1
|
CIB-Mad-W-32
|
"Construction of 670.85m Long PSC &RCC Girder Bridge Over Arial Kha River on Boheratola UP ( Dakhin) Office to Dhurial Bazar Road Via Kala Tola Hat Road At Ch .4200m Under Shibchar Upazila District: Madaripur
[Road ID: 354873033] CIB-Mad-W-32 "
|
CIBRR
|
shibchar
|
354873033
|
|
670.85
|
10
|
9840.00
|
M/S Hamim International.
|
9840.00
|
19/09/2023
|
01/10/2023
|
30/09/2026
|
17
|
1000.00
|
10
|
04/09/2024
|
|
2
|
CRMIDP/MDR/W-315
|
Uttor Romjanpur Notun Hat
|
CRMIDP
|
kalkini
|
|
|
|
90
|
354.00
|
"M/S Nahid Enterprise Magura, Bakai, Gouranadi, Barisal "
|
265.10
|
26/06/2022
|
|
16/06/2021
|
95
|
238.62
|
90
|
27/07/2022
|
|
3
|
CRMIDP/MDR/W-314
|
Chilerchar Hat
|
CRMIDP
|
madaripur-s
|
|
|
|
86
|
306.00
|
M/S Mizan Enterprice, Bottala, New Town, Sadar, Madaripur.
|
245.39
|
02/02/2020
|
|
04/07/2022
|
95
|
211.68
|
86
|
27/07/2022
|
|
4
|
CRMIDP/MDR/W-316
|
Amgram Bazar
|
CRMIDP
|
rajoir
|
|
|
|
56
|
196.00
|
MEK-MAS (JVCA), Sadar, Madaripur
|
162.92
|
13/10/2019
|
|
27/06/2022
|
80
|
91.09
|
56
|
27/07/2022
|
|
5
|
GSIDP/MDR/DW-12
|
Improvement of Kerani Batt Grave Yard, Union: Shibchar Pourashava. [Latitude:23.211759, Longitude: 90.099828.]
|
GSIDP
|
shibchar
|
|
|
|
100
|
7.00
|
M/S. Shankar Chandra Ghosh
|
0.00
|
|
|
|
100
|
|
100
|
25/03/2019
|
|
6
|
GSIDP/MDR/DW-15
|
Improvement of Thengamara Sikder Kandi Grave Yard, Union: Shibchar Pourashava. [Latitude:23.213681, Longitude: 90.099918.]
|
GSIDP
|
shibchar
|
|
|
|
100
|
5.29
|
M/S. Shankar Chandra Ghosh
|
0.00
|
|
|
|
100
|
|
100
|
25/03/2019
|
|
7
|
GSIDP/MDR/DW-21
|
Improvement of 7 no Odhikary bari Sri Sri Radha Krishno Mondir, Union: Shibchar Pourasava.[Latitude:23.3791, Longitude: 90.165]
|
GSIDP
|
shibchar
|
|
|
|
100
|
10.00
|
M/S. Keya Enterpise
|
0.00
|
|
|
|
100
|
|
100
|
25/03/2019
|
|
8
|
GSIDP/MDR/DW-23
|
Improvement of Krokchar New Bazer Jame-E-Mosque, Union: Vandarikandi.[Latitude: 23.2947, Longitude: 90.2227]
|
GSIDP
|
shibchar
|
|
|
|
100
|
19.00
|
M/S Pavel Enterprise
|
0.00
|
|
|
|
100
|
|
100
|
25/03/2019
|
|
9
|
GSIDP/MDR/DW-24
|
Improvement of Delower Bepari hat Jame-E-Mosque, Union: kadirpur.[Latitude:23.3772, Longitude: 90.2336]
|
GSIDP
|
shibchar
|
|
|
|
100
|
9.99
|
M/S. Mujib Enterprise,
|
0.00
|
|
|
|
100
|
|
100
|
25/03/2019
|
|
10
|
IRIDP-2/MDR/DW-11
|
Improvement of UZR-10, Jogdahermath GPS -VRA-16, Kumerpar GPS road via house of Naru Ghoshal.at Ch.00-1880m.
|
IRIDP-2
|
shibchar
|
354875144
|
1.88
|
|
|
70.64
|
M/S Isan Enterprise
|
74.02
|
31/07/2016
|
|
|
100
|
|
|
21/03/2019
|
|
11
|
IRIDP-2/MDR/DW-12
|
Improvement of UZR-5, Malerkandi - Komu Baburchir Mor road via Shop of Motahar.at ch.00-900m.
|
IRIDP-2
|
shibchar
|
354875148
|
0.90
|
|
|
29.17
|
M/S Alomgir Enterprise
|
30.59
|
22/02/2016
|
|
|
100
|
|
|
21/03/2019
|
|
12
|
IRIDP-2/MDR/DW-13
|
Improvement of Baher Char house of Nannu Molla - Balakandi Chander Bazar road. at Ch.00-550m.
|
IRIDP-2
|
shibchar
|
354875166
|
0.55
|
|
|
21.99
|
M/S Howlader Enterprise
|
23.06
|
31/07/2016
|
|
|
100
|
|
|
21/03/2019
|
|
13
|
IRIDP-2/MDR/DW-14
|
Improvement of UNR-24, House of Saha Alam Chowdhury - Choto Kutubpur Hat road via Poddarerchar Govt. Primary School.Ch.00-1150m.
|
IRIDP-2
|
shibchar
|
354875256
|
1.15
|
|
|
41.81
|
M/S Howlader & co
|
43.85
|
31/07/2016
|
|
|
100
|
|
|
21/03/2019
|
|
14
|
IRIDP-2/MDR/DW-15
|
Improvement of Shahid Hosain High School - Majhee Kandi house of Yusuf Shikder road.at Ch.00-380m
|
IRIDP-2
|
shibchar
|
354875158
|
0.38
|
|
|
13.32
|
M/S. Abu Jehat Traders
|
13.96
|
31/07/2016
|
|
|
100
|
|
|
21/03/2019
|
|
15
|
MGSP/MAD/W-01
|
a) Construction of RCC Road at Shahid Bachu Sarak Starting from Kazir More to Howlader Godi. (Ch. 1230.00-1572.00m) (Total Length: 342m)
b) Construction of Drain (Both side) at Shahid Bachu Sarak Starting from Kazir More to Howlader Godi. (Ch. 1230.00-1572.00m) (Total Length: 684m)
c) Construction of RCC Road at Uttoron Club Road (Ch.000-90.00m) (Total Length: 90m)
d) Construction of Drain at Uttoron Club Road (Both side) (Ch.000-90.00m) (Total Length: 180m)
e) Construction of RCC road at Amin Uddin Howlader Sarak. (Ch. 0.00-430.00) (Total Length: 430m)
f) Construction of Drain at Amin Uddin Howlader Sarak. (Ch. 0.00-430.00) (Total Length: 430m)
g) Construction of RCC Road at Sardar Colony Hamid Sikder Sarak Starting from Hamid Akond Sarak. to RHD main Road (Ch. 0.00-420.00m) (Total Length: 420m)
h) Construction of of Drain at Sardar Colony Hamid Sikder Sarak Starting from Hamid Akond Sarak. to RHD main Road (Ch. 0.00-420.00m) (Total Length: 253m)
|
MGSP
|
madaripur-s
|
|
3.00
|
|
|
28598735.00
|
Md. Kabir Hossain
|
25228851.00
|
|
05/02/2015
|
30/07/2016
|
100
|
|
|
|
|
16
|
MGSP/MAD/W-02
|
a) Construction of RCC Road at Shahid Harun Sarak Starting from Madaripur Main Road to Dorgha Sharif Road. (Ch. 0.00-365.00m) (Total Length: 365m)
b) Construction of RCC Road at Pakdi Peshker Bari road starting from Charmuguria Puraton road to Beri badh (Ch0.00m to 280.00m) (Total Length: 280m)
c) Construction of RCC Road at Bankers Colony starting from Madaripur Shariatpur road to Posu Hospital (Ch. 0.00-465.00m) (Total Length: 465m)
d) Construction of Drain at Bankers Colony starting from Madaripur Shariatpur road to Posu Hospital (Ch. 4.00-465.00m) (Total Length: 461m)
e) Construction of RCC Road at L. Faruk Sarak starting from RHD Road to End of Poura Area. (Ch. 0.00-270.00m) (Total Length: 270m)
f) Construction of RCC Road starting from Badamtola Hamid Akind Srak to U.I School (Ch. 0.00-270.00m) (Total Length: 270m)
g) Construction of Drain starting from Badamtola Hamid Akind Srak to U.I School (Ch. 0.00-270.00m) (Total Length: 270m)
h) Construction of RCC Road at the Nasim Nagar Charity Hospital road starting from Charmuguria Main road to Grave Yard road (Ch. 0.00-290.00m) (Total Length: 290m)
i) Construction of drain at the Nasim Nagar Charity Hospital road starting from Charmuguria Main road to Grave Yard road (Ch. 0.00-290.00m) (Total Length: 290m)
|
MGSP
|
madaripur-s
|
|
2.96
|
|
|
26222469.00
|
M/S Atahar EnterPrise
|
22799018.62
|
|
05/02/2015
|
17/04/2016
|
100
|
|
|
|
|
17
|
MGSP/MAD/2015-16/W-03
|
(a) Improvement of (BISIC road) Bachchu Sarak to main road (Ch.0+00 to 0+862m) by BC Pavement.
