Coastal Towns Environmental Infrastructure Project (CTEIP) (Revised)

Serial District Name District Code/ID Upazila Name Upazila Code/ID Project ID Package No Scheme Name Road ID Length of Scheme(Km) - Road Length of Scheme(m) - Bridge/Culverts Building Quantity Estimated Amount(LAC) Contractor Name Contract Amount(LAC) Date of Contract (DD/MM/YYYY) Date of commencement (DD/MM/YYYY) Date of Completion (DD/MM/YYYY) Physical Progress(%) Financial Progress (Amount) (LAC) Financial Progress(%) Date of Progress Update (DD/MM/YYYY) Remarks
1 Bagerhat 44 bagerhat-s 320 287 e-GP/CTEIP/2017-18/BAG/RD-03 Improvement of 2 nos road totalling 5016m including roadside drain 1098m at Bagerhat Pourashava, District: Bagerhat 5.02 600.58 M/S Al Mamun Entrprise 630.53 31/12/2018 01/06/2020 100 615.00 98 04/04/2021 WorkS Completed
2 Bagerhat 44 bagerhat-s 320 287 e-GP/CTEIP/2016-17/BAG/CS-01 Contruction of Cyclone Shelter at Suvechha Shisu Govt. Primary School, Ward No. 07, Bagerhat Pourashava Sadar; District: Bagerhat 1.00 333.94 M/S Alif Store 367.14 25/07/2017 100 372.00 100 04/04/2021 Works Completed
3 Bagerhat 44 bagerhat-s 320 287 e-GP/CTEIP/2016-17/BAG/RD-02 Improvement of 1(One) no road totaling 1486m including road side drain 1450 m at Bagerhat Pourashava; Upazila: Bagerhat Sadar; District: Bagerhat. 1.49 578.23 SSB & IEL JV 591.39 28/05/2017 27/05/2019 100 602.80 100 04/04/2021 Completed
4 Bagerhat 44 bagerhat-s 320 287 e-GP/CTEIP/2016-17/BAG/RD-01 Improvement of 2 (Two) nos. road totaling 5458 m at (1) Improvement of Road by Bituminous Carpeting (BC) of Town Protection Bandh Road. ( Ward no. 1, 4, 5, 7, 8 & 9) (2) Improvement of Road by Bituminous Carpeting (BC) on Rail Line by-pass road from Rail 5.46 1084.39 NT-AMEL-NT JV 1018.30 25/05/2017 24/05/2019 100 1018.00 100 04/04/2021 Completed
5 Barguna 2 amtali 16 287 e-GP/CTEIP/2018-19/AMT/CM-01 Improvement of Amtali Central Cattle Market. 247.15 0.00 10/10/2019 10/09/2020 38 95.00 38 04/04/2021 Works Ongoing
6 Barguna 2 amtali 16 287 e-GP/CTEIP/2018-19/AMT/RD-05 Construction/ Improvement of 5 no. Road under Amtali Pourashava 4.88 369.42 369.42 13/03/2020 12/06/2020 90 287.00 78 04/04/2021
7 Barguna 2 amtali 16 287 e-GP/CTEIP/2018-19/AMT/RD-04 Construction/ Improvement of 2 no. Road 376.02 376.02 26/02/2019 25/02/2020 100 376.00 100 04/04/2021 GOB Funded
8 Barguna 2 amtali 16 287 e-GP/CTEIP/2018-19/AMT/BB-01 Construction of Bus Bay 479.92 479.92 20/02/2019 25/02/2020 75 335.00 70 04/04/2021 GOB Funded
9 Barguna 2 amtali 16 287 e-GP/CTEIP/2017-18/AMT/BLS-01 Construction of 02 nos Boat Landing Station at Aamal Pal Swamill Ghat & Amtali Kat Market Ghat Under Amtali Pourashava 2.00 151.59 Al Mamun Enterprise 166.59 25/10/2018 28/04/2020 98 128.00 77 04/04/2021 Works Ongoing
10 Barguna 2 amtali 16 287 e-GP/CTEIP/2017-18/AMT/BR-01 Construction of 2 nos RCC Long Girder Bridge at Amtali Pourashava, District: Amtali 29.00 280.03 M/S Mohiuddin Ahmed 307.33 05/10/2018 11/10/2019 100 307.30 100 04/04/2021 Completed
11 Barguna 2 amtali 16 287 e-GP/CTEIP/2017-18/AMT/RD-03 Improvement / Construction of Two (02) Nos Road Totaling 2.237 Km Flexible & Rigid Pavement with 06 Nos Box Culvert, 13 Nos Cross Pipe & 340.20m Protection work under Amtali Pourashava, Barguna. 2.24 247.07 M/S Rupali Construction 300.33 05/10/2018 11/10/2019 100 300.68 100 04/04/2021  
12 Barguna 2 amtali 16 287 e-GP/CTEIP/2017-18/AMT/MM-01 Construction of Multipurpose Market at Amtali Pourashava, District: Barguna 1.00 258.08 M/S Mohiuddin Ahmed & M/s Deep Enterprise (JV) 282.58 05/10/2018 11/10/2019 89 240.00 79 04/04/2021  
13 Barguna 2 amtali 16 287 e-GP/CTEIP/2014-15/AMT/RD-02 Improvement of 04 nos. road, totaling 4.531 km at Amtali Pourashava, District: Barguna 4.53 466.86 Md. Mahfuz Khan 402.51 02/01/2016 28/03/2018 100 354.00 100 04/04/2021 Completed
14 Barguna 2 amtali 16 287 e-GP/CTEIP/2016-17/AMT/PT-01 Construction of 3 nos Public Toilet at Amtali Pourashava, District: Barguna 3.00 69.97 M/S Abul Kalam Azad 62.27 24/08/2017 23/02/2019 100 62.96 100 04/04/2021 Completed
