Project Scheme Detail List
SL No.
Package No.
Name
Length (Km)
Allotment (Lac)
Name of Contractor
Contract Amount (Lac)
Date of Commencement
Date of Completion
Physical Progress (%)
Date of Progress Update
Remarks
1
Bogura-s
1
024/176
Construction of Fapore UP Complex
59.000
59.000
31/12/2015
100
01/09/2020
final
2
W.542
Construction of GOKUL UP Complex
116.500
116.500
30/06/2019
100
16/08/2020
FINAL
2
Dhunot
1
W-502
Construction of GOPALNAGAR UP Complex
105.480
105.480
31/12/2018
100
16/08/2020
FINAL
3
Dhupchancia
1
W502
Construction of GOBINDAPUR UP Complex
116.860
116.860
15/12/2019
90
16/08/2020
ONGOING
4
Kahaloo
1
W.291
Construction of KAHALU UP Complex
87.150
87.150
31/05/2014
100
16/08/2020
FINAL
2
027/246
Construction of muril up
59.000
59.000
20/12/2011
100
15/07/2020
ok
3
028/246
Construction of birkedar up
59.000
59.000
18/03/2020
100
15/07/2020
final
5
Nandigram
1
W.593
Construction of VATGRAM UP Complex
126.840
126.840
31/10/2019
95
16/08/2020
FINAL
6
Sariakandi
1
W-11
Construction of KAJLA UP Complex
125.040
125.040
31/05/2020
30
16/08/2020
ONGOING
2
W.543
Construction of HATSHERPUR UP Complex
119.980
119.980
24/01/2019
100
16/08/2020
FINAL
3
W.053
Construction of NAROCHI UP Complex
82.870
82.870
04/03/2014
100
16/08/2020
FINAL
4
026/246
Construction of chondonbaisa up
56.050
56.050
30/11/2011
100
15/07/2020
final
7
Shajahanpur
1
W.574
Construction of ARIA UP Complex
120.080
120.080
30/12/2019
90
16/08/2020
ONGOING
2
W-511
Construction of CHUPINAGAR UP Complex
106.310
106.310
30/12/2019
100
16/08/2020
ONGOING
3
025/246
Construction of khottapara up
46.960
46.960
05/12/2012
100
15/07/2020
ok
8
Sherpur
1
W.241
Construction of BISHLAPUR UP Complex
68.540
68.540
28/02/2014
100
16/08/2020
FINAL
9
Shibganj
1
024/246
Construction of mokamtola up
32.590
32.590
11/11/2007
0
15/07/2020
court case
10
Sonatala
1
023/176
Construction of Digdair UP Complex
59.000
59.000
03/02/2014
100
01/09/2020
revised & final
2
W-08
Construction of MODHUPUR UP Complex
153.150
153.150
30/05/2020
10
16/08/2020
ONGOING
Total :
0.0000 (Km)
1700.40 (Lac)
1700.40 (Lac)