(b) Improvement of (BISIC road) Bachchu Sarak to main road by RCC Pavement (Ch.0+00 to 0+208m) by BC (bypus road)
(c ) Construction of RCC Drain start from Shahid Bachchu Sarak (BISIC road side drain) (R/S) with foothpath Ch. 0+000 to 0+867m under Madaripur Pourashava.
(d) Environmental work on road and drain at Bisic road starting from Bachchu Sarak to main road (Ch. 0+000m to 0+862m) under Madaripur Pourashava, Madaripur. Fixed cost-01
(e) Environmental work on road and drain at Bisic road starting from Bachchu Sarak to main road (Ch. 0+000m to 0+862m) under Madaripur Pourashava, Madaripur. Fixed cost-02
|
MGSP
|
madaripur-s
|
|
1.94
|
|
|
35397555.71
|
M.A.H. Construction Ltd.
|
27332964.56
|
|
06/11/2016
|
05/11/2017
|
41
|
|
|
|
|
18
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-1500
|
UTTOR SIKAR MONGOL
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
35.52
|
M/s Sweety Firm House
|
33.75
|
|
16/06/2018
|
19/04/2019
|
70
|
|
|
|
|
19
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-179
|
POSHCHIM ROMJAN PUR
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
73.16
|
M. M. Builders & Engineers Ltd.
|
65.85
|
|
06/06/2018
|
10/03/2019
|
47
|
|
|
|
|
20
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-180
|
PURBO MAIJ PARA NO.-2
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
69.66
|
M. M. Builders & Engineers Ltd.
|
62.69
|
|
06/06/2018
|
10/03/2019
|
60
|
|
|
|
|
21
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-181
|
PURBO CHAR AIR KANDI
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
78.40
|
M. M. Builders & Engineers Ltd.
|
70.56
|
|
06/06/2018
|
10/03/2019
|
65
|
|
|
|
|
22
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-182
|
UTTOR ROMJAN PUR M.E.
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
73.16
|
M. M. Builders & Engineers Ltd.
|
65.85
|
|
06/06/2018
|
10/03/2019
|
46
|
|
|
|
|
23
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-183
|
LUXMIPUR POKHIRA
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
70.29
|
M. M. Builders & Engineers Ltd.
|
63.26
|
|
06/06/2018
|
10/03/2019
|
70
|
|
|
|
|
24
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-184
|
CHAR LAXMI
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
67.05
|
M. M. Builders & Engineers Ltd.
|
60.35
|
|
06/06/2018
|
10/03/2019
|
70
|
|
|
|
|
25
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-306
|
MATHA BHANGA
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
73.31
|
Md Mahafuz Khan
|
65.98
|
|
06/06/2018
|
10/03/2019
|
60
|
|
|
|
|
26
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-41
|
SONMANDI GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
38.54
|
M/S. Shahid Brothers
|
34.68
|
|
31/05/2018
|
05/03/2019
|
95
|
|
|
|
|
27
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-444
|
DOKKHIN JONAR DONDY
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
72.35
|
M. M. Builders & Engineers Ltd.
|
65.12
|
|
06/06/2018
|
10/03/2019
|
0
|
|
|
|
|
28
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-445
|
DOKKHIN SHAHEB RAMPUR
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
73.51
|
M. M. Builders & Engineers Ltd.
|
66.16
|
|
06/06/2018
|
10/03/2019
|
75
|
|
|
|
|
29
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-82
|
KROKIR CHAR GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
32.52
|
M/S. Shahid Brothers
|
29.26
|
|
31/05/2018
|
05/03/2019
|
95
|
|
|
|
|
30
|
e-Tender/NBIDGPS/MAD/KAL/2017-2018/W1-864
|
CHAR PALORDI GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
kalkini
|
|
|
|
|
71.97
|
Nusrat Jahan Traders
|
68.37
|
|
03/06/2018
|
07/03/2019
|
0
|
|
|
|
|
31
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-1047
|
PURBO DUD KHALI GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
36.80
|
M/S Sadia Enterprise
|
34.96
|
|
28/05/2018
|
10/03/2019
|
80
|
|
|
|
|
32
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-1048
|
SIR KHARA BOLLOVDI
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
31.06
|
Jahid Enterprise
|
29.51
|
|
27/11/2018
|
20/03/2019
|
75
|
|
|
|
|
33
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-1230
|
KALAI MARA NEW BOYS
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
50.82
|
katha Enterprise
|
48.28
|
|
25/07/2018
|
31/05/2019
|
30
|
|
|
|
|
34
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-1255
|
LEBU TOLI BAJIT PUR
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
30.76
|
Hawlader Enterprise
|
29.23
|
|
25/07/2018
|
31/05/2019
|
60
|
|
|
|
|
35
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-1501
|
CHAR MOHISHER CHAR GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
77.29
|
Meem Febriks
|
73.42
|
|
25/07/2018
|
31/05/2019
|
0
|
|
|
|
|
36
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-1502
|
ADAM PUR BORAIL BARI GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
77.69
|
Tamim Enterprise
|
73.81
|
|
25/07/2018
|
31/05/2019
|
20
|
|
|
|
|
37
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-300
|
RAJDHORDI
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
57.33
|
Kohinoor enterprise
|
51.59
|
|
11/03/2018
|
31/12/2018
|
70
|
|
|
|
|
38
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-301
|
CHAR GOBINDO PUR BOARD GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
53.95
|
Kohinoor enterprise
|
48.56
|
|
19/03/2018
|
31/12/2018
|
45
|
|
|
|
|
39
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-302
|
CHHOINA
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
69.28
|
Kohinoor enterprise
|
61.39
|
|
19/03/2018
|
31/12/2018
|
0
|
|
|
|
|
40
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-303
|
CHAR DHURAIL
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
72.85
|
Kohinoor enterprise
|
64.72
|
|
19/03/2018
|
31/12/2018
|
65
|
|
|
|
|
41
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-332
|
NEARST POURO OFFICE MODEL GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
82.51
|
Kohinoor enterprise
|
74.26
|
|
19/03/2018
|
31/12/2018
|
35
|
|
|
|
|
42
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-39
|
AOZ
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
57.52
|
Kohinoor enterprise
|
51.77
|
|
11/03/2018
|
31/12/2018
|
70
|
|
|
|
|
43
|
e-Tender/NBIDGPS/MAD/MAD/2017-2018/W1-40
|
PURBO HOSNA BAD
|
NBIDGPS-1
|
madaripur-s
|
|
|
|
|
38.54
|
Kohinoor enterprise
|
34.68
|
|
05/04/2018
|
10/01/2019
|
10
|
|
|
|
|
44
|
e-Tender/NBIDGPS/MAD/RAJ/2017-2018/W1-00038
|
KOBI RAJ PUR
|
NBIDGPS-1
|
rajoir
|
|
|
|
|
45.52
|
M/S Sheikh Mithu Enterprise
|
43.24
|
|
31/07/2018
|
06/05/2019
|
80
|
|
|
|
|
45
|
e-Tender/NBIDGPS/MAD/RAJ/2017-2018/W1-00191
|
SAT PAR GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
rajoir
|
|
|
|
|
73.38
|
M/S Shahid & Brother
|
66.05
|
|
05/06/2018
|
07/03/2019
|
60
|
|
|
|
|
46
|
e-Tender/NBIDGPS/MAD/RAJ/2017-2018/W1-00192
|
ROTH BARI
|
NBIDGPS-1
|
rajoir
|
|
|
|
|
71.96
|
M/S Shahid & Brother
|
64.77
|
|
29/05/2018
|
28/02/2019
|
85
|
|
|
|
|
47
|
e-Tender/NBIDGPS/MAD/RAJ/2017-2018/W1-00193
|