15 Barguna 2 amtali 16 287 e-GP/CTEIP/2014-15/AMT/WS-01 Construction of Two Production TW; One OHT, Pipeline (26.77 km Dristribution and Transmission; 4.4 km Replaced Pipeline, 1747 Service Connection and replaced 400 service connection); Two Pump House; Supply of O & M tools and Supply, fitting, fixing and co 33.50 1262.27 M/S Zilani Traders-Noor & Co. (JV) 1260.06 17/01/2016 25/02/2019 100 1311.00 100 04/04/2021 Completed
16 Barguna 2 amtali 16 287 e-GP/CTEIP/2014-15/AMT/DR-01 Construction of Drains and box culverts (1) RCC Drain- 680m (5 nos), (2) Construction of 4 nos RCC box culvert (3) Excavation & CC block lining (2 nos) under Amtali Pourashava; Upazilla- Amtali; District- Barguna 1.50 328.99 Tohidul Basar Kabir 311.08 08/07/2015 31/03/2018 100 239.00 76 04/04/2021  
17 Barguna 2 amtali 16 287 CTEIP/2014-15/AMT/CS-01 Contruction of 3 nos. Multipurpose Cyclone Shelters at (1) Amtali Bandar Hosainia Fajil Madrashaa ( Ward-04); (2) Suri kata Govt. primary School (Ward-07); and (3) Basugi Non-Govt, Primary School (Ward-08), under Amtali Pourashava, Upazila: Amtali, Distri 3.00 1265.15 Abul Kalam Azad 1399.66 05/06/2015 10/04/2018 100 1236.87 93 04/04/2021  
18 Barguna 2 amtali 16 287 e-GP/CTEIP/2014-15/AMT/RD-01 Improvement of existing 4 nos roads, totaling 3.38 kms and 01 no road side drain, totaling 0.481 kms under Amtali Pourashava, District: Barguna 3.38 371.68 M/S. Palli Store 283.05 01/10/2015 14/02/2018 100 283.05 100 04/04/2021 Completed
19 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2019-20/BAR/LP-01 Improvement of Circuit House Lake & Circuit House Field in ward no.02 500.00 0.00 0 04/04/2021 DED Complete
20 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2018-19/BAR/RD-06 Improvement of 06 nos Road under Barguna Pourashava 2.96 221.15 M/S FH Enterprise & M/S Islam & Co JV 0.00 27/01/2020 31/05/2020 98 205.00 93 04/04/2021 Works ongoing
21 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2018-19/BAR/RD-05 Improvement of 08 nos Road totalling-10.368km (2404m Rigid and 7964m Flexible Pavement) under Barguna Pourashava 8.54 594.24 Md. Moinul Islam (Partner in-charge) FHE & Mahfug Khan ltd (JV) 594.24 14/08/2019 14/08/2020 99 584.00 98 04/04/2021 Works ongoing
22 Barguna 2 barguna-s 18 287 e-Gp/CTEIP/2018-19/BAR/BT-01 Construction of Barguna Bus Terminal (2 -storied Terminal building with 3-storied Foundation.) 1437.01 Md. Mahfuz Khan 1434.19 25/03/2019 24/09/2020 98 1415.00 93 04/04/2021
23 Barguna 2 barguna-s 18 287 e-Gp/CTEIP/2018-19/BAR/MM-01 Construction of Barguna Multipurpose Market at Barguna Pourashava (2-Storied Building with 5- storied Foundation ) 504.82 Md. Mahfuz Khan 503.78 06/03/2019 05/09/2020 95 466.00 93 04/04/2021
24 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2017-18/BAR/PT-01 Construction of 01 no Public Toilet at Barguna Pourashava 1.00 35.31 M/S Khokon Traders 37.05 25/10/2018 100 37.04 100 04/04/2021 Completed
25 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2017-18/BAR/BLS-01 Construction of Barguna Poura Super Market Boat Landing Station under Barguna Pourashava 1.00 63.03 M/S Arif & Asif Construction and M/S FH Enterprise (JV) 63.03 09/09/2018 100 63.00 100 04/04/2021 Completed
26 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2017-18/BAR/RD-03 Construction/ Improvement of 03 nos Roads at Barguna Pourashava, District: Barguna 1.68 277.92 M/S Arif & Asif Construction and M/S FH Enterprise (JV) 249.57 06/06/2018 12/05/2019 100 224.02 90 04/04/2021  
27 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2017-18/BAR/WS-01 Construction of Two OHT, Pipeline 16.347 km (12.347 km Distribution line and 4.00 km Transmission Line) and 1000 nos water meter supply, fitting, fixing and commissioning of Electromechanical work at Barguna Pourashava, District: Barguna 16.35 1525.29 M/S Zilani Traders 1675.96 07/09/2018 01/08/2020 97 1686.00 96 04/04/2021  
