SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Chitalmari
1 W.391 Construction of sontoshpur UP Complex 85.260 85.260 30/04/2015 100 10/08/2020 final
2 Fakirhat
1 068/246 piljong uccp 59.000 59.000 28/04/2011 100 11/07/2020 final
3 Mollahat
1 w.211 Construction of kodalia UP Complex 85.400 85.400 30/12/2015 100 10/08/2020 final
4 Mongla
1 49/176 Construction of Mithakhali UP Complex 142.650 142.650 31/12/2018 100 31/08/2020 final
5 Morrelganj
1 w.259 Construction of putikhali UP Complex 114.460 114.460 01/03/2016 100 10/08/2020 final
2 w.373 Construction of cingrakhali UP Complex 117.220 117.220 29/12/2016 100 10/08/2020 final
6 Rampal
1 048/176 Construction of baintala UP Complex 126.690 126.690 30/07/2016 100 31/08/2020 final
2 w.028 Construction of rajnagar UP Complex 113.330 113.330 30/11/2016 100 10/08/2020 final
3 w.333 Construction of mollikerber UP Complex 126.690 126.690 30/08/2016 100 10/08/2020 final
4 w.074 Construction of gouramba UP Complex 112.780 112.780 30/12/2015 100 10/08/2020 final