SL No.
|
Package No.
|
Name
|
Length (Km)
|
Allotment (Lac)
|
Name of Contractor
|
Contract Amount (Lac)
|
Date of Commencement
|
Date of Completion
|
Physical Progress (%)
|
Date of Progress Update
|
Remarks
|
1
|
Anwara
|
1
|
RTIP-II/CTG/UZR-50.1
|
Hazrat Mohsin Awolia-Gahira-Fakirhat-Dhalghat
|
4.3000
|
934.962
|
MAQ Engineering Ltd.
|
934.962
|
22/08/2016
|
28/01/2018
|
11
|
23/12/2018
|
|
|
2
|
Banskhali
|
1
|
RTIP-II/CTG/RPM-343
|
Chunati bazar to Katharia and Bailchari u.p. office. (Bailchari-Chunati Rd.)
|
5.6000
|
271.811
|
M/S. Nipa Enterprise
|
271.811
|
03/04/2017
|
30/11/2018
|
100
|
23/12/2018
|
|
2
|
RTIP-II/CTG/RPM-184A
|
Banshkhali Chanua Kutubdia Rd (Bashkhali Chaonua Road) (Remaining Works)
|
6.2480
|
470.192
|
M/S. Nipa Enterprise
|
470.192
|
13/06/2017
|
30/01/2019
|
75
|
23/12/2018
|
|
3
|
RTIP-II/CTG/RPM-184
|
Banshkhali Chanua Kutubdia Rd (Bashkhali Chaonua Road)
|
4.0520
|
553.718
|
M/S. Rangamati Traders &M/S. Chakaria Development Society JV (RT-CDS(JV)
|
553.718
|
30/06/2015
|
30/06/2016
|
100
|
23/12/2018
|
Final (Contract cancelled for non-performance)
|
4
|
RTIP-II/CTG/UNR-5
|
b) Puichari UP to Khudukkhali bazar rd.(Prem bazar-Chanua Emb.)
|
3.3800
|
270.398
|
|
270.398
|
27/05/2015
|
30/01/2018
|
0
|
23/12/2018
|
|
|
3
|
Boalkhali
|
1
|
RTIP-II/CTG/RPM-405
|
Kalurghat-Charandwip-Bhandaljuri-Saraf Bhata-Gudamghar Road (From RHD #126)
|
8.2770
|
515.495
|
M/S. A. Ali Chowdhury
|
515.495
|
29/08/2017
|
30/11/2018
|
100
|
23/12/2018
|
|
2
|
RTIP-II/CTG/RPM-183
|
Kalachand Thakur Road.
|
5.3000
|
119.769
|
M/S. J.J Traders
|
119.769
|
09/06/2015
|
25/05/2016
|
100
|
23/12/2018
|
Final
|
3
|
RTIP-II/CTG/UZR-94-STR-41
|
Construction of 63m RCC Girder Bridge at ch. 14+600km on Kalurghat-Charandwip-Bhandaljuri-Saraf Bhata-Gudamghar Road
|
63.0000
|
294.013
|
Quashem Construction- Monir Ahmed (JV)
|
294.013
|
23/01/2017
|
30/04/2018
|
100
|
23/12/2018
|
|
4
|
RTIP-II/CTG/RPM-46
|
Bengura D.C
|
9.0500
|
160.479
|
M/S. Mithu Enterprise
|
160.479
|
27/05/2013
|
19/10/2014
|
100
|
23/12/2018
|
Final
|
5
|
RTIP-II/CTG/UZR-94
|
Kalurghat-Charandwip-Bhandaljuri-Saraf Bhata-Gudamghar Road (From RHD #126)
|
7.8850
|
2498.229
|
Kamal Associates
|
2498.229
|
25/01/2017
|
28/02/2019
|
77
|
23/12/2018
|
|
|
4
|
Chandanish
|
1
|
RTIP-II/CHI/RPM-154
|
Dewanhat-Bailtali-Barma-Patiya road
|
13.4900
|
476.057
|
JV of Mithu Enterprise & Mesba Associates [Mithu-Mesba (JV)]
|
476.057
|
23/04/2014
|
14/06/2015
|
100
|
23/12/2018
|
Final
|
|
5
|
Fatikchari
|
1
|
RTIP-II/CTG/RPM-344
|
Kazirhat G.C. to Garitana Bazar G.C.Road via Asia Tea Garden (Fatickchari portion)
|
8.5850
|
468.435
|
M.A.H. Construction Ltd
|
468.435
|
10/04/2017
|
30/04/2018
|
52
|
23/12/2018
|
|
2
|
RTIP-II/CTG/UNR-40-STR-32
|
Construction of 15m RCC Girder Bridge at Ch. 7+600 km on Bhujpur UP HQ to Mirzerhat Road via Sandip Para Road
|
75.0000
|
0.000
|
Consonance Engineers & Builders
|
0.000
|
31/01/2016
|
24/01/2018
|
100
|
23/12/2018
|
|
3
|
RTIP-II/CHI/RPM-150
|
Nazirhat to Kazirhat road (Ramgar Road Section-1)
|
16.0100
|
570.780
|
Mitu Enterprise & M/S. Mesba Associates (JV) [Mitu-Mesba (JV)]
|
570.780
|
25/06/2014
|
29/03/2016
|
100
|
23/12/2018
|
Final
|
4
|
RTIP-II/CTG/UNR-40
|
Bhujpur U.P. H.Q. to Mirzerhat Road via Sandip Para.