28 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2017-18/BAR/IES-01 Construction of Integrated Landfill and Resource Recovery Facility at Barguna Pourashav, District: Barguna 1.00 921.87 TURN 942.13 07/08/2018 01/07/2020 97 907.00 87 04/04/2021  
29 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2016-17/BAR/DR-02 Construction of 8 nos RCC drain (5534m) under Barguna Pourashava, Upazila: Barguna sadar, District: Barguna 3.84 659.50 NT-AAC-NT JV 618.74 18/04/2017 17/10/2018 100 611.84 100 04/04/2021 Complete
30 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2015-16/BAR/DR-01 Re-excavation of 2 nos khal (2497m) and Rehabilitation of 2 nos khal (2660m) under Barguna Pourashava, Dist: Barguna 5.16 347.83 Md. Eunus Al Mamun 286.15 24/07/2016 28/11/2018 75 159.20 56 04/04/2021  
31 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2015-16/BAR/CS-01 Construction of Cyclone Shelter at (a) Barguna Maitha Secondary School 9ward no-3) and Barguna Ideal cCollege (ward no-6) under Barguna Pourashava, Dist: Barguna 2.00 734.87 M/S Rupali Constn. and amp SH Ent. (JV) 621.34 21/06/2016 07/03/2018 100 638.67 100 04/04/2021 Completed
32 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2016-17/BAR/BR-01 Construction of 1no RCC Bridge 22.0m and 2 nos RCC Box culvert in Barguna Pourashava, Dist: Barguna 22.00 279.86 PSTL-Maitree (pvt) 232.00 18/04/2017 17/04/2019 100 225.58 93 04/04/2021 Completed
33 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2016-17/BAR/RD-02 Improvement of Road with side drain from Krock khal near Krock Primary School to Nur Hera Madrasha (ward no-4) in Barguna Pourashava, Dist: Barguna 1.20 380.87 NT-AAC-NT JV 315.17 28/06/2017 27/06/2019 100 321.47 100 04/04/2021 Completed
34 Barguna 2 barguna-s 18 287 e-GP/CTEIP/2016-17/BAR/RD-01 Improvement of 5 nos Roads, including road side drain in Barguna Pourashava, Dist: Barguna 4.47 636.71 Md. Mahfuz Khan 533.24 13/02/2017 14/08/2018 100 547.92 100 04/04/2021 Completed
35 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2018-19/BHO/RD-05 Improvement/Rehabilitation of 3 nos road under Bhola Pourashava 7.13 602.60 0.00 0 04/04/2021 Bid under Evaluation-Review
36 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/BR-02 Construction / Improvement of Bridge under Bhola Pourashava, District: Bhola. 368.59 Md. Rashaduzzaman Peter 368.53 31/05/2019 24/05/2020 80 250.00 68 04/04/2021
37 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/RD-04 Improvement of one(1) No road totaling Length 1.125km with road side drain and 2 nos Box culvert under Bhola pourasava, District: Bhola. 0.99 517.26 M/S Prince Enterprise 542.60 21/10/2018 73 388.00 72 04/04/2021  
38 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/RD-03 Improvement of Five (05) Nos. Road Total Length 2111 m Rigid Pavement with 700 m drain, 11 nos Box Culvert and 178m Protection Work under Bhola Pourashava. 2.11 488.23 M/S Mollah Trading & Contacting Service 512.33 06/06/2018 12/05/2019 100 467.00 91 04/04/2021  
39 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/DR-08 Re-excavation of Bhola Khal Ch. 2600-4750m totalling 2150m with RCC Retaining Wall, Walkway and Bank Protection at Bhola Pourashava 2.15 1567.89 M/S AT-SA (JV) 1644.56 28/06/2018 80 1225.00 75 04/04/2021  
40 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/DR-07 Re-excavation of Bhola Khal Ch. 0-2600m totalling 2600m with RCC Retaining Wall and Bank Protection Works at Bhola Pourashava 2.60 1600.79 M/S AT-SA (JV) 1679.71 28/06/2018 27/06/2019 43 677.00 40 04/04/2021  
41 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/DR-06 Construction of 11 nos RCC Secondary Drain of Length 7.043 Km under Bhola Pourashava. 7.04 1386.05 M/S Prince & Azad JV 1413.21 04/02/2018 10/08/2019 96 1336.50 95 04/04/2021  
42 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/DR-04 Re-Excavation of 03 nos Khal Under Bhola Pourashava of Length: 7.058 Km. 7.06 827.62 Prince-Mamun JV 867.26 04/11/2018 04/10/2019 97 805.00 93 04/04/2021  
