Annual Construction Turnover of BDT Tk. 364.00
Lakh (Based on Total Certified Payments Received for contracts in progress
or Completed) over the last 5 (five) years. Single entity or all joint venture (JV) partners together
(With the experience of each partner multiplied by the JV share) must meet the
requirement while one (Lead) partner must meet minimum 40% of the requirement
and the other partners need to meet 25% individually.
(V) Package No. LGED/SWAIWRPMP/NAR/02/2012-13:
Minimum Average Annual Construction Turnover of BDT Tk. 360.00
Lakh (Based on Total Certified Payments Received for contracts in progress
or Completed) over the last 5 (five) years. Single entity or all joint venture (JV) partners together
(With the experience of each partner multiplied by the JV share) must meet the
requirement while one (Lead) partner must meet minimum 40% of the requirement
and the other partners need to meet 25% individually.
c. Financial RESOURCES:
(I) Package No. LGED/SWAIWRPMP/NAR/01/2012-13:
Financial resources requirement is minimum BDT Tk. 91.00 Lakh. Single entity or all joint venture (JV) partners together
(With the experience of each partner multiplied by the JV share) must meet the
requirement while one (Lead) partner must meet minimum 40% of the requirement.
(II) Package No. LGED/SWAIWRPMP/NAR/02/2012-13:
Financial resources requirement is minimum BDT Tk. 90.00 Lakh. Single entity or all joint venture (JV) partners together
(With the experience of each partner multiplied by the JV share) must meet the
requirement while one (Lead) partner must meet minimum 40% of the requirement.
4. Local competitive
bidding (LCB) will be conducted in accordance with ADB's single stage, one
envelope procedure and is open to all bidders from eligible source countries.
5. To obtain
further information and inspect the bidding documents, bidders should contact:
(a) Office of the Executive Engineer, Narail Office, LGED.
Telephone: 0481-62331,
Email:
xen.narail@lged.gov.bd
6. A complete set of
bidding documents in English Language may be purchased by any interested eligible party from the 1. Office of the
Executive Engineer, LGED, Narail 2. Office of the Executive Engineer, LGED,
Khulna 3. Office of the Superintending of Police, District : Narail. 4. Office
of the Deputy Commissioner, Narail 5. Office
of the Executive Engineer, BWDB, Narail 6. Office of the Upazila Engineer,
LGED, Sadar & Kalia upon the payment of
(I) Tk. 3000.00 (Taka Three Thousand)
only for Package No. LGED/SWAIWRPMP/NAR/01/2012-13
(II) Tk. 3000.00 (Taka Three
Thousand) only for Package No. LGED/SWAIWRPMP/NAR/02/2012-13
(Non-Refundable) in the form of Bank
Draft or Pay Order (issued by a local
bank) in favor of Executive Engineer, LGED, Narail during office hours
on working days up to 10 February 2013.
7. Completion
Time:
(I) Package No. LGED/SWAIWRPMP/NAR/01/2012-13 : 180 days from the date of signing
contract.
(II) Package No. LGED/SWAIWRPMP/NAR/02/2012-13 : 180 days from the date of signing
contract.
8. BID
SECURITY:
(I) Package No. LGED/SWAIWRPMP/NAR/01/2012-13:
Must be accompanied by a
Bid Security of Tk. 325000.00 (Taka Three Lac Twenty five Thousand) only in the form of a Payment Order (issued
by a local bank of Faridpur Town) or Bank Draft from any Schedule Bank of
Bangladesh in favor of Executive Engineer, LGED,Narail.
(II) Package No. LGED/SWAIWRPMP/NAR/02/2012-13:
Must be accompanied by a
Bid Security of Tk. 320000.00 (Taka Three Lac Twenty Thousand) only in the form of a Payment Order (issued
by a local bank of Faridpur Town) or Bank Draft from any Schedule Bank of
Bangladesh in favor of Executive Engineer, LGED, Narail.
9. Bids must be submitted in accordance with the
Instructions to Bidders (ITB) included in the Bidding Documents to the
(1) Office of
the Executive Engineer, LGED, Narail
(2) Office of the Deputy Commissioner,
Narail
(3) Office of the Superintending of Police, District : Narail
(4) Office of the Executive Engineer, BWDB, Narail up to 11
February, 2013 on or before 12hrs (noon)
10. Bidders shall
submit their bids only in person which must reach the above offices before
deadline for submission of Bids as Indicated in Paragraph 9 above. Bids
received after the deadline will not be accepted. LGED will not be responsible
for any cost or expenses incurred by Bidders in connection with the preparation
or submission of Bids.
11. Bids will be opened at 14:00 hrs on 11 February 2013 at the office of the undersigned in the
presence of bidders' Representatives who choose to
attend.
12. Acceptance of a bid
will rest with the competent authority who is not bound to accept the lowest or
any of the bids without assigning any reason.
NB: This IFB will also be available on the website www.lged.gov.bd & www.cptu.gov.bd
(Nirmal Kumar Biswas) Executive
Engineer, LGED,
Narail.
Memo
No:LGED/XEN/NAR/Pro-270 /2012/ Date16-01-2013
Copy
forwarded for kind information/information and necessary action to:
01. The Chief Engineer, LGED, Agargaon , Dhaka
02. The Additional Director General, O & M-2, BWDB, Dhaka.
03. The Chief Engineer, South Western Zone, BWDB, Khulna.
04. Superintending
Engineer, Khulna Region, Khulna.
05. The Chief Monitoring, BWDB, Dhaka.
06. The Director, Planning-II & Project Coordinator, SWAIWRPMP, BWDB,
Dhaka.
07. The Project Director, Project Management Office, SWAIWRPMP, BWDB,
Jessore.
08. The Director, Contract & Procurement Cell, BWDB, Dhaka.
09. The Deputy Commissioner, Narail.
10. The Superintendent of Police, Narail.
11. The Executive Engineer, Chenchuri Beel Sub-Project, BWDB, Narail..
12. The System Analyst, Chief Monitoring
Office, WAPDA Building, Dhaka.
13. The Team Leader, ISPM Consultants,
SWAIWRPMP, Jessore.
14. The Deputy Director, Regional
Accounting Center (RAC), BWDB, Faridpur.
15. P.A to ADG
(O&M-2), BWDB, Dhaka.
16. M/S.
.................................................................................................................................
17. Notice Boards,
Master/Office copy.
Executive
Engineer, LGED,Narail