Loading...

Project Scheme Detail List
SL No. Package No. Name Length (Km) Allotment (Lac) Name of Contractor Contract Amount (Lac) Date of Commencement Date of Completion Physical Progress (%) Date of Progress Update Remarks
1 Nawabganj-s
1 w.553 Construction of Islampur UP Complex 114.090 114.090 100 17/08/2020 FINAL
2 w.168 Construction of Sundorpur UP Complex 84.150 84.150 20/02/2014 100 17/08/2020 final
3 W.070 Construction of CHARONUPNAGAR UP Complex 89.970 89.970 23/11/2013 100 16/08/2020 FINAL
2 Shibganj
1 w.073 Construction of shahbajpur UP Complex 86.070 86.070 30/06/2014 100 17/08/2020 final
2 w.143 Construction of dhinagar UP Complex 87.620 87.620 17/11/2013 100 17/08/2020 final
3 W.018 Construction of 5 NO. Cakkirit UP Complex 87.410 87.410 06/07/2014 100 17/08/2020 final
Total : 0.0000 (Km) 549.31 (Lac) 549.31 (Lac)