SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
|
1
|
Galachipa
|
|
1
|
e-GP/CTEIP/2017-18/GAL/BLS-01
|
Construction of 02 nos Boat Landing Station at Galachipa Ferry Ghat and Arrotpotti Ghat
under Galachipa Pourashava, District: Patuakhali
|
2.0000
|
214.513
|
M/S Palli Stors -M/S Gazi Construction (JV)
|
214.513
|
25/07/2018
|
20/03/2021
|
100
|
11/05/2022
|
|
|
2
|
e-GP/CTEIP/2017-18/GAL/MM-01
|
Construction of Multi Purpose Super Market Complex, Ward # 04, Galachipa Pourashava, District: Patuakhali
|
1.0000
|
135.744
|
KE-MC JVCA
|
135.744
|
19/06/2018
|
18/01/2020
|
100
|
11/05/2022
|
Completed
|
|
3
|
e-GP/CTEIP/2017-18/GAL/BR-01
|
Construction of 04 nos RCC Bridge at Galachipa Pourashava, District: Patuakhali
|
57.0000
|
481.301
|
QC-PS-DCL (JV)
|
481.301
|
13/06/2018
|
20/03/2021
|
100
|
11/05/2022
|
|
|
4
|
e-GP/CTEIP/2017-18/GAL/RD/03
|
Improvement / Construction of Five (05) Nos Road Total length 3.89 Km with 246m Road side Drain, 08 Nos Box Culvert, 07 Nos Cross drain, 30 Nos RCC Sitting Bench & 445m Protection work under Galachipa Pourashava, Patuakhali.
|
3.8900
|
492.616
|
M/S Palli Stores
|
492.616
|
15/03/2018
|
13/09/2019
|
91
|
11/05/2022
|
|
|
5
|
e-GP/CTEIP/2015-16/GAL/DR-01
|
Re excavation of 3 nos. Khal totaling 2.833 Km and Constructing of 4 nos. RCC drain, totaling 1.88 Km under Galachipa Pourashava, District: Patuakhali
|
4.7100
|
371.082
|
MN Mallik-Monalisa Ltd (JV)
|
371.082
|
16/02/2016
|
31/12/2021
|
100
|
11/05/2022
|
|
|
6
|
e-GP/CTEIP/2014-15/GAL/WS-01
|
Construction of Two Production TW; One OHT, Pipeline (30 km Distribution and Transmission; 3.4 km Replaced Pipeline and 2500 Service Connection); Two Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical wo
|
33.5000
|
1121.296
|
M/S. Zilani Traders
|
1121.296
|
14/01/2016
|
25/12/2020
|
100
|
11/05/2022
|
Completed
|
|
7
|
e-GP/CTEIP/2018-19/GAL/RD-04
|
Construction/ Improvement of 4 no. Road with 407m Road Side Drain under Galachipa Pourashava
|
1.9800
|
459.390
|
M/S. Kohinoor Enterprise & Mizanur Alom (JV)
|
459.390
|
30/10/2019
|
30/10/2020
|
100
|
09/05/2022
|
Works Ongoing
|
|
8
|
CTEIP/2014-15/GAL/CS-01
|
Construction of 3 nos. Multipurpose Cyclone Shelters at (1) Furfura Sharif Talimul Quran Madrasha (Ward-02); (2) Galachipa Degree College Compound (Ward-09); and (3) Sarshina Khanka Hafezia Madrasha (Ward-03), under Galachipa Pourashava, Upazila Galachipa
|
3.0000
|
1171.688
|
MK-MF (JV)
|
1171.688
|
02/01/2015
|
31/12/2017
|
100
|
04/04/2021
|
Completed
|
|
9
|
e-GP/CTEIP/2016-17/GAL/PT-01
|
Construction of 3 nos Public Toilets under Galachipa Pourashava, District: Patuakhali
|
3.0000
|
74.893
|
M/S Siam Ent.