43 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2017-18/BHO/DR-05 Construction of 5 nos. RCC Secondary Drain Total Length 4.929 km under Bhola Pourashava, District: Bhola 4.93 991.36 M/S Asif Traders 990.26 23/01/2018 30/06/2019 92 902.62 91 04/04/2021  
44 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/DR-03 Construction of 06 (Six) nos RCC Drain (5592m) at Bhola Pourashava District: Bhola 5.59 1102.07 Md. Rashaduz-zaman Peter 1104.34 01/12/2016 30/11/2018 100 1104.34 100 04/04/2021 Completed
45 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2015-16/BHO/DR-02 Construction of 09 (Nine) nos RCC Drain (4893m) at Bhola Pourashava, District: Bhola 4.89 881.45 Eunus Al Mamun & Mollah Trading (JV) 923.76 24/11/2016 23/05/2018 100 927.99 100 04/04/2021 Completed
46 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/DR-01 Construction of 06 (Nine) nos RCC Drain (4749m) at Bhola Pourashava, District: Bhola 4.75 969.94 M/S Asif Traders 969.54 30/03/2017 30/09/2018 100 967.74 100 04/04/2021 Completed
47 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/CS-01 Construction of two multipurpose Cyclone Shelters at Bhola, District: Bhola 2.00 645.05 Md. Rashaduz-zaman Peter 687.91 23/01/2017 22/01/2019 100 687.89 100 04/04/2021 Completed
48 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/BR-01 Construction of 2 (Two) nos. Bridge (10m each) and 1 No. 2 vent Box Culvert at Bhola Pourashava; Upazila: Bhola Sadar; District: Bhola 28.05 221.61 M/S Eli Enterprise 234.88 08/06/2017 07/12/2018 100 244.89 100 04/04/2021 Completed
49 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/RD-02 Improvement of 3 (three) nos road totaling 3992m with road side drain totaling 496m at Bhola Pourashava 3.95 782.69 Md. Rashaduz-zaman Peter 828.45 26/04/2017 25/10/2018 100 826.32 100 04/04/2021 Completed
50 Bhola 4 bhola-s 4 287 e-GP/CTEIP/2016-17/BHO/RD-01 Construction Improvement of 10 (Ten) nos Road (5892m) at Bhola Pourashava District: Bhola 5.89 818.72 Md. Eunus Al Mamun 858.07 01/12/2016 31/05/2018 100 824.20 96 04/04/2021 Completed
51 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2017-18/DAU/MM-01 Construction of Multipurpose Super Market Under Daulatkhan Pourashava, District: Bhola. 316.72 Md. Rashaduzzaman Peter 345.60 23/04/2019 27/11/2020 96 332.00 96 04/04/2021
52 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2018-19/DAU/RD-03 Improvement of 02 nos Road Length - 1800.00 m flexible Pavement with 418m Road side drain ,233.00 m Protection work under Daulatkhan Pourashava. 1.80 274.89 Md. Farid Uddin 283.28 05/05/2019 05/11/2020 99 290.00 94 04/04/2021
53 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2017-18/DAU/BLS-01 Construction of Boat Landing Stations at Daulatkhan Pourashava, District: Bhola 1.00 56.30 M/S Fakhrul Islam 53.48 24/10/2018 100 47.00 88 04/04/2021  
54 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2017-18/DAU/RD-02 Construction / Improvement of 04 nos. road at Daulatkhan Pourashava, District: Bhola 1.91 302.97 Md. Farid Uddin 331.79 10/04/2018 04/04/2020 96 310.00 93 04/04/2021  
55 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2017-18/DAU/PT-01 Construction of Public Toilet at Daulatkhan Pourashava, District: Bhola 1.00 38.78 Md. Farid Uddin 39.76 08/09/2018 02/09/2020 100 39.75 100 04/04/2021 Completed
56 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2016-17/DAU/BR-01 Construction of Two nos. bridge total length 31m at Daulatkhan Pourashava, District- Bhola 27.00 236.41 M/S Nawal Construction 248.18 01/01/2018 30/06/2019 100 242.67 100 04/04/2021 Completed
57 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2016-17/DAU/DR-01 Construction of 13 nos RCC secondary drain of totaling 3.883 km at Daulatkhan Pourashava 3.88 705.39 M/S Nawal Construction 705.48 12/10/2017 11/10/2019 100 702.00 100 04/04/2021 Completed
58 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2016-17/DAU/RD-01 Improvement of Eight (08) nos Road totaling 5.817 km with 8 nos Box Culvert, Road side drain (687m), Cross drain (07 nos) & Protection work (1386.20) under Daulatkhan Pourashava, District- Bhola 5.82 867.65 M/S Nawal Construction 861.76 18/09/2017 17/09/2019 100 818.00 95 04/04/2021  