RAJONDI DARADIA GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
rajoir
|
|
|
|
|
70.31
|
M/S Shahid & Brother
|
63.28
|
|
05/06/2018
|
07/03/2019
|
50
|
|
|
|
|
48
|
e-Tender/NBIDGPS/MAD/RAJ/2017-2018/W1-00322
|
CHOWARI BARI BHENNA BARI GOVT. PRIMARY SCHOOL
|
NBIDGPS-1
|
rajoir
|
|
|
|
|
73.07
|
M/S Shahid & Brother
|
65.77
|
|
05/06/2018
|
10/03/2019
|
40
|
|
|
|
|
49
|
e-Tender/NBIDGPS/MAD/RAJ/2017-2018/W1-00738
|
ULLABARI GOVT PRIMARY SCHOOL
|
NBIDGPS-1
|
rajoir
|
|
|
|
|
69.86
|
Md.Abdul bari Mia
|
66.37
|
|
01/08/2018
|
07/05/2019
|
40
|
|
|
|
|
50
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-1049
|
MADBAR KANDI
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
31.06
|
M/S Mridha Enterprise
|
32.59
|
|
12/06/2018
|
02/02/2019
|
90
|
|
|
|
|
51
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-1231
|
RAJARCHAR BONDOR KHOLA GPS
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
34.54
|
Green Construction
|
36.25
|
|
30/09/2018
|
30/06/2019
|
45
|
|
|
|
|
52
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-1503
|
PURBO KHASH BONDOR KHOLA
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
24.62
|
M/S Pavel Enterprise
|
25.84
|
|
16/08/2018
|
15/05/2019
|
25
|
|
|
|
|
53
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-199
|
CHAR BACHAMARA
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
68.07
|
M/S Hasina Akter
|
71.46
|
|
29/08/2018
|
29/05/2019
|
90
|
|
|
|
|
54
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-304
|
BORO DOWALI KHOLIFA KANDI GPS
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
66.93
|
M/S Kakoli Traders
|
70.23
|
|
28/08/2018
|
28/05/2019
|
85
|
|
|
|
|
55
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-314
|
SHIRUAIL MIAKANDI
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
68.96
|
M/S Pavel Enterprise
|
72.37
|
|
27/08/2018
|
27/05/2019
|
50
|
|
|
|
|
56
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-441
|
BORO KESHOB PUR
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
51.42
|
Madbor Traders
|
53.97
|
|
27/08/2018
|
27/05/2019
|
80
|
|
|
|
|
57
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-442
|
MRIJAR CHAR GPS
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
71.83
|
M/S Pavel Enterprise
|
75.39
|
|
27/05/2018
|
27/05/2019
|
85
|
|
|
|
|
58
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-443
|
MUNSHI KADIR PUR
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
70.91
|
M/S Eni Bani Enterprise
|
74.41
|
|
29/08/2018
|
19/05/2019
|
50
|
|
|
|
|
59
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-85
|
SULTAN KHAN KANDI
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
39.04
|
Md. Shakhawat Hossain
|
40.97
|
|
28/08/2018
|
27/05/2019
|
75
|
|
|
|
|
60
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-865
|
UTTOR CHAR JONAJAT
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
24.62
|
Green Construction
|
25.83
|
|
18/06/2018
|
18/03/2019
|
80
|
|
|
|
|
61
|
e-Tender/NBIDGPS/MAD/SHI/2017-2018/W1-866
|
CHAR SHEKHPUR
|
NBIDGPS-1
|
shibchar
|
|
|
|
|
56.26
|
M/S Hasina Akter
|
59.05
|
|
18/06/2018
|
18/03/2019
|
95
|
|
|
|
|
62
|
CW-39.d/RCIP/MDR
|
1. Improvement of Road from Khasherhat GC to Shariatpur R&H Road (Kalkini Part) (Ch: 00m to 2100m) under Kalkini Upazila, District: Madaripur (Road ID: 354402005) 2. Improvement of Road From Khoajpur-Takerhat R&H to Khasherhat GC Road via Laxmipur UP Office & Shurjamoni hat (Ch: 907m to 16500m) (Effective Length-15138m) under Kalkini Upazila, District: Madaripur (Road ID: 354402007)
|
RCIP
|
kalkini
|
|
17.24
|
0.00
|
66
|
2200.73
|
M/S Kohinoor Enterprise
|
1952.03
|
31/08/2020
|
15/09/2020
|
31/12/2022
|
76
|
1292.81
|
66
|
05/01/2023
|
|
63
|
CW-39.b/RCIP/MDR
|
1. Improvement of Road from NHW-Tribhagdi Hat GC road Ch 00m-5170m under Madaripur Sadar Upazila District Madaripur Road ID 354542003 2. Improvement of Road from Trivagdi GC-Mithapur Hat-Habiganj hat-Mollahat-Shekhpur RHD Ch 00m to 9663mEffective Length-9049m under Sadar Upazila District Madaripur Road ID 354542005
|
RCIP
|
madaripur-s
|
354542003
|
14.08
|
0.00
|
85
|
1945.05
|
M/S Kohinoor Enterprise
|
1957.00
|
31/08/2020
|
15/09/2020
|
18/12/2022
|
97
|
1662.47
|
85
|
31/08/2023
|
|
64
|
CW-39.a/RCIP/MDR
|
01. Improvement of Road from R&H Char Muguria-Sreenadi Hat GC Ch 00m to 17250mEffective Length 17250m under Sadar Upazila District Madaripur Road ID 354542001
|
RCIP
|
madaripur-s
|
354542001
|
17.25
|
0.00
|
85
|
2853.80
|
M/S Kohinoor Enterprise
|
2823.00
|
30/08/2020
|
15/09/2020
|
18/12/2022
|
100
|
2393.00
|
85
|
05/01/2023
|
|
65
|
CW-39.c/RCIP/MDR
|
1.Improvement of Madaripur Puran Bazar-Bangla Bazar-Hosnabad Bazar-Kalikapur UP Road from Ch. 00m to 6300m under Madaripur Sadar Upazila District Madaripur Road ID 354402005 2. Improvement of Road from Kalkini Upazila HQ to Khasherhat GC Road via Shomitirhat Bazar Ch.00m to 12505m under Kalkini Upazila District Madaripur Effective Length-10977m Road ID 354402007
|
RCIP
|
madaripur-s
|
354402005
|
17.28
|
0.00
|
86
|
1747.64
|
M/S Kohinoor Enterprise
|
1550.13
|
31/08/2020
|
15/09/2020
|
31/12/2022
|
90
|
1327.78
|
86
|
05/01/2023
|
|
66
|
CW-08/RCIP/MDR
|
1. Improvement of Paikpara UP-Fultala hat-Dhamarchar Rd. (Road ID354803006, Upazila: Rajoir, District: Madaripur) 2. Improvement of Takerhat GC-Sreenadi GC-Charmuguria-Khagdi RHD road (Road ID354802011, Upazila: Rajoir, District: Madaripur) 3. Improvement of Improvement of Rajoir Upazila H/Q - Sreenadi GC (Road ID354802005, Upazila: Rajoir, District: Madaripur) 4. Improvement of Improvement of Sagolchira R&H - Paikpara Union Road (Road ID354803011, Upazila: Rajoir, District: Madaripur) 5. Improvement of Takerhat GC - Kadambari GC (Road ID354802001, Upazila: Rajoir, District: Madaripur) 6. Improvement of Takerhat GC - Kabirajpur GC via Hossainpur UP (Road ID354802002, Upazila: Rajoir, District: Madaripur) 7. Improvement of Sanerpar R&H - Amgram GC road (Road ID354802003, Upazila: Rajoir, District: Madaripur)
|
RCIP
|
rajoir
|
354803006
|
64.56
|
0.00
|
92
|
8028.62
|
Mir Habibul Alam & Shamim Enterprise (Pvt.) Ltd. JV. Mobile Number: 01712562099
|
7874.06
|
29/09/2019
|
13/10/2019
|
31/03/2023
|
93
|
7221.28
|
92
|
05/01/2023
|
|
67
|
CW-39.e/RCIP/MDR
|
1. Improvement of Road from R&H, Bypass Road to Kathal Bari Ferry Ghat Road via Kutubpur Growth Center and Bangla Bazar (Ch: 00m to 8280m) under Shibchar Upazila, District: Madaripur (Road ID: 354872005)
|
RCIP
|
shibchar
|
354872005
|
8.28
|
0.00
|
91
|
1009.13
|
M/S Hamim International
|
1262.35
|
18/10/2020
|
21/10/2020
|
31/12/2022
|
97
|
1143.71
|
91
|
05/01/2023
|
|
68
|
RERMP-3/MA DARI/W-34
|
Maintenance of Rural
Roads Madaripur()
|
RERMP-3
|
madaripur-s
|
N/A
|
|
|
36
|
2190.00
|
N/A
|
2190.00
|
|
|
|
40
|
798.00
|
36
|
26/12/2021
|
|
69
|
MSRDP/M/17-18/BC/94
|
Improvement of NHW, Pathurirpar (Saw-mill) to Baligram UP Office (R&H Dhulgram Bazar) via West Baligram GPS and Anondho Bazar road from Ch. 2000.00 - 3385.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354403002).