|
74.893
|
31/05/2017
|
30/11/2018
|
100
|
04/04/2021
|
Completed
|
|
10
|
e-GP/CTEIP/2014-15/GAL/RD-02
|
Improvement of 02 nos. Roads (1) Feeder road (Ward-07); and (2) Samudabad Road (Ward-06-08), totaling 1.195 km and 02 nos. Roadside Drains, totaling 0.923 km under Galachipa Pourashava, Upazila – Galachipa, District: Patuakhali
|
1.1950
|
295.241
|
M.M. Enterprise
|
295.241
|
15/11/2015
|
30/04/2017
|
100
|
04/04/2021
|
Completed
|
|
11
|
CTEIP/2014-15/GAL/RD-01
|
Construction / Improvement of 5 roads; total length 6.555 km, under Galachipa Pourashava, Upazila Galachipa, District: Patuakhali
|
6.5550
|
1035.121
|
M/S. S M Construction
|
1035.121
|
03/02/2015
|
31/12/2016
|
100
|
04/04/2021
|
Completed
|
|
|
2
|
Kalapara
|
|
1
|
e-GP/CTEIP/2017-18/KAL/BT-01
|
Construction of Bus terminal (Two storied Terminal Building with 3 storied foundation) at Kalapara Pourashava, District: Patuakhali
|
1.0000
|
269.667
|
M/S Palli Stores
|
269.667
|
09/04/2018
|
30/10/2021
|
100
|
11/05/2022
|
|
|
2
|
e-GP/CTEIP/2017-18/KAL/BLS-01
|
Construction of 01 no Boat Landing Stations with approach road at Kalapara Pourashava, District: Patuakhali
|
1.0000
|
63.161
|
M/S Abul Kalam Azad
|
63.161
|
22/06/2018
|
21/12/2019
|
100
|
11/05/2022
|
Completed
|
|
3
|
e-GP/CTEIP/2017-18/KAL/RD-03
|
Improvement of Three (03) Nos Road by rigid
pavement totaling 0.870 Km with road Side drain at Kalapara Pourashava, District: Patuakhaii
|
0.8700
|
211.352
|
M/S Palli Stores
|
211.352
|
15/05/2018
|
30/10/2021
|
100
|
11/05/2022
|
|
|
4
|
e-GP/CTEIP/2016-17/KAL/WS-01
|
lnstallation of one Production TW, One OHT, Pipeline (23.30 km Distribution and Transmission , 5.76 km replaced Pipeline and 1800 Service Connection , 500 Replaced Service connection) One Pump House Supply of O & M tools and Supply, fitting, fixing and Co
|
28.6000
|
1254.104
|
M/S Zilani Traders
|
1254.104
|
01/12/2016
|
13/12/2020
|
100
|
11/05/2022
|
Completed
|
|
5
|
e-GP/CTEIP/2016-17/KAL/DR/01
|
Construction of 10 nos RCC drain at kalapara pourashava
|
3.7830
|
728.078
|
Md. Eunus Al Mamun
|
728.078
|
16/02/2017
|
30/09/2019
|
100
|
11/05/2022
|
|
|
6
|
e-GP/CTEIP/2016-17/KAL/RD-01
|
Improvement of 10 nos. Road, totaling 6.070 Kms, including 0.132 km road side drain at kalapara pourashava.
|
6.0700
|
770.794
|
M/S. Palli Store
|
770.794
|
25/10/2016
|
30/09/2019
|
100
|
11/05/2022
|
Completed
|
|
7
|
e-GP/CTEIP/2017-18/KAL/PT-01
|
Construction of 02 nos Public Toilets at kalapara Pourashava, District: Patuakhali
|
2.0000
|
64.618
|
M/S Palli Stores
|
64.618
|
22/06/2018
|
21/12/2019
|
100
|
09/05/2022
|
|
|
8
|
e-Gp/CTEIP/2018-19/KAL/RD-04
|
Improvement of Four (04) Nos. Road Total 1808 m Rigid and 834 m Flexible Pavement
|
2.6400
|
374.650
|
M/S SH Enterprise- M/S Athai Enterprise
|
374.650
|
14/02/2019
|
13/08/2020
|
100
|
04/04/2021
|
WorkS Completed
|
|
9
|
eGP/CTEIP/2016-17/KAL/DR/02
|
Construction of 7 Nos RCC Drain Totaling 1.503 km at Kalapara Pourashava, District: Patuakhali
|
1.5000
|
199.757
|
RC-SHE-AK (JV)
|
199.757
|
24/03/2017
|
24/09/2018
|
100
|
04/04/2021
|
Completed
|
|
10
|
e-GP/CTEIP/2015-16/KAL/CS-01
|
Construction of Two Multipurpose Cyclone Shelters at (1) Basonti Mondol Government Primary School (ward no-01) and (2) Badurtali Government Primary School (ward no-09) under Kalapara Pourashava
|
2.0000
|
788.021
|
M/S. Palli Store
|
788.021
|
30/06/2016
|
10/09/2018
|
100
|
04/04/2021
|
Completed
|
|
11
|
e-GP/CTEIP/2016-17/KAL/BR-01
|
Construction of 03 vent Box culvert over Notun Bazar canal (Atimkhana) near Salam vendor office Mohallah (war no-02,04) and Construction of 03 vnet Box culvert over Nazrul Islam road near Mosque (ward n0-04,05) at Kalapara Pourashava
|
12.0000
|
85.156
|
Md. Reaz Uddin
|
85.156
|
08/12/2016
|
07/12/2017
|
100
|
04/04/2021
|
Completed
|
|
12
|
e-GP/CTEIP/2016-17/KAL/RD-02
|
Improvement of 3 nos road totaling 8.438km at kalapara pourashava.