|
11.0500
|
1134.895
|
Taher Brothers Ltd
|
1134.895
|
14/09/2015
|
24/12/2017
|
100
|
23/12/2018
|
Final
|
5
|
RTIP-II/CTG/UZR-51.2
|
Katirhat GC to Azadi bazar (RHD) Road via Samitirhat Bazar (Fatickchari portion)
|
6.4000
|
1981.855
|
Orient Trading & Builders Ltd. And M/S. Monir Ahmed JV.
|
1981.855
|
03/04/2017
|
28/02/2018
|
50
|
23/12/2018
|
|
6
|
RTIP-II/CTG/UZR-51.1
|
Heako G.C. to Sikdarkhil Road
|
3.8100
|
504.588
|
M/S. M. R. Construction
|
504.588
|
27/01/2016
|
28/09/2017
|
100
|
23/12/2018
|
Final
|
|
6
|
Hathazari
|
1
|
RTIP-II/CTG/RPM-185
|
Azizia-Mozidia Road (Badamtoli & Gorduara Connecting Road)
|
12.0000
|
458.572
|
M/S. Yakub & Brothers
|
458.572
|
27/05/2015
|
05/06/2017
|
100
|
23/12/2018
|
Final
|
2
|
RTIP-II/CHI/RPM-153
|
Fateabad-Ramdash hat-Modunaghat road
|
10.1770
|
217.520
|
Mesba Associates
|
217.520
|
12/03/2014
|
24/05/2016
|
100
|
23/12/2018
|
Final
|
3
|
RTIP-II/CTG/UNR-5
|
c) Rowshan road (Mirzapur,Gumanmordon)
|
3.4720
|
807.112
|
|
807.112
|
27/05/2015
|
30/01/2018
|
0
|
23/12/2018
|
|
|
7
|
Lohagara
|
1
|
RTIP-II/CTG/RPM-342
|
Darbesh hat D.C Road (from RHD #128)
|
15.6480
|
955.194
|
M/S. Monjurul Alam Chowdhury & M/S. ARM Engineers [(MAC & ARM (JV)]
|
955.194
|
14/03/2017
|
03/12/2018
|
100
|
23/12/2018
|
|
2
|
RTIP-II/CTG/GCM-3
|
Improvement of Adhunagar Khan Hat GCM
|
1.0000
|
94.070
|
Mohammed Eunus & Brothers (Pvt.) Ltd
|
94.070
|
16/05/2015
|
15/03/2016
|
100
|
23/12/2018
|
Final
|
3
|
RTIP-II/CTG/UZR-5
|
Chunati Pantrisha via Narischa Chandah Patialpara road
|
9.0000
|
2182.300
|
Rana Builders (Pv t) Ltd & M/S. Quashem Construction (RBL-QC JV)
|
2182.300
|
10/09/2015
|
30/06/2018
|
100
|
23/12/2018
|
|
|
8
|
Mirsharai
|
1
|
RTIP-II/CTG/RPM-186
|
Barayear Hat - Santir Hat-Abur Hat G.C Road
|
11.5500
|
548.659
|
M/S. Rangamati Traders, M/S. Nipa Enterprise & M/S. Quashem Construction ( RT-KC-NE JV)
|
548.659
|
14/06/2015
|
07/08/2016
|
100
|
23/12/2018
|
Final
|
2
|
RTIP-II/CTG/GCM-48
|
Improvement of Hadi Fakirhat GCM
|
1.0000
|
117.407
|
M/S. Anma Traders
|
117.407
|
12/06/2017
|
28/03/2018
|
70
|
23/12/2018
|
|
3
|
RTIP-II/CTG/UZR-50.2
|
Bhorer Hat-Sitakunda Mirer Hat G.C. Road
|
4.0200
|
548.690
|
M/S. Mostafa & Sons & The New Trade Link JV, (MS-TNTL JV)
|
548.690
|
07/02/2016
|
15/03/2018
|
99
|
23/12/2018
|
|
|
9
|
Patiya
|
1
|
RTIP-II/CHI/RPM-152
|
b) Dewan hat-Bailtali-Barama-Patiya road (Patiya part) (From RHD #127)
|
8.8930
|
325.623
|
|
325.623
|
13/07/2015
|
10/03/2017