|
RIDPMSRD
|
kalkini
|
354403002
|
1.39
|
|
100
|
96.61
|
M/S Howlader Enterprise
|
91.78
|
17/10/2018
|
24/10/2018
|
24/04/2019
|
100
|
91.78
|
100
|
18/04/2024
|
|
70
|
MSRDP/M/18-19/BC/245
|
Improvement of road by BC of Kalkili bazar - H/O Mati Howladar road from ch. 0.00m - 1350.00m Effective length 1344.00m link road -330mf under Kalkini upazila Dist- Madaripur Road ID no 354404014 .
|
RIDPMSRD
|
kalkini
|
354404014
|
1.35
|
|
100
|
126.32
|
M/S Laskar Steel & Furnitire
|
120.00
|
18/02/2019
|
25/02/2019
|
24/02/2019
|
100
|
123.58
|
100
|
18/04/2024
|
|
71
|
MSRDP/M/18-19/BC/247
|
Improvement of road by BC of Porabari Govt. Primary school - Atipara Monir Howladar House road at ch.0.00m - 1630.00m Effective length 1621.00m under Kalkini upazila Dist- Madaripur Road ID no 354404187.
|
RIDPMSRD
|
kalkini
|
354404187
|
1.63
|
|
100
|
118.63
|
Moin Enterprise
|
112.70
|
25/02/2019
|
04/03/2019
|
03/03/2019
|
100
|
112.69
|
100
|
18/04/2024
|
|
72
|
MSRDP/M/17-18/BC/86
|
Improvement of House of Ramjanpur Nasai Howlader to Uttar Ramjanpur High School road via F.W.C from Ch. 0.00 - 1410.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404053).
|
RIDPMSRD
|
kalkini
|
354404053
|
1.41
|
|
100
|
87.42
|
Simin Enterprise
|
86.97
|
17/10/2018
|
24/10/2018
|
30/06/2019
|
100
|
86.92
|
100
|
30/06/2020
|
|
73
|
MSRDP/M/17-18/BC/87
|
Improvement of UNR-151, House Radesham Gharami to UNR-10, H/O Shobhan Chowkeder via 65 no. Uttar Ramjanpur ME GPS road from Ch. 0.00 - 1630.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404054).
|
RIDPMSRD
|
kalkini
|
354404054
|
1.63
|
|
96
|
148.72
|
M/S Razia Construction
|
141.28
|
31/10/2018
|
07/11/2018
|
07/06/2019
|
100
|
135.11
|
96
|
30/06/2020
|
|
74
|
MSRDP/M/17-18/BC/88
|
Improvement of UNR-11, Hamid Khan hat to UNR-10, Ramjanpur Natun har road via Mohismari Girls School and uttar Ramjanpur Public GPS road from Ch. 3264.00 - 4400.00m by BC and Construction of 3x4.50x5.50m RCC Box Culvert at Ch. 646.00m on the same road under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404208).
|
RIDPMSRD
|
kalkini
|
354404208
|
1.14
|
|
100
|
111.21
|
Sagor Enterprise
|
105.65
|
17/10/2018
|
24/10/2018
|
24/05/2019
|
100
|
105.60
|
100
|
30/06/2020
|
|
75
|
MSRDP/M/17-18/BC/89
|
Improvement of Dhulgram hat to House of Bongram Abdul Hye Munshi road via Dhulgram GPS road from Ch. 0.00 - 1240.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354405290).
|
RIDPMSRD
|
kalkini
|
354405290
|
1.24
|
|
99
|
96.96
|
M/S Alif Mim
|
92.11
|
25/10/2018
|
31/10/2018
|
30/04/2019
|
100
|
91.33
|
99
|
30/06/2020
|
|
76
|
MSRDP/M/17-18/BC/90
|
Improvement of Kornopara R&H (Bottola) to Kornopara Boro Dgungi Bari vai Kornopara GPS road from Ch. 0.00 - 2213.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404188).
|
RIDPMSRD
|
kalkini
|
354404188
|
2.21
|
|
70
|
183.80
|
M/S Jannatul Ferdous
|
174.61
|
31/10/2018
|
07/11/2018
|
07/06/2019
|
100
|
174.58
|
70
|
30/06/2020
|
|
77
|
MSRDP/M/17-18/BC/91
|
Improvement of Krokirchar Mosque to Hamid Khan hat road via Krokirchar GPS road from Ch. 1000.00 - 2400.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404034).
|
RIDPMSRD
|
kalkini
|
354404034
|
1.40
|
|
94
|
93.72
|
M/S Motiar Rahman
|
89.03
|
17/10/2018
|
24/10/2018
|
24/04/2019
|
100
|
84.00
|
94
|
30/06/2020
|
|
78
|
MSRDP/M/17-18/BC/92
|
Improvement of Krokirchar GCCR Kalur Bridge to Sikder Market road via H/O Yousuf Miah road from Ch. 0.00 - 3005.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404167).
|
RIDPMSRD
|
kalkini
|
354404167
|
3.01
|
|
100
|
210.68
|
M/S Zaman Enterprise
|
200.15
|
28/10/2018
|
04/11/2018
|
04/05/2019
|
100
|
197.81
|
100
|
30/06/2020
|
|
79
|
MSRDP/M/17-18/BC/93
|
Improvement of Enayetnagar UP to Somitirhat road from Ch. 1000.00 - 2116.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354403035).
|
RIDPMSRD
|
kalkini
|
354403035
|
1.12
|
|
92
|
80.60
|
M/S Rajib Brother
|
76.57
|
17/10/2018
|
24/10/2018
|
24/04/2019
|
100
|
70.19
|
92
|
30/06/2020
|
|
80
|
MSRDP/M/17-18/BC/95
|
Improvement of UZR-01, CD Khan UP to Hassan Akoner Hat via Haji Karim Khan Hat road from Ch. 1500.00 - 2295.00m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354403031).
|
RIDPMSRD
|
kalkini
|
354403031
|
1.89
|
|
100
|
53.84
|
M/S Laskar Steel & Furnitire
|
51.15
|
17/10/2018
|
24/10/2018
|
24/04/2019
|
100
|
51.11
|
100
|
30/06/2020
|
|
81
|
MSRDP/M/17-18/SR/96
|
Constrcutin of 2 nos 3x4.50x5.50m RCC Box Culvert on NHW, Pathurirpar (Saw-mill) to Baligram UP Office (R&H Dhulgram Bazar) via West Baligram GPS and Anondho Bazar road from Ch. 2000m & 2700m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354403002).