|
8.4380
|
568.854
|
M/S. Rupali Construction & SHE (JV)
|
568.854
|
16/10/2017
|
26/03/2019
|
100
|
04/04/2021
|
Completed
|
|
|
3
|
Patuakhali-s
|
|
1
|
e-GP/CTEIP/2021-22/PAT/RD-06
|
1) Construction of Road by placing Uniblock with Sidewalk from DFO Banjlow to Dc Banglow in Ward No.07, Total Length:290m+160m=450m 2) Construction of RCC Drain with Sidewalk and Cycle Lane from Circuit house to DC Banglow in Ward No.07, Total Length : 290m+160m=450m3) Widening of RCC Road and Cycle Lane from south side of DCBanglow to B-Type Bazar in Ward No.07,Total Length:450m 4) Construction oc RCC Darin with Sidewalk stating from B-Type Road to Sonali Bank turning in Ward No.08, Ch0.00-360m.Total Length 360m.
|
1.7100
|
971.000
|
|
971.000
|
26/12/2021
|
26/04/2022
|
36
|
18/05/2022
|
work Ongoing
|
|
2
|
e-GP/CTEIP/2017-18/PAT/RD-04
|
Improvement of 04 nos Road under Patuakhali Pourashava
|
2.9000
|
593.398
|
M/S Quashem Construction- M/S Palli Store (JV)
|
593.398
|
30/08/2018
|
01/03/2020
|
100
|
11/05/2022
|
|
|
3
|
e-GP/CTEIP/2017-18/PAT/CSR-01
|
Construction of Cyclone Shelter at Hazi Hamej Uddin Mridha College Under Ward 01 with Access Road namely Donavan School at 2 no. Bandh to Al- Amin Lillah Boarding at Sluice Gate via Hamej Uddin Mridha College.
|
1.0000
|
554.492
|
M/S Abul Kalam Azad
|
554.492
|
07/05/2018
|
03/01/2020
|
100
|
11/05/2022
|
|
|
4
|
e-GP/CTEIP/2017-18/PAT/RD-02
|
Improvement of College Road from Patuakhali Govt. Mohila College to 02 no Sluice Gate (Bandh Ghat) via Patuakhali Govt. College by Rigid Pavement (Ward no 05, 02 & 04) under Patuakhali Pourashava
|
1.6700
|
562.428
|
M/S Palli Store
|
562.428
|
23/04/2018
|
22/10/2019
|
96
|
11/05/2022
|
|
|
5
|
e-GP/CTEIP/2017-18/PAT/RDR-01
|
Improvement of Three (03) Nos. Road Total 2258 m Rigid and 1727 m Flexible Pavement with 877 m drain, 02 Nos Cross drain ,16 nos Box Culvert and 74.4 m Protection Work under Patuakhali Pourashava.
|
3.9900
|
803.023
|
DCL-MPS-MGC (JV)
|
803.023
|
18/06/2018
|
31/05/2021
|
100
|
11/05/2022
|
|
|
6
|
e-GP/CTEIP/2016-17/PAT/RD-03
|
Improvement of 1 (one) no RCC road totaling 850m with 705m road side drain 04 nos cross drain 03 nos pipe cross drain and 68.20m C.C block at Patuakhali Pourashava, District: Patuakhali
|
0.8500
|
355.808
|
M.M Builders & Engineers
|
355.808
|
25/05/2017
|
30/01/2020
|
100
|
11/05/2022
|
|
|
7
|
e-GP/CTEIP/2016-17/PAT/DR-01
|
Construction of 05 (Five) nos. RCC Drain totaling 3.549 kms. With 1.569 kms. foothpath, 02-nos box culvert and 04-nos RCC cross drain Under patuakhali Pourashava, District: Patuakhali under Coastal Towns Environmental Infrastructure Project.
|
3.5670
|
728.921
|
Md Reaz Uddin JV
|
728.921
|
26/07/2017
|
25/07/2019
|
100
|
09/05/2022
|
|
|
|
Total :
|
203.4180 (Km)
|
15800.17 (Lac)
|
15800.17 (Lac)
|
|
|
|
|
|
|
|