Government of the
People’s Republic of
Local Government Engineering Department
Office
of the Executive Engineer
District:
Lalmonirhat
Memo.no.LGED/XEN/LAL/2014/11 Dated
:
Sealed tenders are hereby
invited from the updated enlisted contractor of LGED Rangpur region
(Lalmonirhat, Rangpur, Gaibandha &
Kurigram District) for the under mentioned works as per terms and conditions
stated below :
Package
SL. No. |
Name of Works |
Estimated cost (Tk.) |
Tender security (Tk.) |
Time for completion (days) |
Price of tender documents (Tk.) |
XEN/LAL/13-14/FG/W-1 |
Renovation/Repair of Durakuti food godown under
Sadar Upazila, Dist. Lalmonirhat. |
421175.00 |
10000.00 |
60 |
300.00 |
XEN/LAL/13-14/FG/W-2 |
Repair of Mohendranagar food godown under Sadar
Upazila, Dist. Lalmonirhat. |
385411.00 |
9500.00 |
60 |
300.00 |
1. |
Procurement Method |
: |
Limited Tendering Method |
2. |
Source of Funds |
: |
GOB fund |
3. |
Date, time and place of pre-tender meeting |
: |
|
4. |
Last date, time and places of selling
tender documents |
: |
a)
Office of the
Project Director, Construction of Rubbar Dams in small & medium river for
increasing of food production Project, LGED, RDEC Bhaban, Dhaka. b) Office of the Deputy Commissioner,
Lalmonirhat c) Office of the Superintendent of
Police, Lalmonirhat. d) Office of the Executive Engineer,
LGED, Lalmonirhat e) Office of the Upazila Engineer,
LGED, Upazila: Sadar,
Lalmonirhat. |
5. |
Last date, time and places of receiving tender |
: |
a) Office of the Deputy Commissioner,
Lalmonirhat b) Office of the Superintendent of
Police, Lalmonirhat. c) Office of the Executive Engineer,
LGED, Lalmonirhat d) Office of the Upazila Engineer,
LGED,Upazila: Sadar,
Lalmonirhat. |
6. |
Date, time and place of opening of tender |
: |
|
7. |
Tender shall be valid
for a period of 120 days after bid opening and must be accompanied by
the tender security specified above. Interested tenderer may obtain further
information from the office of the undersigned and purchase the tender
documents in cash/treasury chalan/ bank draft from the places mentioned
above. The schedule amounting beyond 5% than the estimated cost shall
rejected as per amendment of PPA'2006 published in Bangladesh Gazette, July
18' 2010. (Reference amendment of Section 19 of Act 24, 2006). The tenderer
or their authorized representatives are allowed to attend the opening of
tenders. The authority reserves the right to accept or reject any or all the
tenders without assigning any reason whatsoever. This invitation for tender
is available on the website www.lged.gov.bd |
|
(Md. Khalilur
Rahman) Executive
Engineer Ph.
0591-61393 |
Memo.no.LGED/XEN/LAL/2014/11(100) Dated
:
Copy forwarded for kind information
and necessary action :
1.
The
Chief Engineer, LGED, LGED Bhaban, Agargaon, Sher-e-Bangla Nagar, Dhaka-1207.
2.
The
Superintending Engineer, Rangpur Region, LGED, Dhap, Jail road, Rangpur.
3.
The
Project Director, Construction of Rubbar Dams in small & medium river for
increasing of food production Project, LGED, RDEC
Bhaban, Agargaon, Sher-e-Bangla Nagar,
Dhaka-1207.
4.
The
Deputy Commissioner, Lalmonirhat.
5.
The
Superintendent of Police, Lalmonirhat.
6.
The
Executive Engineer, BWDB/R&H/PWD, Lalmonirhat.
7.
The
Executive Engineer, LGED, GIS Unit, Level-4,
8.
The
Upazila Engineer, LGED, Sadar/Aditmari/Kaligonj/Hatibandha/Patgram Upazila,
Lalmonirhat.
9.
Mr./
M/S_________________________________________________________________________
|
(Md. Khalilur
Rahman) Executive
Engineer Ph.
0591-61393 |
Memo No.LGED/XEN/LAL/2014/ Date:
Copy forwarded
for kind information :
1.
The
Upazila Chairman, Sadar Upazila Parishad, Lalmonirhat.
2.
The
Upazila Nirbahi Officer, Sadar Upazila,
Lalmonirhat.
|
(Md. Khalilur
Rahman) Executive
Engineer Ph.
0591-61393 |