|
RIDPMSRD
|
kalkini
|
354403002
|
|
27.00
|
100
|
67.24
|
M/S Kazal Krishno Dey
|
63.88
|
31/10/2018
|
07/11/2018
|
07/05/2019
|
100
|
63.88
|
100
|
30/06/2020
|
|
82
|
MSRDP/M/17-18/BC/124
|
Improvement of Dasar Pathuria to Paysarhat Renditala via Maizpara Cumminity Center to Mizpara Adarsha Eatim Khana road from Ch. 00.00 - 910.00m by BC and Construction of 1x3.50x3.50m RCC Box Culvert on this road at Ch 5.00m under Kalkini Upazila Dist. Madaripur Road ID No- 354405179.
|
RIDPMSRD
|
kalkini
|
354405179
|
0.91
|
|
100
|
77.60
|
M/S Razia Construction
|
73.72
|
31/10/2018
|
07/11/2018
|
07/05/2019
|
100
|
73.36
|
100
|
30/06/2020
|
|
83
|
MSRDP/ M/17-18/ BC/179
|
Improvement of BC Road from Laxmipur UP to Surjomoni Hat via Vatobali GPS Road at Ch.1000m-3225m Under Kalkini Upazila Dist Madaripur Road ID No- 354403033.
|
RIDPMSRD
|
kalkini
|
354403033
|
2.23
|
|
100
|
155.90
|
Md. Anowar Hossain
|
148.10
|
17/10/2018
|
24/10/2018
|
24/06/2019
|
100
|
148.08
|
100
|
30/06/2020
|
|
84
|
MSRDP/ M/17-18/ BC/180
|
Improvement of BC Road from Baligram UP-Dashar Bazar road via Kornopara Bazar Badamtola Bazar & Paschim Maizpara Road at Ch.00m-2700m Under Kalkini Upazila Dist Madaripur Road ID No- 354403020.
|
RIDPMSRD
|
kalkini
|
354403020
|
2.70
|
|
100
|
185.26
|
M/S Tafsia Enterprise
|
175.99
|
17/10/2018
|
24/10/2018
|
24/06/2019
|
100
|
175.97
|
100
|
30/06/2020
|
|
85
|
MSRDP/ M/17-18/ BC/181
|
Improvement of BC Road from Sheker Mongol UP Miarhat to CD Khan UP Mukter Hat Road at Ch.00m-2120m Under Kalkini Upazila Dist Madaripur Road ID No- 354403034.
|
RIDPMSRD
|
kalkini
|
354403034
|
2.12
|
|
100
|
149.17
|
M/S Kakoli Enterprise
|
141.71
|
17/10/2018
|
24/10/2018
|
24/05/2019
|
100
|
141.69
|
100
|
30/06/2020
|
|
86
|
MSRDP/ M/17-18/ BC/182
|
Part-A Improvement of BC Road from Dunlop Bazar-Kaliganj Bazar Road Near Choto Sadipur Bridge-Palordi River via Bivagdi Pry School road at Ch 845.00m-1600.00m. Part-B Construction of 1x1.00x1.00m Single Vent RCC Box Culvert on Same Road at Ch 1050.00m Under Kalkini Upazila Dist Madaripur Road ID No- 354404082.
|
RIDPMSRD
|
kalkini
|
354404082
|
0.76
|
|
100
|
63.88
|
S.S Trade International
|
60.69
|
31/10/2018
|
07/11/2018
|
07/05/2019
|
100
|
60.66
|
100
|
30/06/2020
|
|
87
|
MSRDP/M/18-19/HBB/240
|
Improvement of road by HBB of UZR-01Kalkini Upazila HQ to Mollarhat GC road via Sahebrampur UP office to Natun Chair Dawlatkhan GPS road from ch. 0.00m - 568.00m Effective length 568.00m under Kalkini upazila Dist- Madaripur Road ID no 354405517 .
|
RIDPMSRD
|
kalkini
|
354405517
|
0.57
|
|
100
|
26.78
|
M/S Sima Traders
|
25.44
|
10/02/2019
|
17/02/2019
|
17/06/2019
|
100
|
25.42
|
100
|
30/06/2020
|
|
88
|
MSRDP/M/18-19/RCC/241
|
Construction of 3x4.5x4.5m RCC box culvert at UNR-3002NHW Pathuriarpar saw mill to Baligram UP office R&H Dhalugram bazar via paschim Baligram GPS and Ananda bazar road to Dhanua GPS road at ch. 0.00m under Kalkini upazila Dist- Madaripur Road ID no 354405508 .
|
RIDPMSRD
|
kalkini
|
354405508
|
|
12.00
|
100
|
38.32
|
M/S Sumaya Enterprise
|
36.41
|
14/02/2019
|
20/02/2019
|
20/06/2019
|
100
|
36.40
|
100
|
30/06/2020
|
|
89
|
MSRDP/M/18-19/HBB/243
|
Improvement of road by HBB of UZR-05Biddya Bagish GPS road from ch. 0.00m - 700m Effective length 700.00m under Kalkini upazila Dist- Madaripur Road ID no 354405505 .
|
RIDPMSRD
|
kalkini
|
354405505
|
0.70
|
|
100
|
31.27
|
M/S Jana Alam Enterprise
|
29.71
|
17/02/2019
|
24/02/2019
|
24/06/2019
|
100
|
29.69
|
100
|
30/06/2020
|
|
90
|
MSRDP/M/18-19/HBB/244
|
Improvement of road by HBB of VRA-4033Sheikh Hasina Academy - Babazzer Khal Dasar Bazar to Dasar Sayed Atahar ali GPS from ch. 0.00m to 83.00m Effective length 83.00m under Kalkini upazila Dist- Madaripur Road ID no 354405503 .
|
RIDPMSRD
|
kalkini
|
354405503
|
0.83
|
|
100
|
3.52
|
Simin Enterprise
|
3.33
|
14/02/2019
|
20/02/2019
|
20/08/2019
|
100
|
3.33
|
100
|
30/06/2020
|
|
91
|
MSRDP/M/18-19/BC/246
|
Improvement of road by BC of Kornopara NHW to Baligram UProad ch. 0.00m - 1200.00m Effective length 1200.00m under Kalkini upazila Dist- Madaripur Road ID no 354404114 .
|
RIDPMSRD
|
kalkini
|
354404114
|
1.20
|
|
100
|
97.42
|
M/S Lion Enteprise
|
92.55
|
25/02/2019
|
03/03/2019
|
03/10/2019
|
100
|
102.43
|
100
|
30/06/2020
|
|
92
|
MSRDP/M/18-19/BC/249
|
Part-01 Improvement of road by BC of Dashar Hafezia Madrasha - Sayed Chan Miah House road from ch. 0.00m -550.00m Effective length 550.00m under Kalkini upazila Dist- Madaripur Road ID no 354405132.Part-02 Construction of 11.001.00m RCC Box culvert on this road at ch. 310.00m under Kalkini upazila Dist- Madaripur Road ID no 354405132.
|
RIDPMSRD
|
kalkini
|
354405132
|
0.55
|
|
100
|
47.15
|
M/S S S Enterprise
|
44.79
|
18/02/2019
|
28/02/2019
|
25/08/2019
|
100
|
44.77
|
100
|
30/06/2020
|
|
93
|
MSRDP/M/18-19/HBB/250
|
Part-01 Improvement of road by HBB of VRA- 4190Bhanga bridge R&H- Amratola Boro Bari Via Khatial GPS road at ch. 0.00m - 550.00m Effective length 500.00m under Kalkini upazila Dist- Madaripur Road ID no 354405511.Part-02 Construction of 11.001.00m RCC Box culvert on this road at ch. 70.00m under Kalkini upazila Dist- Madaripur Road ID no 354405511.
|
RIDPMSRD
|
kalkini
|
354405511
|
0.55
|
|
100
|
28.12
|
M/S Jana Alam Enterprise
|
26.71
|
17/02/2019
|
24/02/2019
|
24/06/2019
|
100
|
26.70
|
100
|
30/06/2020
|
|
94
|
MSRDP/M/18-19/BC/277
|
Improvement of road by BC of R&H Kazibakai UP Office to UNR-26 Dorshona Bazar & GPS road via Maizpara GPS road from Ch. 1790.00m - 3230.00m Effective length- 1430.00m under Kalkini Upazila Dist Madaripur Road Id No 354403017.