59 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2016-17/DAU/WS-01 Installation of Two production TW; One OHT, Pipeline (15.80 km Distribution line and 1822 Service Connection); One Pump House; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works at Daulatkhan Pourashava, Distri 15.80 976.41 ABM water company 878.77 26/05/2017 26/05/2019 100 877.00 100 04/04/2021 Completed
60 Bhola 4 daulatkhan 30 287 e-GP/CTEIP/2016-17/DAU/CS-01 Construction of Two Multipurpose Cyclone Shelters at (1) Shaheber Hat Madinatul Uloom Madrasha (ward-09) and (2) Hazipur Islamia Fazil Madrasha (ward-07) under Daulatkhan Pourashava, Upazila- Daultakhan, District: Bhola 2.00 761.30 M/S Nabarun Traders 798.60 26/02/2017 30/11/2018 100 798.19 100 04/04/2021 Completed
61 Bogura 51 bogura-s 348 287 e-GP/CTEIP/2018-19/BAR/RD-04 Improvement/Rehabilitation of 3 nos road 2.61 378.88 378.88 06/03/2019 05/09/2020 100 378.00 100 04/04/2021 GOB Funded
62 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2018-19/GAL/RD-04 Construction/ Improvement of 4 no. Road with 407m Road Side Drain under Galachipa Pourashava 1.98 459.39 M/S. Kohinoor Enterprise & Mizanur Alom (JV) 459.39 30/10/2019 30/10/2020 86 386.00 84 04/04/2021 Works Ongoing
63 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2017-18/GAL/BLS-01 Construction of 02 nos Boat Landing Station at Galachipa Ferry Ghat and Arrotpotti Ghat under Galachipa Pourashava, District: Patuakhali 2.00 214.51 M/S Palli Stors -M/S Gazi Construction (JV) 224.95 25/07/2018 80 144.09 77 04/04/2021  
64 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2017-18/GAL/MM-01 Construction of Multi Purpose Super Market Complex, Ward # 04, Galachipa Pourashava, District: Patuakhali 1.00 135.74 KE-MC JVCA 122.17 19/06/2018 100 121.65 100 04/04/2021 Completed
65 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2017-18/GAL/BR-01 Construction of 04 nos RCC Bridge at Galachipa Pourashava, District: Patuakhali 57.00 481.30 QC-PS-DCL (JV) 474.49 13/06/2018 98 397.04 84 04/04/2021  
66 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2017-18/GAL/RD/03 Improvement / Construction of Five (05) Nos Road Total length 3.89 Km with 246m Road side Drain, 08 Nos Box Culvert, 07 Nos Cross drain, 30 Nos RCC Sitting Bench & 445m Protection work under Galachipa Pourashava, Patuakhali. 3.89 492.62 M/S Palli Stores 427.05 15/03/2018 72 180.90 42 04/04/2021  
67 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2015-16/GAL/DR-01 Re excavation of 3 nos. Khal totaling 2.833 Km and Constructing of 4 nos. RCC drain, totaling 1.88 Km under Galachipa Pourashava, District: Patuakhali 4.71 371.08 MN Mallik-Monalisa Ltd (JV) 333.44 16/02/2016 02/12/2017 93 283.49 85 04/04/2021  
68 Patuakhali 1 galachipa 1 287 CTEIP/2014-15/GAL/CS-01 Construction of 3 nos. Multipurpose Cyclone Shelters at (1) Furfura Sharif Talimul Quran Madrasha (Ward-02); (2) Galachipa Degree College Compound (Ward-09); and (3) Sarshina Khanka Hafezia Madrasha (Ward-03), under Galachipa Pourashava, Upazila Galachipa 3.00 1171.69 MK-MF (JV) 1287.70 02/01/2015 31/12/2017 100 1248.00 100 04/04/2021 Completed
69 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2016-17/GAL/PT-01 Construction of 3 nos Public Toilets under Galachipa Pourashava, District: Patuakhali 3.00 74.89 M/S Siam Ent. 55.74 31/05/2017 30/11/2018 100 55.34 100 04/04/2021 Completed
70 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2014-15/GAL/WS-01 Construction of Two Production TW; One OHT, Pipeline (30 km Distribution and Transmission; 3.4 km Replaced Pipeline and 2500 Service Connection); Two Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical wo 33.50 1121.30 M/S. Zilani Traders 1244.22 14/01/2016 26/08/2018 100 1310.00 100 04/04/2021 Completed