|
100
|
23/12/2018
|
|
2
|
RTIP-II/CTG/UZR-4
|
Uzirpur Road
|
6.0800
|
1083.432
|
Yakub Brothers-A.Ali Chowdhury (JV)
|
1083.432
|
03/12/2015
|
30/06/2018
|
99
|
23/12/2018
|
|
|
10
|
Rangunia
|
1
|
RTIP-II/CHI/RPM-152
|
a) Ramgotirhat-Santirhat-Pomra road (From RHD #102)
|
6.9000
|
202.961
|
Joint Venture of M/S. Rangamati Traders, M/S. Quashem Construction & M/S. Nipa Enterprise (RT-KC-NE JV)
|
202.961
|
13/07/2015
|
10/03/2017
|
100
|
23/12/2018
|
Final
|
2
|
RTIP-II/CTG/RPM-49.2
|
Parua D. C. Rd. (From RHD # 99)
|
7.1300
|
160.505
|
Omar Faruque and Saleha JVCA
|
160.505
|
28/08/2014
|
05/11/2015
|
100
|
23/12/2018
|
Final
|
3
|
RTIP-II/CTG/RPM-49.1
|
Parua D. C. Rd. (From RHD # 99)
|
7.0000
|
148.174
|
Omar Faruque & Saleha JVCA
|
148.174
|
01/12/2013
|
30/11/2014
|
100
|
23/12/2018
|
Final
|
4
|
RTIP-II/CTG/UZR-3A
|
Kalurghat-Sarandeep-Banderjari-Sharafvatta Rd (Rangunia Part) (From RHD # 96)
|
6.4350
|
642.816
|
Dolly Construction Ltd.
|
642.816
|
25/01/2018
|
25/04/2018
|
50
|
23/12/2018
|
|
5
|
RTIP-II/CTG/UZR-3
|
Kalurghat-Sarandeep-Banderjari-Sharafvatta Rd (Rangunia Part) (From RHD # 96)
|
|
1395.307
|
M/S. M.R. Construction (JV)
|
1395.307
|
20/05/2015
|
22/06/2017
|
100
|
23/12/2018
|
Final. Partially work done. Therefore contract cancelled.
|
|
11
|
Raojan
|
1
|
RTIP-II/CTG/RPM-187
|
a) Dost Mohammed Road. UZ (H/ Q) to Amir Hat.
|
6.5000
|
275.099
|
M/S. Monir Ahmed & M/S. Chowdhury Enterprise JV, (MA-CE JV)
|
275.099
|
03/09/2015
|
30/01/2018
|
100
|
23/12/2018
|
|
2
|
RTIP-II/CTG/GCM-18
|
Improvement of Gourisanker hat GCM
|
1.0000
|
99.038
|
M/S. Anma Traders
|
99.038
|
03/09/2015
|
15/11/2016
|
100
|
23/12/2018
|
Final
|
3
|
RTIP-II/CHI/RPM-126
|
Raozan Noapara Sec-2 (Ramjan Ali Hat to Noapara Patherhat) road
|
10.0000
|
323.469
|
M/S. Yakub & Brothers
|
323.469
|
12/03/2014
|
30/12/2015
|
100
|
23/12/2018
|
Final
|
|
12
|
Satkania
|
1
|
RTIP-II/CTG/RPM-280
|
Charati-Khoderhat-Moulavir Dokan-Bazalia-Bomang Hat-Noyahat Road (From RHD #129)
|
16.6800
|
1126.982
|
Mohammed Eunus & Brothers (Pvt.) Ltd
|
1126.982
|
12/12/2016
|
25/12/2018
|
98
|
23/12/2018
|
|
|
13
|
Sitakunda
|
1
|
RTIP-II/CTG/RPM-187
|
b) Komaldaha Komar Ali Road (Bhuiyer Hat Forest Office) (From RHD #105)
|
7.1340
|
273.361
|
|
273.361
|
03/09/2015
|
30/01/2018
|
100
|
23/12/2018
|
|
2
|
RTIP-II/CTG/UNR-5
|
a) Abdus Sattar Road
|
1.2850
|
124.975
|
Mohammed Eunus & Brothers (Pvt.) Ltd.
|
124.975
|
27/05/2015
|
30/01/2018
|
0
|
23/12/2018
|
|
|