|
RIDPMSRD
|
kalkini
|
354403017 & 354804013
|
1.44
|
|
43
|
105.86
|
M/S Mim Alif Traders
|
86.27
|
12/05/2019
|
19/05/2019
|
18/05/2020
|
50
|
37.28
|
43
|
30/06/2020
|
|
95
|
MSRDP/M/18-19/SR/299
|
Part-A Construction of 2x4.50x4.50m Rcc Box Culvert on R&H Sanmandi Bazar to NHW Bhanga Bridge Bazar Road at 1579.00m.Part-B Construction of 2x4.50x4.50m Rcc Box Culvert on R&H Sanmandi Bazar to NHW Bhanga Bridge Bazar Road at 1885.00m under Kalkini Dist MadaripurRoad ID No 354404038.Part- C Construction of 3x4.50x5.50m Rcc Box Culvert on R&H Sanmandi Bazar to NHW Bhanga Bridge Bazar Road at 1074.00m.Part-D Construction of 2x4.50x5.50m Rcc Box Culvert on R&H Sanmandi Bazar to NHW Bhanga Bridge Bazar Road at 1396.00m under Kalkini Dist MadaripurRoad ID No 354404038.
|
RIDPMSRD
|
kalkini
|
354404038
|
|
40.00
|
|
143.04
|
|
0.00
|
|
|
|
0
|
|
|
09/07/2019
|
|
96
|
MSRDP/M/18-19/BC/300
|
Part-A Hindu Para H/O Dhulu Mistri to Sona Kha House Road via 68 No. Dakhin Ramjanpur GPS & Talukder Bari Ch.0.00m - 1124.00m under Kalkini Dist. Madaripur Road ID No 354405417.Part-B Construction of 1x1.00x1.00m RCC single vent Box culvert on the same road at Ch. 170.00m.Part-C Construction of 1x1.00x1.00m RCC single vent Box culvert on the same road at Ch. 477.00m.
|
RIDPMSRD
|
kalkini
|
354405417
|
1.12
|
|
|
102.68
|
|
0.00
|
|
|
|
0
|
|
|
09/07/2019
|
|
97
|
MSRDP/M/18-19/BC/301
|
Part-A Improvement of UZR-01 Bordar Ghat to UNR-10 Ramjanpur UP office via Jhurgaon Hat road from Ch. 0.00m - 2184.00m by BC Road ID 354403029.Part-B Improvement of UZR-11 Ramjanpur UP office to UNR-29 via Ramjanpur Notun Hat road from Ch. 3948.00m - 5240.00m by BC Road ID 354403010.Part-CConstruction of 1.00mx1.00m single vent RCC Box culvert on UNR-11 Ramjanpur UP Office to UNR-29 via Ramjanpur Notun Hat & Ramjanpur Madrasa road at Ch. 4210m 4425m 4651m & 4842m.
|
RIDPMSRD
|
kalkini
|
354403010
|
3.48
|
|
|
260.93
|
|
0.00
|
|
|
|
0
|
|
|
09/07/2019
|
|
98
|
MSRDP/M/18-19/BC/313
|
Part-A Improvement of Road by BC Purbo Charairkandi GPS to Uttor Ramjanpur Nurani Madrasha road at Ch. 00.00-1610.00m Effective Length 1606.00m.Part-BConstruction of 1x1.00x1.00m RCC Box Culvert on same road at Ch. 835.00m under Kalkini Upazila Dist Madaripur. Road ID No 354405335 .
|
RIDPMSRD
|
kalkini
|
354405335
|
1.61
|
|
|
127.63
|
|
0.00
|
|
|
|
0
|
|
|
09/07/2019
|
|
99
|
MSRDP/M/18-19/BC/314
|
Improvement of Road by BC Dakhin Char Airkandi Majher Kheya Ghat to Char Palordi GPS Road via H/O Ramjan Hawlader Road at Ch. Ch.0.00m -1940.00m Effective Length 1907.00m under Kalkini Upazila Dist Madaripur Road ID No 354405415 .Construction of 2x4.50x4..50m RCC Box Culvert on Dakhin Char Airkandi Majher Kheya Ghat to Char Palordi GPS Road via H/O Ramjan Hawlader Road From Ch.1095m under Kalkini Upazila Dist Madaripur Road ID No 354405415 .Construction of 3x4.50x5..50m RCC Box Culvert on Dakhin Char Airkandi Majher Kheya Ghat to Char Palordi GPS Road via H/O Ramjan Hawlader Road at Ch.900m under Kalkini Upazila Dist Madaripur Road ID No 354405415 .
|
RIDPMSRD
|
kalkini
|
354405415
|
1.94
|
|
|
218.57
|
|
0.00
|
|
|
|
0
|
|
|
09/07/2019
|
|
100
|
MSRDP/M/18-19/BC/315
|
Part-A Improvement of Road by BC Char Laxmi Tumchar Road At Ch.1000.00m-1780.00m Effective Length 780.00m.Part-B Construction of 1x1.00x1.00m RCC Box Culvert This Road at Ch.1005.00m. Part-C Construction of 1x1.00x1.00m RCC Box Culvert on same road at Ch.1100.00m under Kalkini Upazila Dist Madaripur Road ID No354404121
|
RIDPMSRD
|
kalkini
|
354404121
|
0.78
|
|
|
74.76
|
|
0.00
|
|
|
|
0
|
|
|
09/07/2019
|
|
101
|
MSRDP/M/18-19/BCMaint/03
|
Periodic Maintenance of RHD to Puail Madaripur Road at Ch 0.00 - 525m Under Kalkini Upazila Dist Madaripur Road ID 354404106.
|
RIDPMSRD
|
kalkini
|
354404106
|
0.53
|
|
|
22.37
|
M/S Howlader and Co
|
21.25
|
|
|
|
0
|
|
|
09/07/2019
|
|
102
|
MSRDP/M/17-18/SR/97
|
Constrcutin of 1x4.50x4.50m RCC Box Culvert on Andarchar Hassan Akoner hat to Mokter hat road via Haji Karim hat road from Ch. 700m by BC under Kalkini Upazila, Dist. Madaripur, (Road ID No- 354404168).
|
RIDPMSRD
|
kalkini
|
354404168
|
|
4.50
|
100
|
15.89
|
M/S Mazada Traders
|
15.10
|
24/10/2018
|
31/10/2018
|
31/01/2019
|
100
|
15.09
|
100
|
30/06/2019
|
|
103
|
MSRDP/M/17-18/BC/123
|
Improvement of Shanan Ghata Senior Madrasha-Kachikata Madrasha via Muzibul Haque Mantu Master House road from Ch. 1000.00 - 2500.00m by BC under Kalkini Upazila Dist. Madaripur Road ID No- 354405192.
|
RIDPMSRD
|
kalkini
|
354405192
|
1.50
|
|
100
|
108.65
|
M/S Khokon Bapari
|
103.22
|
28/10/2018
|
04/11/2018
|
04/06/2019
|
100
|
103.20
|
100
|
30/06/2019
|
|
104
|
MSRDP/ M/17-18/ BC/183
|
Improvement of BC Road from CD Khan UP High School to Jurgha Hat via Dhaki Kandi GPS Pazila Road at Ch.00.00m-2930m Under Kalkini Upazila Dist Madaripur Road ID No- 354403038.
|
RIDPMSRD
|
kalkini
|
354403038
|
2.93
|
|
100
|
186.59
|
M/S Motiar Rahman
|
177.26
|
17/10/2018
|
24/10/2018
|
24/06/2019
|
100
|
177.24
|
100
|
30/06/2019
|
|
105
|
MSRDP/ M/17-18/ BC/184
|
Part-A Improvement of BC Road from CD Khan UP Mokter Hat to UZR-01 Sajal Hawlader House road at Ch 00.00.m-1167.00m. Part-B Construction of 1x1.00x1.00m Single Vent RCC Box Culvert on Same Road at Ch 208.00m Under Kalkini Upazila Dist Madaripur Road ID No- 354405395.