71 Patuakhali 1 galachipa 1 287 e-GP/CTEIP/2014-15/GAL/RD-02 Improvement of 02 nos. Roads (1) Feeder road (Ward-07); and (2) Samudabad Road (Ward-06-08), totaling 1.195 km and 02 nos. Roadside Drains, totaling 0.923 km under Galachipa Pourashava, Upazila – Galachipa, District: Patuakhali 1.20 295.24 M.M. Enterprise 237.86 15/11/2015 30/04/2017 100 235.95 100 04/04/2021 Completed
72 Patuakhali 1 galachipa 1 287 CTEIP/2014-15/GAL/RD-01 Construction / Improvement of 5 roads; total length 6.555 km, under Galachipa Pourashava, Upazila Galachipa, District: Patuakhali 6.56 1035.12 M/S. S M Construction 911.33 03/02/2015 31/12/2016 100 911.33 100 04/04/2021 Completed
73 Patuakhali 1 kalapara 12 287 e-Gp/CTEIP/2018-19/KAL/RD-04 Improvement of Four (04) Nos. Road Total 1808 m Rigid and 834 m Flexible Pavement 2.64 374.65 M/S SH Enterprise- M/S Athai Enterprise 310.46 14/02/2019 13/08/2020 100 297.00 100 04/04/2021 WorkS Completed
74 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2017-18/KAL/BT-01 Construction of Bus terminal (Two storied Terminal Building with 3 storied foundation) at Kalapara Pourashava, District: Patuakhali 1.00 269.67 M/S Palli Stores 240.51 09/04/2018 03/03/2020 75 143.00 59 04/04/2021  
75 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2017-18/KAL/BLS-01 Construction of 01 no Boat Landing Stations with approach road at Kalapara Pourashava, District: Patuakhali 1.00 63.16 M/S Abul Kalam Azad 56.02 22/06/2018 100 50.00 100 04/04/2021 Completed
76 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2017-18/KAL/RD-03 Improvement of Three (03) Nos Road by rigid pavement totaling 0.870 Km with road Side drain at Kalapara Pourashava, District: Patuakhaii 0.87 211.35 M/S Palli Stores 198.29 15/05/2018 14/11/2019 68 96.33 49 04/04/2021  
77 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2017-18/KAL/PT-01 Construction of 02 nos Public Toilets at kalapara Pourashava, District: Patuakhali 2.00 64.62 M/S Palli Stores 54.72 22/06/2018 21/12/2019 78 29.00 54 04/04/2021  
78 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2016-17/KAL/WS-01 lnstallation of one Production TW, One OHT, Pipeline (23.30 km Distribution and Transmission , 5.76 km replaced Pipeline and 1800 Service Connection , 500 Replaced Service connection) One Pump House Supply of O & M tools and Supply, fitting, fixing and Co 28.60 1254.10 M/S Zilani Traders 1252.29 01/12/2016 31/05/2018 100 1187.92 100 04/04/2021 Completed
79 Patuakhali 1 kalapara 12 287 eGP/CTEIP/2016-17/KAL/DR/02 Construction of 7 Nos RCC Drain Totaling 1.503 km at Kalapara Pourashava, District: Patuakhali 1.50 199.76 RC-SHE-AK (JV) 164.54 24/03/2017 24/09/2018 100 164.50 100 04/04/2021 Completed
80 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2016-17/KAL/DR/01 Construction of 10 nos RCC drain at kalapara pourashava 3.78 728.08 Md. Eunus Al Mamun 628.77 16/02/2017 03/12/2018 100 621.00 100 04/04/2021  
81 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2015-16/KAL/CS-01 Construction of Two Multipurpose Cyclone Shelters at (1) Basonti Mondol Government Primary School (ward no-01) and (2) Badurtali Government Primary School (ward no-09) under Kalapara Pourashava 2.00 788.02 M/S. Palli Store 681.34 30/06/2016 10/09/2018 100 697.00 100 04/04/2021 Completed
82 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2016-17/KAL/BR-01 Construction of 03 vent Box culvert over Notun Bazar canal (Atimkhana) near Salam vendor office Mohallah (war no-02,04) and Construction of 03 vnet Box culvert over Nazrul Islam road near Mosque (ward n0-04,05) at Kalapara Pourashava 12.00 85.16 Md. Reaz Uddin 65.55 08/12/2016 07/12/2017 100 65.54 100 04/04/2021 Completed
83 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2016-17/KAL/RD-02 Improvement of 3 nos road totaling 8.438km at kalapara pourashava. 8.44 568.85 M/S. Rupali Construction & SHE (JV) 480.58 16/10/2017 26/03/2019 100 452.00 100 04/04/2021 Completed
84 Patuakhali 1 kalapara 12 287 e-GP/CTEIP/2016-17/KAL/RD-01 Improvement of 10 nos. Road, totaling 6.070 Kms, including 0.132 km road side drain at kalapara pourashava. 6.07 770.79 M/S. Palli Store 677.81 25/10/2016 13/08/2018 100 611.00 100 04/04/2021 Completed