|
RIDPMSRD
|
kalkini
|
354405395
|
1.17
|
|
100
|
80.97
|
M/S Khan Traders
|
76.92
|
17/10/2018
|
24/10/2018
|
24/04/2019
|
100
|
76.90
|
100
|
30/06/2019
|
|
106
|
MSRDP/M/18-19/HBB/242
|
Improvement of road by HBB of UZR-03Bhurghata NHW to Kotalipara R&H via Shasikor GC road to Dhamusa GPS road from ch. 0.00m - 150.00mEffective length 150.00m under Kalkini upazila Dist- Madaripur Road ID no 354405508 .
|
RIDPMSRD
|
kalkini
|
354405508
|
0.15
|
|
100
|
6.85
|
M/S Shahajalal Enterprise
|
6.50
|
18/02/2019
|
25/02/2019
|
25/04/2019
|
100
|
6.49
|
100
|
30/06/2019
|
|
107
|
MSRDP/M/18-19/BC/248
|
Improvement of road by BC of Gopalpur - Purbo Baligram road from Ch. 1860.00m - 3150.00m Effective length 1267.00m under Kalkini upazila Dist- Madaripur Road ID no 354405039 .
|
RIDPMSRD
|
kalkini
|
354405039
|
1.29
|
|
100
|
98.73
|
M/S Daber & Brothers
|
93.79
|
10/02/2019
|
17/02/2019
|
17/11/2019
|
100
|
93.77
|
100
|
30/06/2019
|
|
108
|
MSRDP/M/18-19/BC/319
|
Estimate for Construction of Charmugria Hafizia Madrasha - Cleaner Coloney via Beribadh Nasiminagar Freedom Fighter Navel Commander Gafur Khan Road Ch.00.00m 1500m By RCC Under Sadar Upazila Dist Madaripur. Road ID No 354545351.
|
RIDPMSRD
|
madaripur-s
|
354545351
|
1.50
|
|
100
|
130.55
|
|
112.45
|
|
|
|
100
|
112.44
|
100
|
18/04/2024
|
|
109
|
MSRDP/M/ 17-18/BC/48
|
Improvement of BC Road from Aligi - Thither Para road at Ch. 0.00 - 1500.00m under Sadar Upazila Dist. Madaripur Road ID No- 354545111.
|
RIDPMSRD
|
madaripur-s
|
354545111
|
1.50
|
|
52
|
77.50
|
M/S Niloy Enterprise
|
73.63
|
28/05/2018
|
15/09/2018
|
15/03/2019
|
60
|
38.00
|
52
|
30/06/2020
|
|
110
|
MSRDP/M/ 17-18/BC/49
|
A Improvement of BC Road from Bahadurpur - Aligi High School road at Ch. 0.00 - 1500.00m under Sadar Upazila Dist. Madaripur Road ID No- 354544022.B Construction of 1x3.00x3.00m RCC Box Culvert on Bahadurpur - Aligi High School road at Ch. 700.00m under Sadar Upazila Dist. Madaripur Road ID No- 354544022.
|
RIDPMSRD
|
madaripur-s
|
354544022
|
1.50
|
|
65
|
116.00
|
M/S Ashma Sindikt
|
110.21
|
07/06/2018
|
15/09/2018
|
15/04/2019
|
70
|
71.62
|
65
|
30/06/2020
|
|
111
|
MSRDP/M/ 17-18/SR/54
|
Constrcutin of 15.00m Long RCC Girder Bridge on Kalir Bazar Algi High School road F/O Syed Sakowat Hossain at Ch. 540.00m under Sadar Upazila Dist. Madaripur Road ID No- 354544022 .
|
RIDPMSRD
|
madaripur-s
|
354544022
|
|
15.00
|
100
|
82.08
|
M/S Sharmin Construction
|
77.79
|
28/05/2018
|
15/09/2018
|
15/03/2019
|
100
|
77.97
|
100
|
30/06/2020
|
|
112
|
MSRDP/M/ 17-18/SR/55
|
Constrcutin of 2x4.5x4.5m RCC Box Culvert on Dhurial Sarder Kandi - Bill Padma River road at Ch. 460.00m under Sadar Upazila Dist. Madaripur Road ID No- 354545478.
|
RIDPMSRD
|
madaripur-s
|
354545478
|
|
9.00
|
100
|
23.60
|
M/S sadia Enterprise
|
22.42
|
24/05/2018
|
03/06/2018
|
30/10/2018
|
100
|
22.42
|
100
|
30/06/2020
|
|
113
|
MSRDP/M/ 17-18/SR/57
|
Constrcutin of 1x3.00x3.00m RCC Box Culvert on Kunia - Asapat GPS road at Ch. 5.00m under Sadar Upazila Dist. Madaripur Road ID No- 354545068.
|
RIDPMSRD
|
madaripur-s
|
354545068
|
|
3.00
|
100
|
7.65
|
M/S Arifin International
|
7.27
|
28/05/2018
|
15/09/2018
|
15/12/2018
|
100
|
7.25
|
100
|
30/06/2020
|
|
114
|
MSRDP/M/ 17-18/BC/60
|
Improvement of BC Road from LGED Road - Dokkin Mohisher Char CPB Connecting Road at Ch. 0.00 - 500.00 under Sadar Upazila Dist. Madaripur DPP Road ID No- 354545371 New Road ID No- 354545353.
|
RIDPMSRD
|
madaripur-s
|
354545353
|
0.50
|
|
100
|
32.42
|
M/S Mon Mahara Enterprise
|
30.80
|
28/05/2018
|
15/09/2018
|
15/03/2019
|
100
|
30.74
|
100
|
30/06/2020
|
|
115
|
MSRDP/M/17-18/BC/98
|
Improvement of LGED Road-Char Kalikapur GPS connecting road from Ch. 0.00 - 1085.00m by BC and Construction of 2x4.50x4.50m RCC Box Culvert at Ch. 1065.00m on the same road under Sadar Upazila, Dist. Madaripur, (Road ID No- 354545429, New ID No - 354545362).
|
RIDPMSRD
|
madaripur-s
|
354545362
|
1.09
|
|
100
|
95.30
|
M/S Orpa Enterprise
|
90.53
|
18/08/2018
|
15/09/2018
|
15/03/2019
|
100
|
90.44
|
100
|
30/06/2020
|
|
116
|
MSRDP/M/17-18/BC/99
|
Improvement of LGED Road-Uttar Mohisherchar Community Primary School Connecting road from Ch. 0.00 - 1050.00m by BC under Sadar Upazila, Dist. Madaripur, (Road ID No- 354545380, New ID - 354545363).
|
RIDPMSRD
|
madaripur-s
|
354545380
|
1.05
|
|
100
|
75.35
|
M/S Adiba Assiosed
|
0.00
|
13/09/2018
|
20/09/2018
|
20/03/2019
|
100
|
71.55
|
100
|
30/06/2020
|
|
117
|
MSRDP/M/17-18/BC/100
|
Improvement of Moheserchar Pucca Mosjid-Chowkider bari road from Ch. 0.00 - 1000.00m by BC under Sadar Upazila, Dist. Madaripur, (Road ID No- 354544581, New ID - 354545364).
|
RIDPMSRD
|
madaripur-s
|
354544581
|
1.00
|
|
100
|
67.19
|
M/S J Alom Construction
|
63.83
|
01/08/2018
|
15/09/2018
|
15/03/2019
|
100
|
66.68
|
100
|
30/06/2020
|
|
118
|
MSRDP/M/17-18/SR/103
|
Constrcutin of 2x4.50x4.50m RCC Box Culvert on LGED road-Baherchar Katla GPS connecting road from Ch. 345m over Khal under Sadar Upazila, Dist. Madaripur, (Road ID No- 354545383, New ID - 354545365).
|
RIDPMSRD
|
madaripur-s
|
354545383
|
|
9.00
|
100
|
21.07
|
M/S Chokder Enterprise
|
20.02
|
18/08/2018
|
15/09/2018
|
15/12/2018
|
100
|
20.00
|
100
|
30/06/2020
|
|
119
|
MSRDP/M/17-18/BC/111
|
Improvement of Gagonpur Bazar-Tubia Baligram Baro Bari Bridge Jhawdi UP road from Ch. 1000.00 - 2500.00m by BC under Sadar Upazila Dist. Madaripur Road ID No- 354543027.
|
RIDPMSRD
|
madaripur-s
|
354543027
|
1.50
|
|
100
|
125.13
|
Taspia and Brother
|
118.88
|
04/09/2018
|
15/09/2018
|
15/03/2019
|
100
|
118.85
|
100
|
30/06/2020
|
|
120
|
MSRDP/M/17-18/BC/112
|
Improvement of LGED Road-SHEIKHI NOW HATA Connecting road from Ch. 00.00 - 1000.00m by BC under Sadar Upazila Dist. Madaripur Road ID No- 354545411 New ID. 354545359.
|
RIDPMSRD
|
madaripur-s
|
354545411
|
1.00
|
|
53
|
69.49
|
M/S Chokder Enterprise
|
69.49
|
18/08/2018
|
15/09/2018
|
15/03/2019
|
65
|
36.75
|
53
|
30/06/2020
|
|
121
|
MSRDP/M/17-18/BC/114
|
Improvement of Mostafapur UP Bhaban-Chandir Bazar via Chuchia Bhanga Bazar-Korom Bazar road from Ch. 7100.00 - 8600.00m by BC under Sadar Upazila Dist. Madaripur Road ID No- 354544025.
|
RIDPMSRD
|
madaripur-s
|
354544025
|
1.50
|
|
78
|
110.03
|
M/S Mazada Traders
|
104.53
|
05/09/2018
|
15/09/2018
|
15/04/2019
|
80
|
81.77
|
78
|
30/06/2020
|
|
122
|
MSRDP/M/17-18/BC/116
|
Improvement of R&H-Bhadrokhola GPS Connecting road from Ch. 00.00-1065.00m by BC under Sadar Upazila Dist. Madaripur Road ID No- 354545430 New ID. 354545361.
|
RIDPMSRD
|
madaripur-s
|
354545430
|
1.07
|
|
100
|
100.66
|
Afzal Construction
|
95.62
|
23/10/2018
|
30/10/2018
|
30/05/2019
|
100
|
95.61
|
100
|
30/06/2020
|
|
123
|
MSRDP/M/17-18/SR/117
|
Construction of 2 Two Nos. 1x4.50mx3.50m RCC Box Culvert on Kukrail Montu Das bridge to Kordi Delwar Hawlader House road at Ch 1500.00m & 2500.00m over Canal under Sadar Upazila Dist. Madaripur Road ID No- 354545209 .
|
RIDPMSRD
|
madaripur-s
|
354545209
|
|
9.00
|
100
|
27.09
|
M/S Asma Sendicate
|
25.74
|
23/10/2018
|
30/10/2018
|
30/01/2019
|
100
|
25.72
|
100
|
30/06/2020
|
|
124
|
MSRDP/M/17-18/BC/119
|
Improvement of R&H-Bhadrokhola Siddikhola Busstand-Baherandi GPS-Tatibari Bazar road from Ch. 00.00 - 1680.00m by BC under Sadar Upazila Dist. Madaripur Road ID No- 35455245 New ID. 354544029.
|
RIDPMSRD
|
madaripur-s
|
35455245
|
1.68
|
|
93
|
84.56
|
M/S Asma Sendicate
|
80.33
|
23/10/2018
|
30/10/2018
|
30/04/2019
|
100
|
74.96
|
93
|
30/06/2020
|
|
125
|
MSRDP/ M/17-18/ VR-BC/163
|
Improvement of BC Road from Islampur Bridge to TB Clinic Road at CH.1500m-2330mEffective Length 820m Under Jhoudi UP & Construction of 24.5m4.5m RCC Box Culvert on Islampur Bridge to TB Clinic Road at Ch.1830m Under Jhoudi UPMadaripur SadarMadaripur Road ID No- 354545239.
|
RIDPMSRD
|
madaripur-s
|
354545239
|
0.83
|
|
96
|
110.18
|
Honey Bangladesh
|
104.67
|
17/10/2018
|
24/10/2018
|
24/05/2019
|
100
|
101.00
|
96
|
30/06/2020
|
|
126
|
MSRDP/ M/17-18/ VR-SR/164
|
Construction of 18 m RCC Girder Bridge on NHW-Mostafapur Baro Bridge-Parboth Bagan Mostafapur GPS Connecting Road at Ch.12m Under Madaripur Sadar Madaripur Road ID No- 354545341.
|
RIDPMSRD
|
madaripur-s
|
354545341
|
|
18.00
|
100
|
133.85
|
M/S Nargis Enterprise
|
127.16
|
17/10/2018
|
24/10/2018
|
24/05/2019
|
100
|
127.15
|
100
|
30/06/2020
|
|
127
|
MSRDP/ M/17-18/ VR-BC/165
|
Improvement of BC Road from Kalikhola poura Boundary-Madra Bazar Road at Ch.2013m-3032mEffective Length 1000m Under Jhoudi UP & Construction of 1x2.00x2.00m RCC Box Culvert on Kalikhola poura Boundary-Madra Bazar Road at Ch.2650m Madaripur SadarMadaripur Road ID No- 354544004.
|
RIDPMSRD
|
madaripur-s
|
354544004
|
1.02
|
|
100
|
76.26
|
M/S Nur Enterprise
|
72.44
|
23/10/2018
|
30/10/2018
|
30/04/2019
|
100
|
72.37
|
100
|
30/06/2020
|
|
128
|
MSRDP/ M/17-18/ VR-SR/167
|
Construction of 18 m RCC Girder Bridge on Bir Muktijoddha Jillur Rahman Bridge Mithapur Puran BazarDoagibari Bridge- Registered School -Algi High School-Kunia hat-Samadder R& H Katherpool Road at Ch.8650m Under Madaripur Sadar MadaripurRoad ID No- 354543018.
|
RIDPMSRD
|
madaripur-s
|
354543018
|
|
18.00
|
100
|
131.62
|
M/S Mizan Enterprise
|
125.04
|
17/10/2018
|
24/10/2018
|
24/05/2019
|
100
|
125.03
|
100
|
30/06/2020
|
|
129
|
MSRDP/ M/17-18/ VR-BC/169
|
Improvement of BC LGED ROAD-SILAR CHAR AULIAPUR Connecting Road Via Nilkuti Bazar -Mahamudpur Bazar-Shariatpur Border Road At.CH00m-1075mEffective Lnggth1000munder Madaripur Sadar upazila Dist Madaripur. DPP ID NO354545410 Road Inve.ID No.354545377
|
RIDPMSRD
|
madaripur-s
|
354545410
|
1.08
|
|
77
|
108.29
|
M/S M.S Traders
|
102.87
|
17/10/2018
|
24/10/2018
|
24/05/2019
|
90
|
79.08
|
77
|
30/06/2020
|
|
130
|
MSRDP/ M/17-18/ VR-BC/170
|
Improvement of BC Road from R&H - Char Pokhira Connecting Road at Ch00m-1300mEffective Lnggth1300m under Madaripur Sadar upazila Dist Madaripur. DPP ID NO354545391 Road Inve.ID No.354545380.
|
RIDPMSRD
|
madaripur-s
|
354545391
|
1.30
|
|
100
|
94.31
|
M/S Howlader Enterprise
|
89.60
|
17/10/2018
|
24/10/2018
|
24/04/2019
|
100
|
89.57
|
100
|
30/06/2020
|
|
131
|
MSRDP/ M/17-18/ BC/187
|
Improvement of Kazirtek Shiekpur R&H H/O Ex Chairman Abdul Jabbar-Howla Chilarchar Sharitpur Border road from Ch 00-2200m Under Sadar Dist Madaripur Road ID No- 35454490.
|
RIDPMSRD
|
madaripur-s
|
35454490
|
2.20
|
|
100
|
214.17
|
|
190.56
|
11/11/2018
|
18/11/2018
|
18/07/2019
|
100
|
190.50
|
100
|
30/06/2020
|
|
132
|
MSRDP/ M/17-18/ BC/188
|
Part-1 Improvement of R & H Khoajpur Bailey bridge Degree kandi road from Ch 500-1500m Under Sadar Dist Madaripur Road ID No- 354545017.Part-2 Improvement of Lged road Char Gobindopur Sanirvar GPS Connecting road from Ch 00-1000m Under Sadar Dist Madaripur Road ID No- 354545390.
|
RIDPMSRD
|
madaripur-s
|
354545390
|
2.00
|
|
100
|