85 Patuakhali 1 patuakhali-s 14 287 e-GP/CTEIP/2017-18/PAT/RD-04 Improvement of 04 nos Road under Patuakhali Pourashava 2.90 593.40 M/S Quashem Construction- M/S Palli Store (JV) 541.13 30/08/2018 03/01/2020 95 467.40 86 04/04/2021  
86 Patuakhali 1 patuakhali-s 14 287 e-GP/CTEIP/2017-18/PAT/CSR-01 Construction of Cyclone Shelter at Hazi Hamej Uddin Mridha College Under Ward 01 with Access Road namely Donavan School at 2 no. Bandh to Al- Amin Lillah Boarding at Sluice Gate via Hamej Uddin Mridha College. 1.00 554.49 M/S Abul Kalam Azad 581.07 07/05/2018 01/03/2020 94 486.00 84 04/04/2021  
87 Patuakhali 1 patuakhali-s 14 287 e-GP/CTEIP/2017-18/PAT/RD-02 Improvement of College Road from Patuakhali Govt. Mohila College to 02 no Sluice Gate (Bandh Ghat) via Patuakhali Govt. College by Rigid Pavement (Ward no 05, 02 & 04) under Patuakhali Pourashava 1.67 562.43 M/S Palli Store 581.84 23/04/2018 94 448.00 77 04/04/2021  
88 Patuakhali 1 patuakhali-s 14 287 e-GP/CTEIP/2017-18/PAT/RDR-01 Improvement of Three (03) Nos. Road Total 2258 m Rigid and 1727 m Flexible Pavement with 877 m drain, 02 Nos Cross drain ,16 nos Box Culvert and 74.4 m Protection Work under Patuakhali Pourashava. 3.99 803.02 DCL-MPS-MGC (JV) 867.33 18/06/2018 91 693.00 80 04/04/2021  
89 Patuakhali 1 patuakhali-s 14 287 e-GP/CTEIP/2016-17/PAT/RD-03 Improvement of 1 (one) no RCC road totaling 850m with 705m road side drain 04 nos cross drain 03 nos pipe cross drain and 68.20m C.C block at Patuakhali Pourashava, District: Patuakhali 0.85 355.81 M.M Builders & Engineers 319.50 25/05/2017 24/11/2018 92 208.00 65 04/04/2021  
90 Patuakhali 1 patuakhali-s 14 287 e-GP/CTEIP/2016-17/PAT/DR-01 Construction of 05 (Five) nos. RCC Drain totaling 3.549 kms. With 1.569 kms. foothpath, 02-nos box culvert and 04-nos RCC cross drain Under patuakhali Pourashava, District: Patuakhali under Coastal Towns Environmental Infrastructure Project. 3.57 728.92 Md Reaz Uddin JV 730.17 26/07/2017 25/07/2019 72 423.00 58 04/04/2021  
91 Pirojpur 3 mothbaria 37 287 e-Gp/CTEIP/2018-19/MAT/RD-03 Construction / Improvement of 4 nos road 3.66 409.10 TON (JV) 408.85 12/02/2019 12/08/2020 100 407.65 100 04/04/2021 WorkS Completed
92 Pirojpur 3 mothbaria 37 287 e-Gp/CTEIP/2018-19/MAT/MM-01 Construction of Multipurpose Market 1.00 920.97 Md. Mahfuz Khan, Md. Tahidul Basher Kabir, M/S Oishi Construction (JV) 920.69 12/02/2019 12/08/2020 98 887.00 96 04/04/2021
93 Pirojpur 3 mothbaria 37 287 e-GP/CTEIP/2017-18/MAT/BT-01 Construction of Bus Terminal at Mathbaria Pourashava, District: Pirojpur 1.00 80.37 M/S Oishi Construction 64.15 27/05/2018 27 14.91 23 04/04/2021  
94 Pirojpur 3 mothbaria 37 287 e-GP/CTEIP/2017-18/MAT/RD-02 Improvement of Roaad by Flexible Pavement from WAPDA Road to Betmor Khal Via Islambag with two Connecting Roads, Ward no-03, Mathbaria Pourashava, Dist: Pirojpur 1.65 257.38 M/S Oishi Construction 200.32 14/05/2018 100 192.03 96 04/04/2021  
95 Pirojpur 3 mothbaria 37 287 e-GP/CTEIP/2017-18/MAT/BLS-01 Construction of 1 No Boat Landing Station at Mathbaria Pourashava, District: Pirojpur 1.00 27.20 M/S Raj & Brothers 27.19 15/03/2018 100 27.04 100 04/04/2021 Completed
96 Pirojpur 3 mothbaria 37 287 e-GP/CTEIP/2017-18/MAT/WS-01 Construction, Installation and Commissioning of one 4.50 MLD capacity surface water treatment plant (SWTP), Two 500m3 capacity overhead water tanks, 54.2 Km pipeline networks, 3500 Service Connections and other structures of the system along with operatio 48.10 6047.89 Sinoconst-MT & S.S Consortium 5309.95 18/03/2018 97 4216.31 79 04/04/2021  
97 Pirojpur 3 mothbaria 37 287 e-GP/CTEIP/2016-17/MAT/PT-01 Construction of 4 Nos Public Toilets Mathbaria Pourashava, District: Pirojpur 4.00 116.99 M/S Palli Stores 105.07 12/06/2017 29/03/2019 100 104.50 100 04/04/2021 Completed
98 Pirojpur 3 mothbaria 37 287 e-GP/CTEIP/2016-17/MAT/DR-01 Construction of RCC drain 3693m at (9 nos) under Mathbaria Pourashava, District: Pirojpur 3.69 569.20 M/S BB-RT-JVCA 460.97 14/06/2017 31/03/2019 100 461.00 100 04/04/2021 Completed
99 Pirojpur 3 mothbaria 37 287 CTEIP/2014-15/MAT/CS-01 Construction of Multipurpose Cyclone Shelter at Momenia Dakhil madrasha (ward no: 1) Mathbaria Pourashava, Mathbaria, District: Pirojpur 1.00 310.55 M-Khan-STLI (JV) 324.29 22/02/2015 30/10/2017 100 324.28 100 04/04/2021 Completed
100 Pirojpur 3 mothbaria 37 287 CTEIP/2014-15/MAT/RD-01 Construction/Improvement of 4 nos roads including side drains totaling 3.741 kms in Mathbaria Pourashaba, Mathbaria, District: Pirojpur 3.74 727.34 TON (JV) 752.33 22/02/2015 21/02/2017 100 752.33 100 04/04/2021 Completed
101 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2018-19/PIR/RD-04 Construction / Improvement of 3 nos. road at Pirojpur Pourashava 3.88 468.00 468.00 04/02/2020 21/01/2021 97 389.00 83 04/04/2021
102 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2019-20/PIR/RD-05 Construction/ Improvement of 3 no. Road under Pirojpur Pourashava 3.45 325.89 0.00 0 04/04/2021 DED Complete
103 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2017-18/PIR/BLS-01 Construction of Boat Landing Station in Pirojpur Pourashava, Pirojpur. 2.00 105.52 M/S. Gazi Construction 110.80 08/04/2018 10/07/2019 98 79.00 71 04/04/2021  
104 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2017-18/PIR/MM-01 Construction of Multipurpose Super Market at Pirojpur Pourasava District: Pirojpur 1.00 596.33 Wahid Construction ltd 579.09 28/03/2018 98 523.00 90 04/04/2021  
105 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2014-15/PIR/CS-02 Construction of two nos Multipurpose cyclone Shelter (1) Moidho Namajpur Government Primary School(ward-6) and (2) Moidho Dumuritala Government Primary School(ward-9) under Pirojpur Pourashava 2.00 747.90 Mahfuz Khan 822.50 20/01/2016 09/04/2018 100 800.00 100 04/04/2021 Completed
106 Pirojpur 3 pirojpur-s 9 287 CTEIP/2014-15/PIR/CS-01 Construction of three nos Multipurpose cyclone Shelter (1) Adarshapara Secondary School(ward-05)(2) Khamkata Govt. Primary School (ward-08) and (3) Hularhut Dakil Madrasha (ward - 03) under pirojpur Pourashava Upazila: Pirojpur, Dist: Pirojpur 3.00 1064.17 EE-JI (JV) 1222.55 22/01/2015 15/01/2018 100 1179.85 100 04/04/2021 Completed
107 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2017-18/PIR/RD-03 Improvement of 4 nos road totaling 3.81 km with 5 nos box culvert at Pirojpur Pourashava, District: Pirojpur 5.10 531.79 PMPL-TTSL (JV) 558.26 23/11/2017 100 552.00 100 04/04/2021 Completed
108 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2017-18/PIR/IES-01 Construction of Integrated Landfill and Resource Recovery Facility at Pirojpur Pourashava, District: Pirojpur 1.00 815.09 TURN 851.08 07/01/2018 06/06/2020 98 768.00 88 04/04/2021  
109 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2016-17/PIR/PT-01 Construction of 1 no community toilet and 1 no public toilet at Pirojpur Pourashava, District: Pirojpur 2.00 49.03 M/S Saurav Construction 58.30 02/05/2017 20/01/2019 100 58.30 100 04/04/2021 Completed
110 Pirojpur 3 pirojpur-s 9 287 e-GP/CTEIP/2014-15/PIR/DR-01 Re-excavation of khal and Construction of RCC Drain & U-Drain (1) Re-excavation of khal ( Lenth: 14.994 km) (2) Construction of RCC Drain & U-Drain (Lenth: 4.14 km) (Total: 13 No), under Pirojpur Pourashava, District: Pirojpur. 19.14 1080.20 LA -TTSL ( JV) 1182.93 11/02/2016 07/02/2019 100 1163.00 100 04/04/2021  
111 Pirojpur 3 pirojpur-s 9 287 CTEIP/PIR/2015-16/RD-02 Improvement of 8 nos road (8.044 km), Construction of road side Drain 02 nos, (432 m)and Construction 0f 15 nos. RCC Box Culvert, in Pirojpur Pourashava. District: Pirojpur 7.74 902.59 M/S Mohiuddin Ahmed 950.85 01/03/2016 20/01/2019 100 946.50 100 04/04/2021 Completed
112 Pirojpur 3 pirojpur-s 9 287 CTEIP/PIR/2015-16/RD-01 Construction/Improvement of 8 Nos Roads totalling 13.533 kms including Bridge and Culvarts in Pirojpur Pourashava, District: Pirojpur 13.95 2104.34 Md. Mahfuz Khan-MMBELJV 2226.06 21/03/2016 13/02/2018 100 2161.72 100 04/04/2021